In re Village of Morrisville Water & Light Department

365 A.2d 525, 134 Vt. 428, 1976 Vt. LEXIS 695
CourtSupreme Court of Vermont
DecidedSeptember 17, 1976
DocketNo. 187-75
StatusPublished
Cited by2 cases

This text of 365 A.2d 525 (In re Village of Morrisville Water & Light Department) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Village of Morrisville Water & Light Department, 365 A.2d 525, 134 Vt. 428, 1976 Vt. LEXIS 695 (Vt. 1976).

Opinion

Larrow, J.

Eastern Magnesia Talc Co., claiming special status as a contract customer of the Village of Morrisville Water and Light Department, has appealed from the Findings and Order of the Public Service Board dated June 16, 1975, granting that Department an overall 37.7% increase in its base rates. The order was expressly made applicable to the appellant.

Pursuant to V.R.A.P. 13(d) the Board has certified to us nine questions for appellate review. We will not recite them all at length, because some of them are conditioned on answers other than those herein contained.

Question No. 1 is as follows:

1. Did the Public Service Board err in finding that the evidence was insufficient to establish a lawful “contract for a definite term” within the meaning of 30 V.S.A. Section 229?

Questions 2, 3 and 4 relate to interpretation of such a contract, if Question No. 1 is answered affirmatively, and to power of the Board to change a rate specified therein. These questions become immaterial in light of the negative answer to Question No. 1 hereinafter contained.

Question No. 5 is as follows:

5. Was EMT afforded adequate notice of the proceedings to change its “contract” rates, sufficient to satisfy the notice requirements of the laws of the United States and Vermont?

Questions 6, 7, and 8 are predicated upon a negative answer to No. 5. They become immaterial in light of our affirmative answer hereinafter contained.

Question No. 9 is as follows:

9. Was the evidence sufficient to sustain the findings of fact and conclusions of law of the Public Service Board relating to the new level of rates set for EMT?

Like most rate cases, a simple recital of the facts involved verges on the impossible. The ones pertinent to the issues here presented we will attempt to outline.

[430]*430On January 1, 1972, a contract previously in effect between appellant and Morrisville expired by its terms. Shortly thereafter, Morrisville filed proposed new rate schedules with the Board, encompassing its various filed rates but not those previously in force with appellant. On October 12, 1972, the Board ordered a revised filing, specifying that “the revised rate schedules should also include a rate schedule or contract with the Eastern Magnesia Talc Company.” Subsequently, in October, 1973, the parties executed a new contract, purporting to commence, retroactively, January 1, 1973. Morrisville forwarded this contract to the Board, by letter received October 17, 1973. No proceedings were taken with respect to it. About a week later, Morrisville filed its new rate schedules, again without reference to appellant. The contract differed from usual rate schedules in that it provided for (a) furnishing service outside Morrisville’s usual service area (b) a maximum rate of taking, from surplus energy generated or purchased (c) a delivery at 34,400 volts, 3 phase, 60 cycles (d) discounts for metering equipment and transformer ownership (e) 15 minute peak demand charges, and (f) a three year term, automatically extended, terminable after three years on six months’ notice.

Public notice of the changes was given November 5, 1973. On November 23, the Board suspended the changes and ordered an investigation into their reasonableness under 30 V.S.A. § 226. By order dated April 15, 1974, a temporary increase was granted Morrisville, following a February 28 hearing. On appellant’s April 3 bill was a notice that it was a tentative invoice, subject to adjustment for the expected order. The 13.9% temporary increase authorized was billed to appellant, above its claimed “contract rate”, and paid under protest.

Appellant’s general manager appeared at a November 14, 1974, hearing and testified about the claimed contract. He was given the prefiled testimony and exhibits. Thereafter, appellant intervened, appearing only for the limited purpose of contesting the validity of applying any rate increase to it. By written brief, it argued the Board lacked authority to change the written contract, that procedural difficulties precluded such change, and that the evidence was insufficient to warrant rescission. Following a hearing, and an “update hearing,” the [431]*431Board ruled that the contract contemplated modification by the Board, that even if it did not the Board had legal authority to change the contract rates, that appellant had been provided with adequate notice, and that the increased cost of service attributable to appellant justified an increase in its rates. A recoupment surcharge under 30 V.S.A. § 226(b) was authorized as to all customers. The instant appeal resulted.

The gravamen of the appeal before us is that the agreement dated as of January 1, 1973, is a valid, enforceable obligation under Vermont law, creating a fixed rate, and that it does not contemplate modification by the Public Service Board. Appellant claims that without any agreement as to modification, the Board has no statutory authority to modify, under 30 V.S.A. § 229. Appellant argues further that even if there is such authority, it had insufficient notice, that the proof was insufficient, that it should be refunded the amounts it paid under protest as a temporary increase, and that retroactive recoupment should not be allowed against it.

30 V.S.A. § 229 deals generally with the prohibition of special rates, rebates and the like by a public utility. Without quoting it in full, it contains two exceptions which are here pertinent. They read as follows:

... No public service company may enter into any contract, agreement or arrangement relating to the furnishing or rendering of any special product or special service not provided for or covered in the schedule without the prior approval of the board.
.. . Subject to the approval of the board, it shall be lawful for any public utility to make a contract for a definite term for its product or service.

Both Morrisville and the appellant, as well as the Board, seem to regard the agreement in question as within the quoted provision relating to contracts for a definite term, subject to board approval, although appellant argues that it had Board “approval” prior to its execution because of the Board’s order of October 12, 1972, requiring Morrisville to file revised schedules, including a new schedule or contract with the appellant. Nothing in that order required or even suggested that such contract be for a stated term, and we are unable to concur with appellant’s contention that the general direction con[432]*432tained in the order was a blanket approval for whatever contract was to be submitted. We cannot strain the literal meaning of “approval” to include a prior uninformed endorsement of whatever terms the parties may arrive at, or to mean unlimited authority to contract at will. Only by such interpretation could the mandate of the 1972 order be construed as “approval”.

Nor can we accept appellant’s contention that, absent formal approval or disapproval, the Board will be deemed to have approved the contract. The record amply demonstrates that the Board considered the contract terms as encompassed within the ongoing rate schedule review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daniels v. Elks Club of Hartford and the Human Rights Commission
2012 VT 55 (Supreme Court of Vermont, 2012)
Public Service Commission v. Diamond State Telephone Co.
468 A.2d 1285 (Supreme Court of Delaware, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
365 A.2d 525, 134 Vt. 428, 1976 Vt. LEXIS 695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-village-of-morrisville-water-light-department-vt-1976.