In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its West Service Territory Missouri Public Service Commission v. The Office of Public Counsel Spire Missouri Inc.

Missouri Court of Appeals·Decided November 19, 2019·No. WD82302, WD82373·Published

Opinion

In the

Missouri Court of Appeals Western District

IN THE MATTER OF THE  APPLICATION OF SPIRE MISSOURI  INC TO CHANGE ITS  INFRASTRUCTURE SYSTEM REPLACEMENT SURCHARGE IN ITS  SPIRE MISSOURI EAST SERVICE  TERRITORY; IN THE MATTER OF  THE APPLICATION OF SPIRE  WD82302 MISSOURI INC TO CHANGE ITS  CONSOL. WITH: INFRASTRUCTURE SYSTEM  WD82373 REPLACEMENT SURCHARGE IN ITS  WEST SERVICE TERRITORY;  OPINION FILED: MISSOURI PUBLIC SERVICE  COMMISSION,  NOVEMBER 19, 2019 Respondent,  

v.  

THE OFFICE OF PUBLIC COUNSEL,  Appellant;

SPIRE MISSOURI INC.,  Appellant.  

Appeal from Public Service Commission

Before Division Two: Thomas H. Newton, Presiding Judge, Anthony Rex Gabbert, Judge, Thomas N. Chapman, Judge

The Office of Public Counsel and Spire Missouri, Inc. appeal the Report and Order of the Public Service Commission of the State of Missouri. In three points on appeal, Spire Missouri, Inc. claims the Public Service Commission erred in disallowing $4,100,000 in Infrastructure System Replacement Surcharges. In one point on appeal, the Office of Public Counsel claims the Public Service Commission erred in allowing Spire to collect costs it incurred to replace cast iron and bare steel mains and service lines. The Commission’s Report and Order is reversed and the case is remanded.

Facts1

The Public Service Commission of the State of Missouri (“PSC”) is a state administrative agency that regulates public utilities. §§ 386.040; 386.250.2 Spire Missouri, Inc. (“Spire”)3 is an investor-owned gas utility providing retail gas service to large portions of Missouri through its two operating units or divisions, Spire Missouri East and Spire Missouri West. Spire is a “gas corporation” and a “public utility” as defined in section 386.020. The Office of Public Counsel (“OPC”) may represent and protect the interests of the public in any proceeding before or appeal from the PSC.

On June 7, 2018, Spire filed an application and petitions with the PSC to change its Infrastructure System Replacement Surcharges (“ISRS”) in its East and West service territories. Spire requested an adjustment to its ISRS rate schedules to recover costs incurred in connection with infrastructure system replacements made during the period that ran from October 1, 2017 through April 30, 2018, with pro forma ISRS costs updated through June 30, 2018. The PSC

1 Much of the recitation of facts is taken directly from the PSC’s Report and Order without further attribution. 2 All statutory references are to RSMo 2016 unless otherwise indicated. 3 In 2017, Spire stopped doing business under the name of Laclede Gas Co, and changed its name to Spire.

issued notice of the applications and provided an opportunity for interested persons to intervene. No intervention requests were submitted.

On August 6, 2018, the Staff of the PSC (“Staff”) filed its reports proposing a number of corrections and adjustment’s to Spire’s calculations. Staff recommended that the PSC reject the original tariff sheets and approve ISRS adjustments for Spire based on Staff’s determination of the appropriate amount of ISRS revenues. Staff later provided corrections and information for the updated months of May and June 2018.

On August 16, 2018, Spire filed a motion objecting to Staff’s recommendations and requesting an evidentiary hearing. The OPC filed a motion to dismiss Spire’s applications. The PSC held an evidentiary hearing on August 27, 2018.

The PSC found the following in its Report and Order: The last general rate cases applicable to Spire were decided by the PSC by order issued on March 17, 2018, with new rates effective April 19, 2018. As part of those general rate cases, Spire’s existing ISRS were reset to zero. The ISRS filings at issue in this case are Spire’s first ISRS filings since the last general rate case.

