IN THE MATTER OF DENIAL OF CEDAR KNOLLS 2006 LLC'S HAZARDOUS DISCHARGE SITE REMEDIATION, ETC. (NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION)

New Jersey Superior Court Appellate Division·Decided December 5, 2018·No. A-3151-17T1·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-3151-17T1

IN THE MATTER OF DENIAL OF CEDAR KNOLLS 2006 LLC'S HAZARDOUS DISCHARGE SITE REMEDIATION FUND INNOCENT PARTY GRANT APPLICATION WITH REGARD TO REIMBURSEMENT OF REMEDIAL ACTION COSTS.

Argued October 22, 2018 – Decided December 5, 2018 Before Judges Sabatino, Sumners and Mitterhoff.

On appeal from the New Jersey Department of Environmental Protection.

Jeffrey W. Cappola argued the cause for appellant Cedar Knolls 2006 LLC (Wilentz, Goldman & Spitzer, PA, attorneys; Gordon J. Golum, of counsel; Jeffrey W.

Cappola and Yin Zhou, on the brief).

Mark S. Heinzelmann, Deputy Attorney General, argued the cause for respondent Department of Environmental Protection (Gurbir S. Grewal, Attorney General, attorney; Melissa H. Raksa, Assistant Attorney General, of counsel; Mark S. Heinzelmann, on the brief).

PER CURIAM

Cedar Knolls 2006, LLC appeals from the May 1, 2018 final agency decision of the New Jersey Department of Environmental Protection (DEP) denying its request for payment of future remedial costs under the former innocent party grant program through the Brownfield and Contaminated Site Remediation Act (Brownfield Act), N.J.S.A. 58:10B-1 to -31. We affirm.

This matter returns to us following our September 20, 2017 decision reversing the November 2, 2015 final agency decision of the DEP that Cedar Knolls did not qualify as a "person" under N.J.S.A. 58:10B-6(a)(4) to submit an innocent party grant to pay for the remediation of contaminated property that Cedar Knolls owns. Cedar Knolls 2006, LLC v. NJDEP, No. A-1405-15 (App. Div. Sept. 20, 2017). On the day of our ruling, Cedar Knolls reached out to the agency to reactivate its previously denied grant request. Over the next three months, the DEP reviewed Cedar Knolls' invoices and other documents submitted to support the company's grant request.

On December 26, 2017, the DEP informed Cedar Knolls that its application was approved with recommended funding of $97,837.78 for past remedial costs, and "[fifty percent] of eligible costs related to future work may be added to the total recommendation amount." (emphasis added). The DEP requested that Cedar Knolls "[k]indly forward a Scope of Work and Cost A-3151-17T1

Estimate to [them] for [the] proposed work." Two days later, Cedar Knolls provided the DEP with documentation for the estimated costs of future work totaling $2,159,466.38.

On January 9, 2018, the DEP issued a letter to Cedar Knolls stating it "received notice of the Appellate [Division's September 20, 2017] decision to reverse the [DEP's] November 2, 2015 denial" of Cedar Knolls' application and, therefore, "revisited the Innocent Party Grant . . . request that was submitted . . . ," and offered the company the original $97,837.78 in grant funds for incurred costs, but made no mention of future remedial costs.

On January 16, the Legislature passed Assembly Bill 1954 L. 2017, c. 353 (the amendment) into law, which among other things, eliminated the innocent party grant program on the day of passage. The amendment stated:

This act shall take effect immediately and shall apply to any application for financial assistance or a grant from the [innocent party grant program] pending before [the DEP] on the effective date of this act, or submitted on or after the effective date of the act, but shall not apply to any application determined to be technically eligible and recommended for funding by [the DEP]

and pending before the New Jersey Economic Development Authority [(EDA)] on the effective date of this act.

[L. 2017, c. 353 § 6. (emphasis added).]

A-3151-17T1

Almost a month later on February 20, the Attorney General's Office, on behalf of the DEP, sent an e-mail to Cedar Knolls' counsel acknowledging receipt of the company's documents – forwarded to the agency on December 28 – supporting future remedial action, but advising that "the descriptions and total sums for the [future] work were administratively incomplete . . . [and] required significantly more detail on the specific tasks to be performed, rather than general statements and lump sums." As an example, the DEP indicated that the mass excavation work portion of Cedar Knolls' request "should have been broken down into tasks and sub-tasks, which would then outline the specific cost and time (days/hours) associated with personnel (contractor and sub-contractor), labor, equipment, materials, etc.," to indicate how the total amount was being calculated. The email stated further that, in light of the amendment and because the future remedial work was requested with the application for past work, the DEP "elected to review and approve the application for the [past] work and present it to the EDA on an expedited basis" in lieu of denying the entire application. At the same time, the DEP determined the application for future remedial costs was denied as incomplete; the first time Cedar Knolls was made aware its documentation for future remedial costs was deficient.

