In re the Arbitration between Zephyr Construction Co. & Boro Hall Corp.

7 A.D.2d 915, 182 N.Y.S.2d 946, 1959 N.Y. App. Div. LEXIS 10123

This text of 7 A.D.2d 915 (In re the Arbitration between Zephyr Construction Co. & Boro Hall Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Zephyr Construction Co. & Boro Hall Corp., 7 A.D.2d 915, 182 N.Y.S.2d 946, 1959 N.Y. App. Div. LEXIS 10123 (N.Y. Ct. App. 1959).

Opinion

Appeals from an order which (1) denied the motion of Zephyr Construction Co:, Inc., to confirm an award of arbitrators directing Boro Hall Corp. to pay Zephyr $37,052.75 “in full settlement of all claims submitted to arbitration, by either party against the other”, (2) granted Boro Hall’s motion to vacate the award, and (3) remitted the matter to the same arbitrators “in order that an award [916]*916issue which shall be mutual, final and definite upon the subject matter submitted”. Zephyr appeals from the entire order; Boro Hall appeals from so much of the order as remits the matter to the same arbitrators for correction of the award, instead of directing a new hearing before different arbitrators. The arbitration proceeding arose out of Zephyr’s claim for extra work under a construction contract. Boro Hall asserted a claim for damages theretofore incurred and to be incurred thereafter, because of Zephyr’s delay in completing the building as agreed. At the arbitration hearings, the parties stipulated that Zephyr’s claim for compensation would include only that for work done, and materials furnished up to March 10, 1957. There was some dispute at the hearings as to whether under that stipulation the arbitrators were empowered to assess Boro Hall’s damages, if any, for delay only up to March 10, 1957. It also appears that a payment in excess of $8,000, on account of Zephyr’s claim for extra work, was made by Boro Hall subsequent to that date but prior to the hearings and award. The Special Term, in denying Zephyr’s motion to confirm the award and directing that the matter be remitted to the same arbitrators so that the award could be clarified, held that it was impossible to determine from the face of the award whether the arbitrators had made their determination of Zephyr’s claim up to the cut-off date of March 10, 1957, whether and to what extent they had allowed Boro Hall’s claim, and whether Boro Hall had been credited with the payment made after March 10, 1957. Order affirmed, without costs. In our opinion the award was not, under the circumstances presented, mutual, final and definite ” and was properly vacated under subdivision 4 of section 1462 of the Civil Practice Act (cf. Hiscock v. Harris, 74 N. Y. 108, 113; Matter of Kyne [Molfetas], 3 A D 2d 384, 386). We are also of the opinion that the Special Term did not exceed or abuse its authority in remitting the matter to the same arbitrators for a correction of their award, rather than directing a rehearing (cf. Matter of Kyne [Molfetas], supra; Matter of Trophy Handbags v. Craft Ind. Case Corp., 156 N. Y. S. 2d 45, affd. 3 A D 2d 733; Blood v. Robinson, 55 Mass. 389). Nolan, P. J., Murphy, Ughetta, Hallinan and Kleinfeld, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hiscock v. . Harris
74 N.Y. 108 (New York Court of Appeals, 1878)
Blood v. Robinson
55 Mass. 389 (Massachusetts Supreme Judicial Court, 1848)

Cite This Page — Counsel Stack

Bluebook (online)
7 A.D.2d 915, 182 N.Y.S.2d 946, 1959 N.Y. App. Div. LEXIS 10123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-zephyr-construction-co-boro-hall-corp-nyappdiv-1959.