Sections 393.1009 through 393.1015 permit gas corporations to recover certain infrastructure system replacements costs outside of a formal rate case through a surcharge on its customers’ bills. Historically, Spire has used a piecemeal approach to pipe replacement by replacing pipes when they were failing or about to fail. In 2010, Spire changed to what it contends is a more systematic and economical approach where it retires pipes in place and installs new plastic pipes often in a different location. The new location is more accessible and more efficient to maintain than the location of old pipes which were often under streets.

Spire’s current neighborhood replacement program replaces or retires in place and no longer uses cast iron, steel, and plastic pipes. Most of the cast iron pipes being replaced are over

a hundred years old. Cast iron pipes are unsafe to use because they undergo a process called graphitization in which the iron leeches out making the pipe subject to cracking and leaking. The steel pipe being replaced is bare and not cathodically-protected so those pipes corrode relatively quickly and need to be replaced.

Some of the plastic pipes that Spire replaced or retired in place are not worn out or in a deteriorated condition. Spire did not conduct a review to determine if that plastic pipe was worn out or deteriorated before replacing it. The polyethylene plastic pipe that Spire uses should last indefinitely. Spire’s work order authorization sheets did not explain if a main or service line being replaced was worn out or deteriorated. Spire did not provide sufficient information for Staff to determine whether any plastic pipe being replaced was incidental to and required to be replaced in conjunction with the replacement of other worn out or deteriorated components. Spire has not attempted to calculate the amount of plastic pipe replaced that was worn out or in a deteriorated condition. Some of Spire’s blanket work order involved replacing or repairing plastic pipes that were not worn out or deteriorated.

In Matter of Application of Laclede Gas Co. to Change Its Infrastructure Sys. Replacement Surcharge in Its Missouri Gas Energy Serv. Territory v. Office of Pub. Counsel, 539 S.W.3d 835 (Mo. App. W.D. 2017) (“2016 ISRS Case”), this court reversed the PSC’s order that the plastic pipe was an integral component of the worn out and deteriorated cast iron and steel pipe and that the cost could be recovered through an increase to the existing ISRS surcharges. Based on the opinion in the 2016 ISRS Case, Staff developed a methodology to remove the cost of the replacement of ineligible plastic mains and service lines from Spire’s ISRS cost recovery.

The PSC found in its Report and Order that Staff witnesses provided credible testimony on the correct methodology for determining the cost of ineligible plastic pipe replacements and that

Staff’s evidence on this issue was the best evidence presented at the hearing. Staff made appropriate adjustments to Spire’s ISRS request based on the plastic pipe replaced and calculated a revised ISRS revenue requirements (“Adjusted ISRS”). The Adjusted ISRS recommended by Staff resulted in Spire collecting ISRS revenues in the amount of $2,607,610 for its East service territory and $5,411,793 for its West service territory.

These appeals by Spire and OPC follow. Spire seeks an additional $4,100,000 in ISRS revenues. OPC maintains the matter should be remanded with instructions to remove from the ISRS revenue awarded the cost incurred to replace cast iron and bare steel mains and service lines.

Standard of Review

“The Commission’s Order will be affirmed if it is lawful and reasonable.” Id. at 837. “The Commission’s Order is lawful if it is authorized by statute, and our review of this issue is de novo.” Id. at 838. “The Commission’s Order is reasonable if it is supported by substantial, competent evidence on the whole record; the decision is not arbitrary or capricious; [and] where the [Commission] has not abused its discretion.” Id. (internal quotation marks omitted). “The party appealing bears the burden of proving that the Commission’s Order is unlawful or unreasonable.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its West Service Territory Missouri Public Service Commission v. The Office of Public Counsel Spire Missouri Inc., (Mo. Ct. App. 2019).

In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its West Service Territory Missouri Public Service Commission v. The Office of Public Counsel Spire Missouri Inc. (In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri Inc. to Change its Infrastructure System Replacement Surcharge in its West Service Territory Missouri Public Service Commission v. The Office of Public Counsel Spire Missouri Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Laclede Gas Co. v. Office of Pub. Counsel
539 S.W.3d 835 (Missouri Court of Appeals, 2017)