In Re the Commissioner's Order Denying Permit Application 93-1024

527 N.W.2d 173, 1995 Minn. App. LEXIS 203, 1995 WL 44827
CourtCourt of Appeals of Minnesota
DecidedFebruary 7, 1995
DocketC1-94-1944
StatusPublished
Cited by4 cases

This text of 527 N.W.2d 173 (In Re the Commissioner's Order Denying Permit Application 93-1024) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re the Commissioner's Order Denying Permit Application 93-1024, 527 N.W.2d 173, 1995 Minn. App. LEXIS 203, 1995 WL 44827 (Mich. Ct. App. 1995).

Opinion

*175 OPINION

PARKER, Judge.

The Watershed District challenges the order of the Commissioner of the Department Natural Resources summarily dismissing the district’s application for a permit to work in public waters. We affirm.

FACTS

The district court approved establishment of the Red Lake Watershed District (“RLWD”), relator, in 1969. Recently, RLWD devised the “Maple Lake Project” to augment lake levels in Maple Lake and to bolster flood-control measures in the area near the lake. Construction of the project would involve building a dike on state-owned land, and the ultimate impact would include occasional flooding of substantial portions of the Polk Wildlife Management Area. The Department of Natural Resources (“DNR”) manages the affected state land and opposes any use of state land for this project.

RLWD commissioned an engineering report on the project and appointed three residents as appraisers of the project’s costs and benefits, pursuant to state law. The RLWD’s Board of Managers then held public hearings, found the benefits outweighed the costs, and approved the project. However, RLWD made no effort to condemn or otherwise acquire rights in the state land targeted by the project. Instead, RLWD next applied to the DNR for a permit to work in public waters in order to begin construction of the project.

The DNR rejected RLWD’s permit application. Following RLWD’s request for a contested case hearing, the DNR moved for summary disposition and formal denial of RLWD’s permit request. The DNR relied, in part, on Minn.R. 6115.0240, subpt. 2.A, which requires applicants to describe their rights in, or ability to acquire rights in, land integral to a project. The administrative law judge recommended summary disposition, and the Commissioner of Natural Resources summarily denied RLWD’s permit request. The Commissioner based his conclusion, as did the ALJ, on RLWD’s inability to show that it could acquire property rights neees-sary to construct the Maple Lake Project. RLWD appeals from the Commissioner’s order.

ISSUES

I. Can RLWD condemn the state land needed for the Maple Lake Project?

II. Did the Commissioner err by granting summary disposition?

III. Did the Commissioner’s order constitute an impermissible appeal of RLWD’s decision to approve the project?

DISCUSSION

I.

RLWD contends the Commissioner erred, because RLWD has the authority to acquire the necessary property rights from the state by eminent domain. Under Minnesota law, the state retains general authority over water management policy. See, e.g., Minn.Stat. § 103A.201, subd. 1 (1994). However, watershed districts possess broad powers to develop local water policy plans and to undertake projects pertaining to flood control, lake levels, and other aspects of water management. See id. §§ 103D.201-.821. State law also grants “drainage authorities” substantial power to regulate “drainage” on a local level. See id. §§ 103E.005-.745. Chapter 103D delineates powers and procedures pertaining to watershed districts generally, while chapter 103E lays out supplemental powers and procedures applicable to drainage authorities constructing drainage projects. RLWD’s challenge involves interpretation of these statutes and triggers de novo review. See Arvig Tel. Co. v. Northwestern Bell Tel. Co., 270 N.W.2d 111, 114 (Minn.1978).

Specifically, RLWD argues that Minn.Stat. §§ 103D.715, subdivision 4, and 103E.025 provide it with authority to take or damage state land for this project, over the DNR’s objection. We conclude that RLWD misconstrues these statutes. RLWD correctly asserts that section 103E.025, subdivision 2, gives drainage authorities a powerful *176 tool to take state land for drainage projects. 1 However, chapter 103E, titled “Drainage,” applies only to drainage projects. 2 See id. §§ 103E.005, 103E.011. Although subdivision 4 of section 103D.715 refers to parts of 103E, including 103E.025, it concludes the reference with the phrase, “as they are applicable.” Id. § 103D.715, subd. 4. Because chapter 103E covers drainage, section 103D.715 implicitly refers only drainage 'projects forward to chapter 103E. Other sections of chapter 103D similarly refer drainage projects to chapter 103E. See id. §§ 103D.601, subd. 1(b); 103D.621; 103D.625.

Closer examination of chapter 103E reveals the following: Section 103E.005 defines “drainage authority,” “drainage project,” and “drainage system.” 3 Id. § 103E.005, subd. 9, subd. 11, subd. 12. Then, section 103E.011 delineates “drainage authority powers.” This section includes a requirement that drainage authorities obtain permission from the Commissioner of Natural Resources to perform work that would affect public waters. Id. § 103E.011, subd. 3. Finally, section 103E.011 grants drainage authorities limited power to manipulate lake levels and build structures affecting non-public waters. Id. § 103E.011, subd. 4. Nothing in chapter 103E displaces the DNR’s preeminent authority over non-drainage projects affecting public waters.

Outside the discrete realm of drainage projects, watershed districts must look to chapter 103D (“Watershed Districts”) to discern their powers and applicable procedures. See id. §§ 103D.201; 103D.335, subd. 11 (enunciation of general eminent domain power); 103D.511 (specific exclusion of section 117.155 implies that chapter 117 generally applies to condemnations under chapter 103D). Chapter 103D lacks the expedited procedures and enhanced powers of chapter 103E. Under the general provisions, watershed district projects comprise three stages: board hearings, appraisers’ report, and condemnation of property, if necessary. Robertson v. Belle Creek Watershed Dist., 255 N.W.2d 236, 240 (Minn.1977) (watershed district wanted to build flood-control project). The instant appeal does not address the first two stages.

Condemnation becomes necessary when a landowner refuses to convey land sought by a watershed district or other public entity. See id. Chapter 117 governs condemnation procedure generally. Id.; Minn.Stat. § 117.011. In reviewing condemnation powers, the Minnesota Supreme Court observed that not all condemnors enjoy equal powers of eminent domain. State v. Christopher, 284 Minn. 233, 238, 170 N.W.2d 95, 99 (1969). A hierarchy of entities exists, with the state at the top because of its sovereign authority. Id. • Furthermore, condemnation of public property for use inconsistent with its established public use requires specific statutory authorization.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minch v. Buffalo-Red River Watershed District
723 N.W.2d 483 (Court of Appeals of Minnesota, 2006)
Agra Resources Coop v. Freeborn County Board of Commissioners
682 N.W.2d 681 (Court of Appeals of Minnesota, 2004)
Elizabeth Bd. of Educ. v. NJT CORP.
776 A.2d 821 (New Jersey Superior Court App Division, 2001)
State Ex Rel. Humphrey v. Byers
545 N.W.2d 669 (Court of Appeals of Minnesota, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
527 N.W.2d 173, 1995 Minn. App. LEXIS 203, 1995 WL 44827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-commissioners-order-denying-permit-application-93-1024-minnctapp-1995.