In the Matter of Petition of Montana-Dakota Utilities Co.

2007 SD 104, 740 N.W.2d 873, 2007 S.D. LEXIS 172, 2007 WL 3036815
CourtSouth Dakota Supreme Court
DecidedOctober 17, 2007
Docket24448
StatusPublished
Cited by3 cases

This text of 2007 SD 104 (In the Matter of Petition of Montana-Dakota Utilities Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In the Matter of Petition of Montana-Dakota Utilities Co., 2007 SD 104, 740 N.W.2d 873, 2007 S.D. LEXIS 172, 2007 WL 3036815 (S.D. 2007).

Opinion

KONENKAMP, Justice.

[¶ 1.] The question we address in this administrative appeal is whether an electric utility may petition to provide service outside its statutorily assigned service territory to a “large load” customer in another utility’s assigned service area. We conclude that SDCL 49-34A-56 allows only customers to petition for an outside provider. Thus, we affirm the Public Utilities Commission’s ruling that an outside provider lacked standing to bring a petition under the statute.

Background

[¶ 2.] The Public Utilities Commission (PUC) regulates which utility provides a customer with service. SDCL Chapter 49-34A. Under SDCL 49-34A-42, the Legislature allotted each utility an exclusive right to provide service to all new and existing customers within its assigned territory. 1 North Central Farmers Elevator decided to build a new facility in Bow-dle, South Dakota. Montana-Dakota Utilities Company (MDU) and FEM Electric Association (FEM) both furnish power to customers in the vicinity, but FEM is statutorily assigned to provide power in the territory where the Bowdle facility would be built. North Central entered into discussions with both MDU and FEM to decide whether it would receive service from the incumbent provider, FEM, or seek permission from the PUC to use the outside provider, MDU. Ultimately, North Central executed a service agreement with FEM.

[¶ 3.] Disappointed with FEM’s choice, MDU brought a petition under SDCL 49-34A-56 seeking to have the PUC assign MDU as the provider for power to the Bowdle . facility. Despite the fact that FEM had exclusivity in serving the new facility, MDU asserted in its petition that “regardless of customer preference, MDU is the best suited to provide electric service to North Central under a service contract pursuant to the criteria established by SDCL 49-34A-56[.]” In particular, MDU averred that the Bowdle facility is a large load customer and MDU “is fully able to provide the electrical service requirements of the load to be served.” It also alleged that it had an adequate power supply available and would expend fewer dollars than FEM to provide service. According to MDU, it would need only one half mile of additional line, while FEM’s line would have to extend for four miles.

[¶ 4.] FEM, North Central, and the South Dakota Rural Electric Association successfully petitioned to intervene. North Central asserted that MDU’s petition was improperly brought because, among other things, it was North Central’s preference that FEM provide service. Correlatively, FEM argued that the new Bowdle facility is within its exclusive territory, and it was willing and able to furnish *876 adequate services, and therefore, it should be the provider.

[¶ 5.] FEM moved for summary disposition, alleging that MDU did not have standing to bring a petition under SDCL 49-34A-56. The PUC granted summary disposition concluding that (1) because the Bowdle facility would be located in FEM’s service territory, FEM had the exclusive right to provide service; and (2) MDU is not a customer, and therefore, it did not have standing under SDCL 49-34A-56 to bring a petition. The circuit court upheld the PUC’s decision. MDU now appeals to this Court. The question hinges purely on statutory interpretation: did the Legislature intend to open the competition between utilities for “large load” customers, or did it intend to grant exclusive territories for utilities except when customers seek an outside provider.

Standard of Review

[¶ 6.] We review agency decisions the same as the circuit court; there is no presumption that the circuit court’s decision was correct. U.S. West Communications, Inc. v. Public Util. Comm’n, 505 N.W.2d 115, 122-23 (S.D.1993) (citing Northwestern Bell v. Public Util. Comm’n, 467 N.W.2d 468, 469 (S.D.1991)). Neither do we defer “to the interpretation of the trial court, nor to the agency’s conclusions of law.” Id. Questions of statutory interpretation are reviewed de novo. Aspen Storage, Inc. v. Flanagan, 2007 SD 66, ¶ 9, 737 N.W.2d 277, 280 (citing Town Square Ltd. P’ship v. Clay County Bd. of Equalization, 2005 SD 99, ¶ 9 n. 1, 704 N.W.2d 896, 899 n. 1 (citing Fall River County v. S.D. Dep’t of Rev., 1999 SD 139, ¶15, 601 N.W.2d 816, 821 (citations omitted))).

Analysis and Decision

[¶ 7.] In 1975,- our Legislature adopted the “South Dakota Territorial Act.” This Act gave the PUC the power to establish zones in which utilities would be assigned exclusively to provide service to all new and existing customers in their respective territories. In the case of In the Matter of Establishing Certain Territorial Elec. Boundaries (Mitchell Area), 281 N.W.2d 65, 70 (S.D.1979), we acknowledged that the Act was adopted to avoid duplication of facilities and wasteful spending. Although the Act gave, utilities exclusive service areas, it also established limited exceptions whereby a customer might obtain service from an alternative provider. SDCL 49-34A-58; SDCL 49-34A-55; SDCL 49-34A-56. 2 See also In the Matter of Northwestern Public Service Co. (Hub City), 1997 SD 35, ¶ 16, 560 N.W.2d 925, 928. The exception implicated in this ease is found in SDCL 49-34A-56. It provides:

Notwithstanding the establishment of assigned service areas for electric utilities provided for in §§ 49-34A-43 and 49-34A-44, new customers at new locations which develop after March 21, 1975, ... and who require electric service with a contracted minimum demand of two thousand kilowatts or more shall not be obligated to take electric service from the electric utility having the assigned service area where the customer is located if, after notice and hearing, .the Public Utilities Commission so determines after consideration of the following factors:
*877 (1) The electric service requirements of the load to be served;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leonard v. State Ex Rel. South Dakota Real Estate Commission
2010 S.D. 97 (South Dakota Supreme Court, 2010)
Heinemeyer v. Heartland Consumers Power District
2008 SD 110 (South Dakota Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 SD 104, 740 N.W.2d 873, 2007 S.D. LEXIS 172, 2007 WL 3036815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-petition-of-montana-dakota-utilities-co-sd-2007.