In re the Complaint of Robbins Maritime, Inc.

906 F. Supp. 309, 1995 A.M.C. 2191, 1995 U.S. Dist. LEXIS 12038
CourtDistrict Court, E.D. Virginia
DecidedJune 9, 1995
DocketCiv. A. No. 2:94cv515
StatusPublished
Cited by3 cases

This text of 906 F. Supp. 309 (In re the Complaint of Robbins Maritime, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Complaint of Robbins Maritime, Inc., 906 F. Supp. 309, 1995 A.M.C. 2191, 1995 U.S. Dist. LEXIS 12038 (E.D. Va. 1995).

Opinion

ORDER AFFIRMING MAGISTRATE JUDGE’S REPORT & RECOMMENDATION

DOUMAR, District Judge.

I. Procedural Background

This matter is now before the court on Universal’s objections to the recommendation of the Magistrate Judge that Hale Intermo-dal Marine Company (“Hale”) be granted summary judgment in its claim against Universal Maritime Service Corporation (“Universal”) for indemnity arising out of a fire on a barge on April 15, 1994. The fire caused extensive property damage. Universal is the stevedoring company which loaded the barge, the Liberty Trader. Hale is the owner of the barge. Hale claims that Universal breached its implied warranty of workmanlike service in loading the barge and seeks indemnity from Universal for any damages it will incur as a result of the fire.

Senior United States District Judge John A. MacKenzie, by an Order entered March 28, 1995, pursuant to 28 U.S.C. § 636(b)(1)(B), designated Magistrate Judge William T. Prince to conduct a hearing and to submit to a Judge of the court proposed recommendations for disposition of Hale’s Motion for Summary Judgment Against Universal, filed February 17, 1995; and Universal’s Cross-Motion for Summary Judgment filed March 6, 1995.

The Magistrate Judge held a hearing on March 30, 1995, and issued its Report and Recommendation on April 13, 1995, recommending summary judgment be granted in favor of Hale against Universal on Hale’s claim for indemnity. Objections by Universal to said report were then lodged with the court and oral argument was requested. The undersigned District Judge held a hearing on the objections to the report and recommendation on May 30, 1995.

For the foregoing reasons, after de novo consideration of the objected-to portions of the report, the court will AFFIRM the recommendation contained in the Magistrate Judge’s report and GRANTS Hale’s motion for summary judgment against Universal.

II. Facts

The record in this case contains a plethora of undisputed facts; the real dispute by Universal with the magistrate judge’s report has to do with the legal implications of those [312]*312facts. The undisputed record shows the following. The barge Liberty Trader was chartered by Hale via an oral agreement to the Maersk company, and delivered on April 12, 1994, at Port Elizabeth, New Jersey. Maersk intended to use the barge to ship containerized cargo to Baltimore and Norfolk. Maersk had an oral agreement with Universal to perform stevedoring operations, including loading at the Dundalk terminal in Baltimore on April 14, 1994. Maersk, Hale, and Universal had a longstanding course of dealing with each other. There were no written contracts involved in the specific dispute at issue here.

Maersk normally determined a day in advance the number and type of containers it planned to load on a Hale barge. This information was provided to Hale’s Port Superintendent, in this case Mr. Kellenberger, who would prepare a “prestow” plan. Kellenber-ger testified that the prestow plan would indicate to Universal “where I think the cargo should go on the barge so that its stays balanced and trimmed properly, keep the dangerous cargo separate.” (Dep. at 42). Universal’s Marine Manager, Mr. Benston, testified that the purpose of the prestow was to “give [Universal] a map, so to speak, of where to stow the individual containers on the basis of size, kind, and other distinguishing things.” (Dep. at 23). Kellenberger’s prestow plan had what Kellenberger admitted was a “stupid” mistake — it called for a 45 foot dry cargo container to be placed atop a 40 foot diesel generator container (used to power a refrigeration unit). The 45 foot container would overhang and block the 40 foot generator container’s exhaust. The fire ultimately was caused by the build-up of heat resulting from this overhang.

The exhaust pipe configuration, which was designed by Hale, involves the exhaust pipe protruding horizontally out a foot or two at one end of the generator container, then bending 90 degrees up and terminating near the top edge of the generator container. Thus, something placed atop the generator container which overhangs the generator container by several feet will block the exhaust. It is this blocked emission which caused the excessive heat that built up, resulting in a fire starting in the cargo container above the exhaust pipe. Universal maintains that this design is faulty and that Universal should have been warned by Hale of this allegedly latent defect. The configuration of the exhaust pipe in this generator container was said to be quite rare. However, Hale maintains that the configuration of the pipe is not hidden in any way and that Universal had extensive experience with the particular generator unit in question.

Hale’s main legal contention as applied to these facts, which was accepted by the magistrate judge, is that any error on Hale’s part did not “prevent or seriously handicap” Universal, the stevedore, from performing its functions in a “workmanlike” manner. Hale emphasizes that the ensuing fire was far from inevitable and the fault for not avoiding the loss lies with Universal. First, it is undisputed that Universal was still responsible for reviewing the Hale prestow plan and preparing the final, more detailed, stowage plan. Hale emphasizes that it (Hale) had been responsible for both the prestow and final plan up until 1992. In late 1992, Universal insisted that it prepare the final pres-tow plan and it charged premium overtime rates for the service. In this case, Mr. Bolton, the Universal “shiprunner” who reviewed Kellenberger’s prestow and prepared the final stowage plan, did not catch Kellen-berger’s error and it was duplicated in the final stowage plan.

It is also undisputed that Universal employees did the actual loading of containers onto the barge. Hale maintains that the Universal employees who physically loaded the barge could have easily detected and corrected the “obvious” problem. Hale emphasizes that Universal loaded the 40 foot generator container and then “loaded the 45 foot container over the generator exhaust.” (Br. in Supp. of S.J. at 10). Universal employees then secured the 45 foot container in place, installing twist locks less than three feet away from the “over-stowed exhaust.” Id. A Universal subcontractor, Multimarine Refrigeration, then hooked up the generator container to the refrigerated units, started the generator, tested its output, and cheeked the refrigerator temperatures.

[313]*313Hale also emphasizes that Mr. Cavanaugh, Universal’s Marine Superintendent at the site, was inexperienced and does not know if he even performed an inspection on the barge as allegedly required during the loading operation. However, Universal points out that it is undisputed that Kellenberger, Hale’s employee, made a final inspection of the barge before the voyage. Hale contends that it was dark when Kellenberger and the tug captain performed their inspection, and Kellenberger’s deposition asserts that inadequate lighting was provided, which federal law requires Universal to provide. Cava-naugh testified that he does not know if there was any portable fighting available.

On April 15, 1994, while being towed from Baltimore to Norfolk, the barge caught fire, damaging the barge and its cargo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
906 F. Supp. 309, 1995 A.M.C. 2191, 1995 U.S. Dist. LEXIS 12038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-complaint-of-robbins-maritime-inc-vaed-1995.