In the Matter of Alsem Construction LLC

CourtDistrict Court, E.D. Louisiana
DecidedSeptember 24, 2024
Docket2:23-cv-00287
StatusUnknown

This text of In the Matter of Alsem Construction LLC (In the Matter of Alsem Construction LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In the Matter of Alsem Construction LLC, (E.D. La. 2024).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

IN RE: ALSEM CONSTRUCTION, CIVIL ACTION LLC, AS OWNER OF THE DECK BARGE 7137UF, PETITIONING FOR NO: 2:23-cv-00287 EXONERATION FROM AND/OR

LIMITATION OF LIABILITY SECTION T (3)

ORDER and REASONS Before the Court is Motion for Summary Judgment (R. Doc. 47) filed by Limitation Claimants William Gegenheimer, Steven Lewellen, Deborah Lewellen, Richard Cordes, Gilda Cordes, Richard Puglise, Sr., and Jo Ann Puglise (collectively, the “Gegenheimer Claimants”), Jason Schilling, Mikel Crossen, Lisa Crossen, Jason Schell, and Susan Cox Bourgeois, individually and on behalf of similarly situated individuals, (collectively, the “Schilling Claimants”), and the Louisiana Department of Transportation and Development (the “DOTD”) (and collectively with the Gegenheimer Claimants and the Schilling Claimants, “Claimants”). The Motion seeks dismissal of the Limitation Action filed by Alsem Construction, LLC, as owner of the Deck Barge 7137UF, on the basis that the Limitation Action was not timely filed under 46 U.S.C. § 30529(a). R. Doc. 47. For the reasons set forth below, the Court will deny the Motion for Summary Judgment. BACKGROUND This action arises out of an allision of three vessels with the Leo Kerner Bridge, a swing 1 bridge connecting Jean Lafitte to Barataria in Jefferson Parish, on August 29, 2021, following landfall of Hurricane Ida. One of the alliding vessels was the Deck Barge 7137UF, which is owned and operated by the Limitation Petitioner, Alsem Construction, LLC. As a result of the allision, the bridge sustained severe damage, rendering it unserviceable and making overland passage impossible. On September 8, 2021, the Louisiana National Guard constructed an emergency temporary floating bridge to allow access to Barataria while crews removed the damaged bridge. The DOTD subsequently entered into a $4 million contract to construct a temporary bridge. That temporary bridge, however, does not accommodate marine traffic. Construction of a permanent replacement for the swing bridge commenced in Spring of 2023. On November 22, 2021, counsel for the DOTD sent a letter to the registered agent and

