IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE MONTVILLE-WHIPPANY 230KV TRANSMISSION PROJECT IS REASONABLY NECESSARY FOR THE SERVICE, CONVENIENCE OR WELFARE OF THE PUBLIC (NEW JERSEY BOARD OF PUBLIC UTILITIES)

CourtNew Jersey Superior Court Appellate Division
DecidedNovember 1, 2019
DocketA-2183-17T3
StatusUnpublished

This text of IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE MONTVILLE-WHIPPANY 230KV TRANSMISSION PROJECT IS REASONABLY NECESSARY FOR THE SERVICE, CONVENIENCE OR WELFARE OF THE PUBLIC (NEW JERSEY BOARD OF PUBLIC UTILITIES) (IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE MONTVILLE-WHIPPANY 230KV TRANSMISSION PROJECT IS REASONABLY NECESSARY FOR THE SERVICE, CONVENIENCE OR WELFARE OF THE PUBLIC (NEW JERSEY BOARD OF PUBLIC UTILITIES)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE MONTVILLE-WHIPPANY 230KV TRANSMISSION PROJECT IS REASONABLY NECESSARY FOR THE SERVICE, CONVENIENCE OR WELFARE OF THE PUBLIC (NEW JERSEY BOARD OF PUBLIC UTILITIES), (N.J. Ct. App. 2019).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-2183-17T3

IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE MONTVILLE-WHIPPANY 230 KV TRANSMISSION PROJECT IS REASONABLY NECESSARY FOR THE SERVICE, CONVENIENCE OR WELFARE OF THE PUBLIC. ___________________________________

Submitted October 3, 2019 – Decided November 1, 2019

Before Judges Nugent and DeAlmeida.

On appeal from the New Jersey Board of Public Utilities, Docket No. EO15030383.

Weiner Law Group LLP, attorneys for appellant Montville Township Board of Education (Stephen J. Edelstein, of counsel and on the brief; Aimee S. Weiner, on the brief).

Cozen O'Connor, PC, attorneys for respondent Jersey Central Power & Light Company (Gregory Eisenstark, on the brief). Gurbir S. Grewal, Attorney General, attorney for respondent New Jersey Board of Public Utilities (Jason W. Rockwell, Assistant Attorney General, of counsel; Andrew M. Kuntz, Deputy Attorney General, on the brief).

PER CURIAM

Appellant Montville Township Board of Education (BOE) challenges the

November 21, 2017 final order of respondent New Jersey Board of Public

Utilities (BPU) granting the petition of respondent Jersey Central Power & Light

Company (JCP&L) to construct a transmission line project not subject to the

Municipal Land Use Law (MLUL), N.J.S.A. 40:55D-1 to -163, or any other

governmental ordinances or regulations, permits, or license requirements made

under the authority of the MLUL. We affirm.

I.

The following facts are derived from the record. JCP&L is a public utility

in the business of purchasing, distributing, transporting, and selling electricity

to approximately 1.1 million customers in New Jersey. It is subject to BPU's

regulatory supervision and control. See N.J.S.A. 48:2-13(a).

JCP&L filed a petition with the BPU pursuant to N.J.S.A. 40:55D-19

seeking approval to construct a seven-mile long 230 kV transmission line

between its substations in East Hanover Township and Montville Township (the

A-2183-17T3 2 Project). The transmission line will be constructed in thirteen segments, mostly

along existing transmission lines in JCP&L's existing right of way (ROW). The

Project also includes upgrades to the two substations. The petition required BPU

to determine whether the Project is reasonably necessary for the service,

convenience, or welfare of the public and is, therefore, not subject to zoning and

land use ordinances, or other government regulations enacted pursuant to the

MLUL.

BPU transferred the petition to the Office of Administrative Law for a

hearing. BOE thereafter intervened. 1 An Administrative Law Judge (ALJ) held

a three-day evidentiary hearing at which JCP&L presented live and pre-filed

testimony describing the need for the new transmission line.

The ALJ found that PJM Interconnection, LLC (PJM), a regional

transmission organization, was approved by the Federal Energy Regulatory

Commission to plan the region's electricity transmission grid. PJM ensures

transmission owners, including JCP&L, comply with North American Electric

Reliability Corporation (NERC) reliability standards.

1 Montville Township also intervened, but resolved its objections to the Project through a stipulation with JCP&L altering the Project's route. A-2183-17T3 3 PJM's responsibilities include identifying violations of NERC's reliability

criteria. There are three categories of conditions used to assess criteria

violations: (1) Category A examines whether a system functions properly and

can meet customer demand needs under normal operating conditions; (2)

Category B examines system function when there is a loss of any single

generating unit, transmission line, transformer, circuit breaker, capacitor, or

single pole of a bi-polar transmission line; and (3) Category C examines system

functionality when there are events resulting in the loss of any Category B

element followed by the loss of a second element in the transmission system.

