In the Matter of the Application of North Dakota Pipeline Company LLC for a Certificate of Need for the Sandpiper Pipeline Project in Minnesota. In the Matter of the Application of North Dakota Pipeline Company LLC for a Pipeline Routing Permit for the Sandpiper Pipeline Project in Minnesota.

Court of Appeals of Minnesota·Decided September 14, 2015·No. A15-16·Published

Opinion

STATE OF MINNESOTA

IN COURT OF APPEALS

A15-0016

In the Matter of the Application of North Dakota Pipeline Company LLC for a Certificate of Need for the Sandpiper Pipeline Project in Minnesota.

In the Matter of the Application of North Dakota Pipeline Company LLC for a Pipeline Routing Permit for the Sandpiper Pipeline Project in Minnesota.

Filed September 14, 2015

Reversed and remanded

Klaphake, Judge*

Public Utilities Commission File No. PL-6668/CN-13-473, PL-6668/PPL-13-474

Leigh K. Currie, Kathryn M. Hoffman, Minnesota Center for Environmental Advocacy, St. Paul, Minnesota (for relator Friends of the Headwaters)

Lori Swanson, Attorney General, Alethea M. Huyser, Leah M. P. Hedman, Max Kieley, Assistant Attorneys General, St. Paul, Minnesota (for respondent Minnesota Public Utilities Commission)

Richard D. Snyder, John E. Drawz, Patrick D.J. Mahlberg, Fredrikson & Byron, P.A., Minneapolis, Minnesota (for respondent North Dakota Pipeline Company LLC)

Gerald W. Von Korff, Rinke Noonan, St. Cloud, Minnesota (for amicus curie Carlton County Land Stewards)

Considered and decided by Rodenberg, Presiding Judge; Cleary, Chief Judge; and Klaphake, Judge.

*

Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10.

SYLLABUS

When certificate of need proceedings precede routing permit proceedings for a large oil pipeline, the Minnesota Environmental Policy Act requires that an environmental impact statement be completed before a final decision is made on the certificate of need.

OPINION

KLAPHAKE, Judge Relator argues that conducting certificate of need proceedings for a large oil pipeline prior to the completion of an environmental impact statement violates the Minnesota Environmental Policy Act (MEPA). All parties agree that the pipeline is subject to environmental review under MEPA, but this review is set to occur during the routing permit proceedings after a certificate of need has been granted. Because the decision to grant a certificate of need for a large oil pipeline constitutes a major governmental action that has the potential to cause significant environmental effects, we conclude that MEPA requires an environmental impact statement to be completed before a final decision is made to grant or deny a certificate of need. Accordingly, we reverse and remand for respondent Minnesota Public Utilities Commission (MPUC) to reconsider whether to issue a certificate of need after an environmental impact statement has been completed.

FACTS

Relator Friends of the Headwaters (FOH) challenges the MPUC’s order to proceed with a final decision on a certificate of need for a large oil pipeline, arguing that to do so without preparing the required environmental analysis will violate the MEPA.

In November 2013, intervenor North Dakota Pipeline Company LLC (NDPC)

filed applications for a certificate of need and a pipeline routing permit with the MPUC to construct a 612-mile pipeline to transport crude oil from Tioga, North Dakota to terminals in Clearbrook, Minnesota and Superior, Wisconsin. Approximately 300 miles of the proposed pipeline would cross northern Minnesota carrying between 225,000 and 375,000 barrels of oil per day.

In February 2014, the MPUC accepted the applications as substantially complete and referred both matters to the Minnesota Office of Administrative Hearings for joint contested case proceedings on the certificate of need and routing permit. The MPUC also directed the Energy Environmental Review and Analysis unit (EERA) of the Minnesota Department of Commerce to facilitate the development of alternative route proposals to those proposed by NDPC.