officer for Alsem Construction, Douglas Alsem, notifying Limitation Petitioner of the DOTD’s intent to hold it liable for the damage to the Leo Kerner Bridge caused by the Deck Barge. See R. Docs. 47-4 and 47-5. The letter provided, in relevant part: As you know, several vessels that broke loose from Tom’s Marine & Salvage yard during Hurricane Ida struck the Leo Kerner Swing Bridge, causing significant damage to the bridge, rendering it inoperable and forcing its closure to vehicular traffic. We understand that at least one of these vessels, a barge, was owned by you/your company. The purpose of this letter is to notify you that the Louisiana Department of Transportation and Development holds you and your company responsible for the damage sustained by the bridge as a result of the incident, and for all the costs incurred by the Department in responding to this casualty, including providing ferry services for passengers, construction of a temporary bridge, temporary and permanent repairs, and all incidental costs and expenses regarding this matter. 2 We respectfully request that you promptly notify and forward this letter to your insurance agents and carriers, and that you request that they promptly contact the undersigned at (504) 524-5353. Claimants contend this letter provided unambiguous notice to the Limitation Petitioner that, as a result of the Deck Barge’s allision with the Leo Kerner Bridge on August 29, 2021, the DOTD was making a claim against it for all related damages sustained and to be incurred. R. Doc. 47-1, p. 3. On July 18, 2022, the DOTD filed suit against Tom’s Marine & Salvage, LLC, Alsem Construction, and Triple T. Marine, LLC, seeking damages arising from the August 29, 2021 allisions. R. Doc. 47-1, p. 3. Alsem Construction was subsequently named as a defendant in two additional actions filed on August 29, 2022, by the Gegenheimer and Schilling Claimants who likewise seek damages resulting from the August 29, 2021 allisions. R. Doc. 47-1, p. 4. Alsem Construction filed an answer to each suit. Alsem Construction later filed its Limitation Complaint in this Court on January 20, 2023. R. Doc. 1. In the Complaint, Alsem Construction seeks to be exonerated from liability for the allision or limit its liability to the value of the Deck Barge pursuant to the Limitation of Liability Act, 46 U.S.C. § 30505 et seq. Alsem Construction asserts that the value of the Deck Barge is $10,000 and requests the Court transfer its interest to a trustee. This Court issued an Order staying and restraining all actions against Alsem Construction or the Deck Barge arising from the allision and set a monition date of July 24, 2023. R. Docs. 3 and 6. The Gegenheimer Claimants, the Schilling Claimants, and the DOTD all timely filed their 3 Answer and Claims in response to the Limitation Petitioner’s Limitation Complaint on or before the monition deadline. R. Docs. 7, 8, and 9. In the present Motion, Claimants assert the Limitation Petitioner’s Limitation Complaint filed on January 20, 2023, was untimely because it was not filed within the six-month period prescribed by 46 U.S.C. § 30529(a) and Supplemental Admiralty Rule F(1). They specifically contend that Alsem Construction had notice of the possible claims against it as early as November 22, 2021, when the DOTD sent its demand letter to Alsem Construction’s registered agent and officer. Accordingly, Claimants assert the filing of the Limitation Complaint on January 20, 2023, was well beyond the time limitation for the filing of the action. Alsem Construction did not file a timely response to the Motion for Summary Judgment.

R. Doc. 74. In its belated filing, with permission of the Court, Alsem Construction does not dispute the facts as set forth above, except to the extent that it claims it never received the letter from the DOTD. Thus, Alsem Construction, as the Limitation Petitioner, asserts that, although the letter was allegedly mailed via the United States Postal Service, there is a genuine issue of material fact as to whether it was received. R. Doc. 74, p. 1. Alsem Construction contends it did not have notice of the claims against it until July 20, 2022, when it was served with the suit against it by the DOTD. R. Doc. 74, p. 2. In support of its argument, Alsem Construction attaches a Declaration from Douglas Alsem, the registered agent and officer of the Limitation Petitioner. R. Doc. 74-2. LAW AND ANALYSIS

Summary judgment is proper “if the movant shows that there is no genuine dispute as to 4 any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “A genuine dispute as to a material fact exists ‘if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.’” Rogers v. Bromac Title Servs., L.L.C., 755 F.3d 347, 350 (5th Cir.2014) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986)). “[T]he plain language of Rule 56(c) mandates the entry of summary judgment ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harvill v. Westward Communications, L.L.C.
433 F.3d 428 (Fifth Circuit, 2005)
Custer v. Murphy Oil USA, Inc.
503 F.3d 415 (Fifth Circuit, 2007)
Dillon v. Rogers
596 F.3d 260 (Fifth Circuit, 2010)
Rosenthal v. Walker
111 U.S. 185 (Supreme Court, 1884)
Hagner v. United States
285 U.S. 427 (Supreme Court, 1932)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Wells Fargo Business Credit v. Ben Kozloff, Inc.
695 F.2d 940 (Fifth Circuit, 1983)
Eckstein Marine Service L.L.C. v. Lorne Jac
672 F.3d 310 (Fifth Circuit, 2012)
Anson McFaul v. Daniel Valenzuela
684 F.3d 564 (Fifth Circuit, 2012)
Wanda Rogers v. Bromac Title Services, L.L.C., et
755 F.3d 347 (Fifth Circuit, 2014)
Lisa Lupyan v. Corinthian Colleges Inc
761 F.3d 314 (Third Circuit, 2014)
RLB Contracting, Inc. v. Butler
773 F.3d 596 (Fifth Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
In the Matter of Alsem Construction LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-alsem-construction-llc-laed-2024.