In the Matter of the Joint Application of Missouri-American Water Company and DCM Land, LLC, for a Variance from the Company's Tariff Provisions Regarding the Extension of Company Mains v. Office of Public Counsel

Supreme Court of Missouri·Decided August 15, 2023·No. SC99978·Published

Opinion

SUPREME COURT OF MISSOURI en banc

IN THE MATTER OF THE JOINT ) Opinion issued August 15, 2023 APPLICATION OF MISSOURI- ) AMERICAN WATER COMPANY AND ) DCM LAND, LLC, FOR A VARIANCE ) FROM THE COMPANY'S TARIFF ) PROVISIONS REGARDING THE ) EXTENSION OF COMPANY MAINS, )

)

Respondent, )

)

v. ) No. SC99978 )

OFFICE OF PUBLIC COUNSEL, )

)

Appellant. )

APPEAL FROM THE MISSOURI PUBLIC SERVICE COMMISSION The Office of the Public Counsel ("Public Counsel") appeals the order of the Public Service Commission ("the Commission"), granting the joint application of Missouri- American Water Company ("Water Company") and DCM Land, LLC, ("DCM") for variances from Water Company's tariff, absent explicit language in the tariff that allows for variances. Public Counsel raises three points on appeal: (1) the Commission erred in granting the variances because the Commission does not have legal authority to grant the variance requests; (2) even if the Commission had the legal authority to grant the requested

variances, the Commission did not establish "good cause" to approve a variance; and (3) the Commission's decision was unduly discriminatory. The Commission's order is reversed, and the case is remanded with directions for the Commission to enter an order in accordance with this opinion.

Facts and Procedural History DCM, a developer, is building the Cottleville Trails subdivision ("the Development") in St. Charles County, Missouri, in the service area of Water Company and Public Water Supply District No. 2 of St. Charles County ("Water District No. 2"). Due to a territorial agreement between Water Company and Water District No. 2, the Development is in Water Company's exclusive territory. Water Company is a "water corporation" and "public utility" as defined in § 386.020. 1 The services provided by Water Company are subject to a tariff,2 which is approved by the Commission. The Development is located in the "St. Louis Metro District" for purposes of Water Company's tariff.

Water Company and DCM submitted a joint application with the Commission seeking three variances from Rule 23 in Water Company's tariff, which governs the funding of water main extensions. The requested variances, together, would effectively increase Water Company's responsibility and decrease DCM's responsibility for the cost of a water main extension.

1 All statutory references are to RSMo 2016 unless indicated otherwise. 2 A tariff is "a document published by a public utility, and approved by the [C]ommission, that sets forth the services offered by that utility and the rates, terms, and conditions for the use of those services." 20 C.S.R. 4240-3.010(28).

The first requested variance was from the language of Rule 23A.2, which states, in pertinent part:

The Company will be responsible for all main extensions where the cost of the extension does not exceed four (4) times the estimated average annual revenue from the new Applicant(s) whose service pipe(s) will immediately be connected directly to the extension and from whom the Company has received application(s) for service upon forms provided by the Company for this purpose. New Applicants shall be those who commit to purchase water service for at least one year, and guarantee to the Company that they will take water service at their premises within one hundred twenty (120) days after the date the Company accepts the main and determines it ready for Customer Service[.]

(Emphasis added). Specifically, Water Company and DCM wanted a variance from the emphasized language above to increase the 120-day deadline to five years for new applicants.

Next, Water Company and DCM requested variances from the language of Rules 23.A.39 and 23.C.6, which describe how water main extensions were to be funded. The Rules state, in pertinent part:

[Rule 23A.3] If the estimated cost of the proposed extension required in order to furnish general water service exceeds four (4) times the Company’s estimate of average annual revenue from the new Applicant, the Applicant and Company shall fund the remaining cost (i.e., total cost less four (4) times the estimated average annual revenue from any new Applicant(s)) of the proposed water main extension at a ratio of 95:5 (i.e., 95% Applicant funded and 5% Company funded) for St. Louis Metro District, and 86:14 (i.e., 86% Applicant funded and 14% Company funded) for all other districts.

....

[Rule 23.C.6] Upon completion of the Main Extension, and prior to acceptance of the extension by the Company, the Applicant will provide to the Company a final statement of Applicant’s costs to construct such extension. The final statement of costs will be added to the actual costs for

Company to provide services as per the Developer Lay Proposal. Upon acceptance of the main extension, the Company will then issue payment to the Applicant of five percent (5%) (for St. Louis Metro District contracts)

and fourteen percent (14%) (for all other district contracts) of the total, final costs that exceed four (4) times the estimated average annual revenue pursuant to Provision A.2 and 3, above. . . .

(Emphasis added). Specifically, DCM and Water Company requested variances that would make them subject to the 86:14 funding ratio applicable to all districts other than St. Louis, as opposed to the 95:5 funding ratio applicable pursuant to the tariff.

DCM and Water Company submitted their joint application for the variances to the Commission pursuant to 20 C.S.R. 4240-2.060(4)(B), which requires that an application for a variance must include, among other requirements, "[t]he reasons for the proposed variance or waiver and a complete justification setting out the good cause for granting the variance or waiver[.]" DCM and Water Company listed several reasons to support their assertion "good cause" existed. 3 The staff of the Commission filed a recommendation for the Commission to deny the requested variances from Rules 23.A.39 and 23.C.6, stating the Commission lacked

3 The joint application first stated there was "good cause" for the variances because "the build-out of a development of such magnitude may not reasonably be expected to occur in 120 days, but is reasonably anticipated to occur over a 5-year period." Next, the application stated:

[B]ut for the territorial agreement filed between [Water District No. 2] and [Water Company] . . . for which DCM Land and its predecessors in interest received no notice, Cottleville Trails could be served by [Water District No. 2] and DCM Land would not be required to construct the water system in the development at its cost and contribute it to [Water Company] without a reasonable opportunity to recover the cost thereof[.]

Finally, the application asserted that if the variances were not granted, DCM would be required "to pay significantly higher development costs, and/or the home buyers in the Cottleville Trails subdivision to pay higher costs for their homes, than would result if water service were provided" by Water District No. 2.

authority to grant tariff variances and the funding-ratio variance would be unduly discriminatory. Water Company and DCM filed responses, stating the improvements DCM would make through the variances would also constitute good cause because planned main replacement "would improve fire protection in the area and provide water main access to several additional properties nearby."

The Commission granted the three requested variances to the tariff, finding good cause existed. Public Counsel then filed an application for rehearing, which the Commission granted. After the rehearing, the Commission issued a revised order, once again granting the three requested variances. Within the revised order, the Commission determined it had the statutory authority to grant a tariff variance and that good cause existed to do so. Public Counsel sought transfer after opinion by the court of appeals. This Court granted transfer and has jurisdiction. Mo. Const. art. V, § 10.

Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

In the Matter of the Joint Application of Missouri-American Water Company and DCM Land, LLC, for a Variance from the Company's Tariff Provisions Regarding the Extension of Company Mains v. Office of Public Counsel, (Mo. 2023).

In the Matter of the Joint Application of Missouri-American Water Company and DCM Land, LLC, for a Variance from the Company's Tariff Provisions Regarding the Extension of Company Mains v. Office of Public Counsel (In the Matter of the Joint Application of Missouri-American Water Company and DCM Land, LLC, for a Variance from the Company's Tariff Provisions Regarding the Extension of Company Mains v. Office of Public Counsel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State Ex Rel. St. Louis County Gas Co. v. Public Service Commission
286 S.W. 84 (Supreme Court of Missouri, 1926)