In Re the Arbitration Between Wilaka Construction Co. & New York City Housing Authority

216 N.E.2d 696, 17 N.Y.2d 195, 269 N.Y.S.2d 697, 1966 N.Y. LEXIS 1456
CourtNew York Court of Appeals
DecidedMarch 31, 1966
StatusPublished
Cited by20 cases

This text of 216 N.E.2d 696 (In Re the Arbitration Between Wilaka Construction Co. & New York City Housing Authority) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re the Arbitration Between Wilaka Construction Co. & New York City Housing Authority, 216 N.E.2d 696, 17 N.Y.2d 195, 269 N.Y.S.2d 697, 1966 N.Y. LEXIS 1456 (N.Y. 1966).

Opinion

Keating, J.

By permission of this court, the New York City Housing Authority appeals from an order of the Appellate Division, First Department, unanimously affirming, without opinion, an order of the Supreme Court, New York County (Lyman, J.), which, on motion of the respondent, Wilaka Construction Co., directed the parties to arbitrate a dispute for extra compensation arising out of a construction contract between them.

The contract contains certain conditions precedent to invoking arbitration, and it is the alleged failure of Wilaka to abide by them which gives rise to the present controversy.

On this appeal, both parties agree that Special Term erred in holding that the fulfillment of conditions precedent to arbitration is a question for the arbitrator. That question is for the court. (Matter of Exercycle Corp. [Maratta], 9 N Y 2d 329; Matter of Rosenbaum [American Sur. Co.], 11 N Y 2d *199 310; Matter of Lipman [Haeuser Shellac Co.], 289 N. Y. 76; Matter of Board of Educ. [Heckler Elec. Co.], 7 N Y 2d 476.)

The facts are undisputed, and the primary questions of law presented are whether the contractor, Wilaka, failed to comply with time requirements of the contract for invoking arbitration of a claim and, if it did, whether the claim may nonetheless be arbitrated because the Housing Authority waived compliance.

Before turning to the facts, we briefly outline the pertinent provisions of the contract.

Wilaka undertook to serve as general contractor for the construction of a housing project known as West Brighton Houses.

Article 15 of the contract deals with disputes. Section a makes time of the essence, and it accordingly provides, in substance, that all work directed by the Authority shall be performed by Wilaka without delay ‘ ‘ reserving to the parties the right to have determined by the method in this Contract provided all questions relating to compensation, damages, or other payments of money.”

Subdivision (1) of section b deals with “Disputes as to Money Payment or for Damages * * * Conditions Precedent To Recovery. ” If the contractor claims that any direction involves “Extra Work entailing extra cost,” he must, within five days after receipt of such instructions and before executing the work, ‘ file with the Authority written notice of his intention to make a claim for extra compensation ’

“ The filing by the Contractor of a notice of claim * * * within the time limited herein, shall be a condition precedent to the settlement of any claim or to the right of appeal to arbitration as hereinafter provided”.

Subdivision (2) of section b gives the Authority power to determine whether work required is extra work or whether the contractor is entitled to compensation for damages and such determination shall be final, subject to the provisions of the paragraphs entitled “Appeal from Decision ” and “Arbitration.” Until a determination is made following a claim by the contractor “ as above provided ” for extra work, the contractor shall not proceed with the work.

Section c is entitled “Appeal from Decision.” It provides that the decision of the Authority “made upon the notice of claim” “ shall be conclusive and binding upon the Contractor *200 unless within ten (10) days from the service upon the Contractor of written notification of such decision, the Contractor files with the Authority * * * a notice of intention to arbitrate ”.

The failure of the Authority to make a decision within 30 days shall be deemed a denial of the claim, and the contractor has 10 days thereafter to demand arbitration. ‘ ‘ In default of such notice of intention to arbitrate within the time limited herein, the Contractor shall be deemed to have ratified such decision and to have waived any and all rights and remedies which he might otherwise have had, and the service of such notice of intention to arbitrate within the time limited, shall be a condition precedent to the right to appeal to' arbitration ’ ’.

Section d deals with the arbitration procedure itself but, for our purposes, it need not be considered.

We turn now to the facts.

The contract was made on September 29, 1960 and, among other things, it required. Wilaka to construct the framework “ true and plumb ” within certain tolerances. Wilaka engaged Lafayette Ironworks, Inc., to perform this work.

On May 16,1961 the Authority informed Wilaka that columns in certain buildings were out of plumb. It asked what corrective measurements would be taken and stated, ‘ ‘ Any remedial work which may be necessary is to be done by you without added cost to the Authority.”