In March, EERA held seven public meetings in six counties along the proposed pipeline route. More than 1,000 comments were submitted by 940 commenters and organizations in response to the notice for comments. After reviewing these extensive comments, EERA identified 62 alternative project proposals for consideration as part of the ongoing proceedings. In identifying these proposals EERA made a distinction between proposed route and system alternatives. Consistent with previous MPUC

dockets, “route” alternatives were defined “as a deviation from the [NDPC’s] proposed route to address a concern or issue and met the stated purpose and need of the proposed project with no apparent major engineering or environmental issues.” In contrast, a “system” alternative represented “a pipeline route that is generally separate or independent of the pipeline route proposed by [NDPC], and that does not connect to the specified Project endpoints (the North Dakota border to Clearbrook and Clearbrook to Superior, Wisconsin).” EERA designated 8 of the identified proposals as system alternatives and 54 as route alternatives.

After additional comments and a public hearing, the MPUC accepted 53 of the route alternatives and one of the system alternatives for consideration in the routing permit contested case hearing. Around the same time, many organizations and agencies raised concerns about conducting the certificate of need and routing permit proceedings jointly based on the complexity of the issues facing the parties and the MPUC.

In September, the MPUC held a public hearing on the issue of bifurcating the proceedings and staying the routing permit proceedings pending completion of the certificate of need proceedings. At the hearing, the Minnesota Pollution Control Agency (MPCA) and the Minnesota Department of Natural Resources (DNR), as well as EERA recommended bifurcating the proceedings, with the certificate of need proceedings occurring first. These parties also urged the MPUC to forward the remaining system alternatives for consideration during the certificate of need proceedings. FOH and Amicus Carlton County Land Stewards supported bifurcating the proceedings, but also argued that MEPA required the MPUC to prepare an environmental impact statement

(EIS) evaluating both route and system alternatives prior to making a final decision in the certificate of need proceedings. NDPC opposed both the proposed bifurcation of proceedings and further consideration of the remaining system alternatives as part of the certificate of need process. NDPC also argued that preparation of an EIS at the certificate of need stage in bifurcated proceedings would be unnecessary and inappropriate, because a MEPA-compliant environmental review was already required as part of the routing permit proceedings.

In October, the MPUC ordered that the certificate of need and routing permit proceedings be bifurcated, with the certificate of need proceedings to be completed first. The MPUC also determined that six of the remaining system alternatives should be evaluated as part of the certificate of need proceedings, while the 53 route alternatives and one system alternative would still be reviewed during the routing permit proceedings. Finally, the MPUC directed EERA to conduct a “high-level” environmental review of the six system alternatives to be considered during the certificate of need proceedings. While the MPUC concluded that such a review would assist in developing the record, it acknowledged that this environmental review would “not be equivalent in terms of the specificity and level of detail to a comparative environmental analysis undertaken in the route permit proceeding.” FOH petitioned for reconsideration, which the MPUC denied. This certiorari appeal follows.

ISSUES

Does MEPA require the completion of an environmental impact statement before the MPUC makes a final decision on a certificate of need for a large oil pipeline?

ANALYSIS

This court will affirm an administrative agency’s decision unless its findings, inferences, conclusions or decisions are:

(a) in violation of constitutional provisions; or (b) in excess of the statutory authority or jurisdiction of the agency; or

Free access — add to your briefcase to read the full text and ask questions with AI

In the Matter of the Application of North Dakota Pipeline Company LLC for a Certificate of Need for the Sandpiper Pipeline Project in Minnesota. In the Matter of the Application of North Dakota Pipeline Company LLC for a Pipeline Routing Permit for the Sandpiper Pipeline Project in Minnesota., (Mich. Ct. App. 2015).

In the Matter of the Application of North Dakota Pipeline Company LLC for a Certificate of Need for the Sandpiper Pipeline Project in Minnesota. In the Matter of the Application of North Dakota Pipeline Company LLC for a Pipeline Routing Permit for the Sandpiper Pipeline Project in Minnesota. (In the Matter of the Application of North Dakota Pipeline Company LLC for a Certificate of Need for the Sandpiper Pipeline Project in Minnesota. In the Matter of the Application of North Dakota Pipeline Company LLC for a Pipeline Routing Permit for the Sandpiper Pipeline Project in Minnesota.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related