In re the Discipline of Stubbs

1999 UT 15, 974 P.2d 296, 363 Utah Adv. Rep. 12, 1999 Utah LEXIS 20, 1999 WL 77649
CourtUtah Supreme Court
DecidedFebruary 19, 1999
DocketNo. 970439
StatusPublished
Cited by3 cases

This text of 1999 UT 15 (In re the Discipline of Stubbs) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Discipline of Stubbs, 1999 UT 15, 974 P.2d 296, 363 Utah Adv. Rep. 12, 1999 Utah LEXIS 20, 1999 WL 77649 (Utah 1999).

Opinions

DURHAM, Associate Chief Justice:

¶ 1 The Utah State Bar (the Bar) appeals from a district court order suspending Byron Stubbs from the practice of law for three years. The Bar contends that the district court erred in deviating from the presumptive level of discipline and that it should have ordered disbarment. Stubbs cross-appeals, asserting that the district court erred by imposing too severe a sanction against him and requesting a reduction in the term of his suspension.

¶ 2 On July 26, 1996, Stubbs pled guilty to one count of communications fraud, a class A misdemeanor, in violation of Utah Code Ann. § 76-10-1801. The guilty plea was based on Stubbs’ participation in a scheme to defraud the State through the preparation of a letter on behalf of his client, Tool Design, Engineering and Manufacturing (Tool Design). The letter Stubbs prepared contained false representations regarding the status of environmental remediation efforts on a piece of property Tool Design owned. Stubbs knew the statements contained in the letter were false and he knew his client intended to send the letter to the State to facilitate the scheme to defraud.

¶ 3 In June 1988, the State issued a notice of violation to Tool Design based on dangerously high levels of lead and chrome found in a ditch on Tool Design property. [298]*298Stubbs represented Tool Design at the time the State issued the notice. Shortly thereafter, Tool Design replaced Stubbs with other counsel. On March 6, 1989, the State and Tool Design, with the assistance of its new counsel, entered into a consent decree whereby Tool Design promised to remediate the contamination. Soon after the entry of the consent decree, Stubbs resumed his role as Tool Design’s counsel. Although he had not participated in the negotiations leading to the consent decree, Stubbs was aware of its terms.

¶ 4 In October 1989, the State approved a site remediation plan submitted by EarthFax Engineering, Inc., on Tool Design’s behalf. Tool Design failed to implement the plan due to financial difficulties. In October 1990, Tool Design submitted a modified plan for remediating the contaminated ditch in which Wasatch Environmental, Inc. (Wasatch), would conduct the remediation efforts. The State gave its approval to the initial stages of the modified plan, which included soil sampling and testing. In April 1991, Wasatch began sampling and testing the contaminated soil, but discontinued the testing because Tool Design failed to pay for the work.

¶ 5 On December 16, 1991, the State issued an order to show cause regarding Tool Design’s failure to comply with the remediation requirements. Stubbs suggested that Tool Design contract with Don Hall to perform site preparation work so that Wasatch could continue its testing. On December 28, 1991, Hall and another worker removed a substantial amount of contaminated soil from Tool Design property and took it to the city dump. Although it is unclear who gave Hall the order to remove the soil, such action specifically violated the consent decree. Later, that day, Stubbs visited the ditch and told Hall to stop removing the soil.

¶ 6 Stubbs claims that it was not until shortly after the December 28 removal of the contaminated soil that he realized the removal violated the consent decree. On January 7, 1992, at a meeting arranged by Stubbs, Stubbs met with State representatives to discuss Tool Design’s failure to comply with the site remediation plan. Stubbs urged Tool Design president Herb Strehl to attend the meeting, but Strehl refused and ordered Stubbs not to disclose the wrongful removal of the contaminated soil, [id] At the meeting, Stubbs represented that Wasatch had completed three-fourths of the sampling and that the remainder would be completed by the end of summer. Stubbs did not disclose the removal of the contaminated soil.

¶ 7 On November 1, 1996, Stubbs submitted a letter to the Bar attempting to explain his criminal conduct. In that letter, Stubbs lied, claiming that at the January 7, 1992 meeting he had informed the State that contaminated soil had been removed from Tool Design property.

¶ 8 On March 13, 1992, Stubbs met with Wasatch representatives Les Pennington and John Rabideau. At that meeting, Stubbs paid Wasatch for work performed and proceeded to misrepresent the facts surrounding the removal of the contaminated soil. Stubbs lied to Pennington and Rabideau, claiming that Strehl had removed some soil over the weekend and that he (Stubbs) did not know where the soil was taken. In fact, Stubbs knew how much soil had been removed, where it was taken, and that the soil had been moved by Hall more than two months earlier.

¶ 9 On March 13, 1992, after the meeting with Wasatch, Stubbs met with Strehl, Hall, and Tool Design employee James Robertson at the Tool Design ditch. Stubbs stated that “we’ve got our titty in a bit of a twister.” Stubbs went on to explain that they needed to put some dirt back into the ditch and they were unable to recover the dirt that had already been removed. Stubbs suggested that they get clean dirt to replace that which was removed, place a pump in the chrome rinse tank, and then contaminate the new soil. On March 14, 1992, believing the conduct suggested by Stubbs was illegal, Rober-ston contacted the State and disclosed the substance of the March 13 meeting. Robertson’s disclosure triggered an investigation by the Attorney General’s Office.

¶ 10 On March 19, 1992, Stubbs spoke with Robertson regarding the replacement and contamination of the new soil. Robertson informed Stubbs that he would not par[299]*299ticipate in the plan. Robertson reiterated his refusal to Strehl. Shortly thereafter, Stubbs informed Robertson that Strehl had abandoned the plan to contaminate the new soil because they had been able to get some of the old dirt back.

¶ 11 In his November letter to the Bar, Stubbs admitted that he watched the replacement of dirt in the ditch in March of 1992. At trial in this matter, Stubbs directly contradicted the admission made in that letter.

¶ 12 In March 1992, Stubbs discovered that Strehl intended to camouflage the ditch by placing additional debris in it to create the illusion that the ditch was in its original condition. Instead of discouraging Strehl from carrying out this illegal plan, Stubbs aided Strehl by tossing debris into the ditch. Stubbs’ acts were surreptitiously videotaped by the Attorney General’s investigator. Stubbs contended at trial that he tossed debris into the ditch “facetiously,” to make fun of his client. The trial court rejected Stubbs’ explanation.

¶ 13 On March 30, 1992, Stubbs and Strehl again met with Wasatch. At that meeting, Strehl lied to Wasatch by stating that all the dirt removed from the ditch had been put back. Strehl also stated that any change in the volume of soil was due to the removal of debris. Stubbs made no effort to rectify Strehl’s representations even though he knew they were false and that Wasatch would rely on those representations. Later that day, Wasatch representatives Rabideau and Pennington visited the Tool Design ditch. Rabideau observed a significant change in the size and shape of the ditch and determined that it needed to be re-surveyed.

¶ 14 On April 9, 1992, Stubbs, Pennington, and Rabideau met with State representatives. Strehl did not attend the meeting but had agreed that Stubbs should reveal that Strehl had disturbed the contaminated soil.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re of the Discipline of Grimes
2012 UT 87 (Utah Supreme Court, 2012)
Brussow v. Utah State Bar
2012 UT 53 (Utah Supreme Court, 2012)
In Re the Discipline of Pendleton
2000 UT 77 (Utah Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
1999 UT 15, 974 P.2d 296, 363 Utah Adv. Rep. 12, 1999 Utah LEXIS 20, 1999 WL 77649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-discipline-of-stubbs-utah-1999.