Wilaka answered on July 6, 1961 that it was enclosing a technical report from a consulting firm employed by Lafayette along with three letters from Lafayette, all dated June 8, 1961. The letter from Wilaka to the Authority asks the Authority to consider the technical report and the letters, and to inform Wilaka so that it may proceed with corrective measures. The letters from Lafayette to Wilaka and the technical report make it clear that Lafayette attributed the problem to faulty construction plans.

The Authority wrote back on July 14, 1961, acknowledging receipt of Wilaka’s letter and the technical report, but indicating that Wilaka had forgotten to enclose the letters from Lafayette to Wilaka. “ In any event ”, wrote the Authority, it should be emphasized that no contractual relationship exists between [Lafayette] and the Authority.” “ We wish to remind you, in this connection, that any corrective work that is needed * * * *201 must be done at your cost and expense ”, notwithstanding the technical report which attributed fault to the Authority’s plans.

The extra expenses allegedly incurred by Lafayette form the basis of Wilaka’s claim here;

Wilaka responded on July 24, 1961 and requested a meeting “for the purpose of resolving, if possible, the question of responsibility for the existing condition and a determination as to the nature and extent of the corrective work required.”

The Authority answered on August 8, 1961. They acknowledged the conflict on the question of responsibility, reiterated their position that corrective work must be done at 11 your [Wilaka’s] cost and expense ”, refused to consider the claim by Lafayette “ with whom we have no contractual relationship ”, and stated, “ Such claims, if made, should be made by you in writing in accordance with the provisions of the contract.”

Ten days later, on August 18,1961, Wilaka again wrote to the Authority. To avoid further misunderstanding, Wilaka made it clear that, in forwarding the technical report and letters from Lafayette, it was acting on behalf of itself as well as Lafayette, and it would “ in due course, submit [a] claim for all of the increased costs incurred ”, but in the meantime “ to resolve the existing impasse, we are prepared to proceed with the suggested remedial measures ”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evan Louis Realty Corp. v. Flagg Properties, LLC
306 A.D.2d 409 (Appellate Division of the Supreme Court of New York, 2003)
Anagnostopoulos v. Union Turnpike Management Corp.
300 A.D.2d 393 (Appellate Division of the Supreme Court of New York, 2002)
Niagara Frontier Transportation Authority v. Computer Sciences Corp.
179 A.D.2d 1037 (Appellate Division of the Supreme Court of New York, 1992)
In re the Arbitration between City of Albany & Pomakoy
142 A.D.2d 775 (Appellate Division of the Supreme Court of New York, 1988)
In re the Arbitration between Morrow & Paragon Enterprises, Ltd.
135 A.D.2d 931 (Appellate Division of the Supreme Court of New York, 1987)
Dardaganis v. Grace Capital, Inc.
664 F. Supp. 105 (S.D. New York, 1987)
Evansville-Vanderburgh School Corp. v. Evansville Teachers Ass'n
494 N.E.2d 321 (Indiana Court of Appeals, 1986)
Norris v. Cooper
461 N.E.2d 1261 (New York Court of Appeals, 1984)
In re the Arbitration between Yengo & Watt
97 A.D.2d 574 (Appellate Division of the Supreme Court of New York, 1983)
Peter Kiewit Sons' Co. v. Port of Portland
628 P.2d 720 (Oregon Supreme Court, 1981)
In re the Arbitration between Dobbs Ferry Union Free School District & Dobbs Ferry United Teachers
74 A.D.2d 924 (Appellate Division of the Supreme Court of New York, 1980)
In re the Arbitration between Lane
70 A.D.2d 838 (Appellate Division of the Supreme Court of New York, 1979)
United Nations Development Corp. v. Norkin Plumbing Co.
380 N.E.2d 253 (New York Court of Appeals, 1978)
In re the Arbitration between Niagara Mohawk Power Corp. & Perfetto & Whalen Construction Corp.
52 A.D.2d 1081 (Appellate Division of the Supreme Court of New York, 1976)
In re the Arbitration between Board of Education & Auburn Teachers Ass'n
343 N.E.2d 760 (New York Court of Appeals, 1975)
Incorporated Village of Hempstead v. Anron Air System, Inc.
50 A.D.2d 571 (Appellate Division of the Supreme Court of New York, 1975)
Opan Realty Corp. v. Pedrone
335 N.E.2d 854 (New York Court of Appeals, 1975)
Gary Excavating, Inc. v. Town of North Haven
318 A.2d 84 (Supreme Court of Connecticut, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
216 N.E.2d 696, 17 N.Y.2d 195, 269 N.Y.S.2d 697, 1966 N.Y. LEXIS 1456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-wilaka-construction-co-new-york-city-ny-1966.