In 2012, PJM identified a Category C reliability violation in JCP&L's bulk

electric system resulting from the hypothetical outage of the Montville-Roseland

230 kV line followed by the loss of either the Kittatinny-Newton 230 kV line or

the Newton-Montville 230 kV line. This scenario would result in an interruption

in service affecting approximately 86,719 JCP&L customers and violate PJM's

planning criteria. A failure of this magnitude also could result in significant

financial penalties for JCP&L. PJM determined the Project, if constructed,

would address the criteria violation.

JCP&L presented testimony detailing its consideration of alternative

routes and methods to address the criteria violation. The utility considered

A-2183-17T3 4 constructing a 115 kV transmission line, but rejected that option because its

substations were not designed to support an additional 115 kV circuit, and an

additional 115 kV line would not provide a satisfactory level of resilience.

JCP&L also considered placing a 230 kV transmission line underground. The

utility rejected this option because the underground transmission line would: (1)

create several environmental issues related to wetlands and other sensitive areas;

(2) multiply the costs of the Project by four to ten times; (3) increase the

magnetic field exposure at ground level because the transmission line would be

closer to the surface; and (4) increase repair time of the transmission line.

JCP&L also performed a routing study that considered three alternative

routes. One of the alternatives had two alternate segments. The routing study

concluded the proposed route was superior because it is the shortest, minimizes

the overall effect of the Project on the natural and human environment, avoids

unreasonable costs and special design requirements, and best complies with the

BPU's requirement concerning the use of existing ROWs because eighty-nine

percent of the route parallels or rebuilds existing transmission lines.

JCP&L presented two expert witnesses to discuss the effects of electric

and magnetic fields (EMF), audible noise, and radio noise associated with the

A-2183-17T3 5 Project. The experts concluded the EMF exposure when the Project is operating

would be well below State and international exposure limits.

At the hearing, BOE's President testified. She was not qualified as an

expert witness in any field. She explained BOE takes issue with segment 10 of

the Project, which calls for the construction of a transmission line adjacent to

one of BOE's schools, the Robert R. Lazar Middle School. The new

transmission line would be carried on new 110-foot-tall monopoles constructed

next to existing transmission lines in an existing JCP&L ROW abutting the

property on which the school is located. The new monopoles will be seventy

feet from the edge of the ROW and approximately 175 feet closer to the school

than the existing transmission lines. Some of the trees that presently serve as a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borough of Roselle v. Public Service Electric & Gas Co.
173 A.2d 233 (Supreme Court of New Jersey, 1961)
Mayflower Securities Co. v. Bureau of Securities
312 A.2d 497 (Supreme Court of New Jersey, 1973)
Olivieri v. Y.M.F. Carpet, Inc.
897 A.2d 1003 (Supreme Court of New Jersey, 2006)
In Re Carter
924 A.2d 525 (Supreme Court of New Jersey, 2007)
Henry v. Rahway State Prison
410 A.2d 686 (Supreme Court of New Jersey, 1980)
Matter of Estate of Dawson
641 A.2d 1026 (Supreme Court of New Jersey, 1994)
Tarus v. Borough of Pine Hill
916 A.2d 1036 (Supreme Court of New Jersey, 2007)
Elizabethtown Water Co. v. New Jersey Board of Public Utilities
527 A.2d 354 (Supreme Court of New Jersey, 1987)
Sacharow v. Sacharow
826 A.2d 710 (Supreme Court of New Jersey, 2003)
Zirger v. General Accident Insurance
676 A.2d 1065 (Supreme Court of New Jersey, 1996)
In Re Pub. Ser. Elec. & Gas Co.
771 A.2d 1163 (Supreme Court of New Jersey, 2001)
In Re Petition of Jersey Central Power & Light Co.
428 A.2d 498 (Supreme Court of New Jersey, 1981)
Velasquez v. Franz
589 A.2d 143 (Supreme Court of New Jersey, 1991)
Culver v. Insurance Co. of North America
559 A.2d 400 (Supreme Court of New Jersey, 1989)
Charlie Brown of Chatham, Inc. v. BOARD OF ADJUSTMENT FOR TOWNSHIP OF CHATHAM
495 A.2d 119 (New Jersey Superior Court App Division, 1985)
O'Brien v. Telcordia Technologies
20 A.3d 1154 (New Jersey Superior Court App Division, 2011)
State v. K.P.S. and State v. Carmini Laloo
112 A.3d 579 (Supreme Court of New Jersey, 2015)
State v. Jamil McKinney(073070)
126 A.3d 1200 (Supreme Court of New Jersey, 2015)
Adelman v. BSI Fin. Servs., Inc.
179 A.3d 431 (New Jersey Superior Court App Division, 2018)
In re Stallworth
26 A.3d 1059 (Supreme Court of New Jersey, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE MONTVILLE-WHIPPANY 230KV TRANSMISSION PROJECT IS REASONABLY NECESSARY FOR THE SERVICE, CONVENIENCE OR WELFARE OF THE PUBLIC (NEW JERSEY BOARD OF PUBLIC UTILITIES), Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-the-petition-of-jersey-central-power-light-company-njsuperctappdiv-2019.