A-3151-17T1

On May 1, Cedar Knolls was formally notified of the agency's decision denying its request for future remedial costs.1 In this appeal, Cedar Knolls contends that its application was grandfathered under the amendment to the Brownfield Act, and thus, DEP's denial of its future remedial funding request was arbitrary, capricious, and unreasonable. In the alternative, Cedar Knolls asserts that, due to equitable considerations, the amendment should not be applied prospectively to deny its request.

To address Cedar Knolls' grandfather clause contention, we must examine the DEP's interpretation and application of the amendment. It is well settled that we "afford substantial deference to an agency's interpretation of a statute that the agency is charged with enforcing." Richardson v. Bd. of Trs., Police & Firemen's Ret. Sys., 192 N.J. 189, 196 (2007). Nevertheless, "we are 'in no way bound by the agency's interpretation of a statute or its determination of a strictly legal issue.'" Utley v. Bd. of Review, Dep't of Labor, 194 N.J. 534, 551 (2008) (citations omitted). Thus, our review of a question of law is de novo. Mount v.

1 Cedar Knolls' initial Notice of Appeal reflected that the final agency decision was the February 20 email. However, an Amended Notice of Appeal was later filed clarifying that the May 1 notification was the agency's final decision.

A-3151-17T1

Bd. of Trs., Police & Firemen's Ret. Sys., 233 N.J. 402, 419 (2018) (citation omitted).

It is well settled that the primary purpose of "statutory interpretation is to determine and 'effectuate the Legislature's intent.'" State v. Rivastineo, 447 N.J. Super. 526, 529 (App. Div. 2016) (quoting State v. Shelley, 205 N.J. 320, 323 (2011)). We start with considering "the plain 'language of the statute, giving the terms used therein their ordinary and accepted meaning.'" Ibid. And where "[t]he Legislature's chosen words lead to one clear and unambiguous result, the interpretive process comes to a close, without the need to consider extrinsic aids." Ibid. Hence, we do "not 'rewrite a plainly-written enactment of the Legislature [or] presume that the Legislature intended something other than that expressed by way of the plain language.'" Ibid. (quoting Marino v. Marino, 200 N.J. 315, 329 (2009) (alteration in original)).

Free access — add to your briefcase to read the full text and ask questions with AI

IN THE MATTER OF DENIAL OF CEDAR KNOLLS 2006 LLC'S HAZARDOUS DISCHARGE SITE REMEDIATION, ETC. (NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION), (N.J. Ct. App. 2018).

IN THE MATTER OF DENIAL OF CEDAR KNOLLS 2006 LLC'S HAZARDOUS DISCHARGE SITE REMEDIATION, ETC. (NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION) (IN THE MATTER OF DENIAL OF CEDAR KNOLLS 2006 LLC'S HAZARDOUS DISCHARGE SITE REMEDIATION, ETC. (NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Klein
80 U.S. 128 (Supreme Court, 1872)
Plaut v. Spendthrift Farm, Inc.
514 U.S. 211 (Supreme Court, 1995)
O'Neill v. State Highway Department
235 A.2d 1 (Supreme Court of New Jersey, 1967)
Marino v. Marino
981 A.2d 855 (Supreme Court of New Jersey, 2009)
Oberhand v. Director, Division of Taxation
940 A.2d 1202 (Supreme Court of New Jersey, 2008)
W v. Pangborne & Co. v. New Jersey Department of Transportation
562 A.2d 222 (Supreme Court of New Jersey, 1989)
Rudbart v. North Jersey District Water Supply Commission
605 A.2d 681 (Supreme Court of New Jersey, 1992)
Nobrega v. Edison Glen Associates
772 A.2d 368 (Supreme Court of New Jersey, 2001)
Utley v. Board of Review, Department of Labor
946 A.2d 1039 (Supreme Court of New Jersey, 2008)
State v. Shelley
15 A.3d 818 (Supreme Court of New Jersey, 2011)
State of New Jersey v. Richard Rivastineo
149 A.3d 321 (New Jersey Superior Court App Division, 2016)
Richardson v. Board of Trustees, Police & Firemen's Retirement System
927 A.2d 543 (Supreme Court of New Jersey, 2007)
Mount v. Bd. of Trs., Police & Firemen's Ret. Sys.
186 A.3d 248 (Supreme Court of New Jersey, 2018)