In re the New York, West Shore & Buffalo Railway Co.

94 N.Y. 287
CourtNew York Court of Appeals
DecidedJanuary 15, 1884
StatusPublished
Cited by9 cases

This text of 94 N.Y. 287 (In re the New York, West Shore & Buffalo Railway Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the New York, West Shore & Buffalo Railway Co., 94 N.Y. 287 (N.Y. 1884).

Opinion

Rapallo, J.

By the confirmation at Special Term of the

report of the commissioners, and the entry and recording of the order reciting the proceeding, and the payment of the compensation directed to be paid to the land-owners, the railroad company became entitled, under the statute, to take possession of and use the land for the purposes of its incorporation, and all persons who were parties to the proceeding were divested [291]*291and barred of all right, estate and interest in the land during the corporate existence of the company.

But, notwithstanding the change of title thus effected, and the taking possession by the railroad company, either party might under the provisions of the statute obtain a review, by the Supreme' Court, of the appraisal of the commissioners. This review did not affect either the title or right of possession of the railroad company, but only the amount paid by it. If in the judgment of the court it was excessive or insufficient, the court was empowered to direct a new appraisal before the same or new commissioners, in its discretion. If by the second appraisal the damages should be reduced, the company would be entitled to have the difference refunded. If the amount should be increased, the company would be bound to pay the increased amount, and it would become a lien upon the land, the title to which had already become vested in the company. (Laws of 1850, chap. 140, §§ 17,18.)

The court having in this case, on the appeal of the railroad company to the General Term, from the order confirming the report of the commissioners, exercised the discretion conferred upon it by the statute, by vacating the award of the commissioners and the confirmation thereof, and directing a new appraisal before new commissioners, its determination, in that respect, cannot be reviewed by this court. It involves simply questions of fact and matters of discretion, of which this court cannot take cognizance.

It is claimed on the part of the appellants that inasmuch as the order of the General Term awards costs against them absolutely, it is appealable in that respect, and consequently the whole of the order is reviewable here, and the case of Bergen v. Carman (79 N. Y. 146) is cited as an authority for that proposition.

Conceding that the part of the order which awards costs, and the judgment entered thereon, are appealable if the award of costs was contrary to law, or unauthorized by law, it does not follow that the other portions of the order are appealable, and Bergen v. Carman is not an authority to that effect. The ob[292]*292jection in that case was that the order appealed from sent the case hack to the referee for a further hearing, and therefore, was not final. The difficulty in this case is that the order,- in so far as it directs a new appraisal and the appointment of new commissioners, depended on questions of fact and was discretionary, so that, even if the general provisions applicable to appeals to this court extend to condemnation proceedings under the railroad law (which is controverted), the questions are not of such a nature that they can be reviewed here. The award of costs cannot confer jurisdiction over those questions.

The next question which arises is on the order of the General Term denying the motion of the land-owners to dismiss the appeal from the order confirming the report of the commissioners.

It may be assumed that if, after the award of the commissioners had been confirmed, the railroad company had entered into a valid agreement with the land-owners to abide by the award and not to appeal from the confirmation thereof, or had done acts which in law had constituted a waiver of the right to appeal from such confirmation, the General Term could and ought to have enforced such agreement or waiver, and that its refusal to do so would present a question of law reviewable here. It is not necessary to decide that question now, because we are of opinion that no waiver of the right to appeal to the General Term was shown.

The facts claimed to constitute a waiver are that, under a former proceeding to acquire title to the lands in question, the company had obtained possession and begun the construction of an embankment and road-way thereon. Those proceedings were subsequently reversed and annulled, pursuant to the judgment of this court, and a new proceeding (the present one) was instituted. The company thereupon applied to the court, under section 21 of the Railroad Act, for an order allowing it to continue in possession until the final conclusion of the new proceeding, the compensation awarded in the first proceeding having been already deposited. The order asked for was granted, but a provision was inserted in it for the benefit of the land-owners, [293]*293requiring the company to leave and keep open a gap in their embankment, through which vessels could pass from the river to the brickyards of the land-owners. This order was dated July 22, 1882. Commissioners were appointed under the second proceeding, August 29, 1882. Their report was made November 24,1882, and was confirmed December 4,1882, and the order of confirmation, being the order from which the appeal was taken to the General Term, contained a provision that, on payment or deposit of the sums thereby awarded to the landowners for their compensation, the railway company have full and complete possession of the lands, and that any and all orders theretofore granted, inconsistent with such possession, be annulled and set aside. The company thereupon paid the awards to the land-owners, and immediately thereafter closed up the gap which it had left open, pursuant to the order of July 22, 1882, and on the 21st of December, 1882, it appealed to the General Term for the purpose of reviewing the amount of the awards.

The motion at General Term to dismiss the appeal was made upon the ground that, by thus closing the gap, the company had taken a benefit awarded to it by the order of confirmation appealed from, viz.: that it had availed itself of that part of the order which gave it full possession of the premises and annulled all former orders inconsistent with such possession, and that, by thus availing itself of that provision of the order of confirmation, it had precluded itself from appealing from any part of the order. We think that the motion to dismiss was properly denied. The right of the company to take full possession of the premises, and use them for the purposes of its incorporation, on paying the awards, was conferred upon it by the statute, independently of the order of the court, and by the same statute the land-owners, who were parties to the proceeding, were divested and barred of all estate, right and interest in the land which could interfere with such use. The company did not after that time hold possession under the order of July 22, and ceased to be subject to the condition imposed by that order. It held, by virtue of the condemnation of December [294]*2944, 1882, the payment of the awards, and the right which the statute conferred as consequent thereupon. By exercising this right and filling up the gap, it did not avail itself of any benefit conferred by the order appealed from, which should preclude it from appealing. The condemnation was complete and final; nothing could, thereafter, be reviewed upon the appeal but the amount of the award, and the statute very clearly provides that this review may be had after the awards have been paid, and the title has changed and possession has been taken.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grand River Dam Authority v. Jarvis
124 F.2d 914 (Tenth Circuit, 1942)
Utah Copper Co. v. Stephen Hayes Estate, Inc.
31 P.2d 624 (Utah Supreme Court, 1934)
City of Eufaula v. Ahrens
159 P. 327 (Supreme Court of Oklahoma, 1916)
Peoria, Bloomington & Champaign Traction Co. v. Vance
95 N.E. 1081 (Illinois Supreme Court, 1911)
Gano v. Minneapolis & St. Louis Railroad
114 Iowa 713 (Supreme Court of Iowa, 1901)
Owsley v. Oregon Railway & Navigation Co.
20 P. 782 (Washington Supreme Court, 1889)
Crosby v. . Stephan
97 N.Y. 606 (New York Court of Appeals, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
94 N.Y. 287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-new-york-west-shore-buffalo-railway-co-ny-1884.