In re the Arbitration between Raisler Corp. & New York City Housing Authority

298 N.E.2d 91, 32 N.Y.2d 274, 344 N.Y.S.2d 917, 1973 N.Y. LEXIS 1307
CourtNew York Court of Appeals
DecidedMay 2, 1973
StatusPublished
Cited by72 cases

This text of 298 N.E.2d 91 (In re the Arbitration between Raisler Corp. & New York City Housing Authority) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Raisler Corp. & New York City Housing Authority, 298 N.E.2d 91, 32 N.Y.2d 274, 344 N.Y.S.2d 917, 1973 N.Y. LEXIS 1307 (N.Y. 1973).

Opinion

Breitel, J.

This is a proceeding to confirm an arbitration award, embracing a cross motion to vacate the award. The issues raised by appellant New York City Housing Authority are whether failure of petitioner Raisler Corporation to comply with conditions precedent to arbitration was a question for the arbitrator, and, if so, whether refusal by the arbitrator to consider this issue was a misconstruction of law or an imperfect execution of power. The quite separate issue raised by appellant S. S. Silberblatt, Inc. is whether the arbitrator properly awarded Raisler damages directly against Silberblatt, despite Silberblatt’s being a party to the arbitration only on a claim by the Housing Authority.

The arbitrator awarded petitioner Raisler $13,800, plus interest, against respondent Silberblatt for failure to supply timely, temporary elevator service, and $94,612.10, plus interest, against respondent Authority—$54,112.10 for balance due on its con[279]*279tract, $4,500 for additional work performed, and $36,000 damages for unreasonable delay in the project. It is only the $36,000 damage award which the Authority now contests. Special Term confirmed the arbitration award. The Appellate Division affirmed, different Justices dissenting on different grounds. Both unsuccessful parties appealed to this court.

The order of the Appellate Division should be affirmed. On the Authority’s appeal the requirements for filing a notice of claim are expressly made a condition precedent to arbitration in the agreement between the parties. The issue of compliance with these requirements was at least initially for the court. The Authority lost its opportunity for court review of this issue by its untimely petition to stay arbitration. Even if the arbitrator had in a matter of law incorrectly refused to determine this issue, it would only be an “ error ’ ’ of law judicially unreviewable. On Silberblatt’s appeal, the agreement between Silberblatt and the Authority has arbitration provisions giving the Authority the right to make Silberblatt a party to any arbitration between the Authority and another contractor. Again, even if the arbitrator had “ erred ” in a matter of law in holding Silberblatt directly liable to Raisler, his determination would be unreviewable.

On December 27, 1961, Raisler and Silberblatt executed separate agreements with the Authority for part of the construction of the Mott Haven apartment complex in the Bronx, being built under five separate prime contracts as required by statute. Raisler was the heating contractor and Silberblatt supplied, among other things, temporary elevator service. The project consisted of eight high-rise apartment buildings and a two-story community center. The project was substantially completed by May 26, 1965 and accepted by the Authority on December 1, 1965.

Under the separate agreements between the two contractors and the Authority, any claim by the contractor ‘ ‘ for any damages sustained by reason of any act or omission of the Authority ” had to be made in writing within five days after the claim had arisen. If the Authority demanded additional data, the contractor was required to furnish it within five days of the written demand. The immediately following sentence of the agreements provided: ‘ ‘ The filing by the Contractor of a notice of claim [280]*280and the compliance by the Contractor with the demand, if any, for additional data, depositions, or verified statements, both within the time limited herein, shall be a condition precedent to the settlement of any claim or to the right of appeal to arbitration as hereinafter provided, or to the right to resort to any other remedy, proceeding, or action.”

During the course of construction, Baisler made various written complaints about delays and interference with its work, including absence of temporary elevator service when it was heeded. On June 6, 1966, about six months after the project was completed, Baisler sent the Authority a detailed notice of claim. The parties dispute whether Baisler complied with the notice of claim provisions. On July 22, 1966, the Authority received a notice of intention to arbitrate from Baisler. The. notice stated that the Authority had 10 days in which to apply, pursuant to subdivision (c) of CPLB 7503, for a stay of arbitration on the ground that the agreement was invalid or had not been complied with.

On August 2,1966,11 days after the notice had been .received, one day late, the Authority mailed Baisler a notice of petition for a stay on the ground that Baisler .had not complied with a condition precedent to arbitration. Special Term denied the stay for untimeliness, and granted Baisler’s cross motion to compel arbitration. The Appellate Division affirmed (27 A D 2d 802), and this court denied leave to appeal (20 N Y 2d 645).

On November 2, 1967, in the arbitration proceeding, the Authority served demands to bring in Silberblatt and other contractors as parties to the arbitration. Silberblatt resisted, and was compelled to arbitrate by Special Term, in an order affirmed by the Appellate Division (30 A D 2d 917).

Préviously, on April 5, 1965, Baisler began an action in Supreme Court against Silberblatt seeking damages for failure to supply temporary elevator service. Apparently the action has since-been discontinued by stipulation.

In the arbitration proceeding, the Authority urged that the arbitrator should consider the issue of compliance with the contract five-day notice of claim provision. Baisler contended that the arbitrator was precluded from considering this issue by Special Term’s denial of a stay. The arbitrator apparently refused [281]*281to consider the issue of compliance, but did leave open for the Authority to show that it had been prejudiced by the lateness of the claim. After the hearing, extending over two years and 2,000 pages of transcript, the arbitrator found no prejudice to the Authority and awarded damages.

During arbitration the parties stipulated orally before the arbitrator that participation in the arbitration proceeding would not be deemed a waiver of any right they might have to determine the issue of compliance with conditions precedent at a later date in court.

The Authority is now challenging confirmation of that part of the award to Raisler of $36,000 on its damage claim for delay. It contends that the arbitrator improperly refused to hear and determine the issue of compliance with conditions precedent to arbitration, and that this refusal was not merely a misconstruction of law. The contentions of Silberblatt are separate and will be treated later.

Subdivision (c) of CPLR 7503 provides in part: “ A party may serve upon another party a notice of intention to arbitrate, specifying the agreement pursuant to which arbitration is sought and the name and address of the party serving the notice, or of an officer or agent thereof if such party is an association or corporation, and stating that unless the party served applies to stay the arbitration within ten days after such service he shall thereafter be precluded from objecting that a valid agreement was not made or has not been complied with and from asserting in court the bar of a limitation of time. ”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ingham v. Thompson
113 A.D.3d 534 (Appellate Division of the Supreme Court of New York, 2014)
LIVINGSTON COUNTY, MTR. OF
Appellate Division of the Supreme Court of New York, 2012
In re the Arbitration between Livingston County & Civil Service Employees Ass'n
101 A.D.3d 1697 (Appellate Division of the Supreme Court of New York, 2012)
Goldstein v. Goldstein
214 A.D.2d 567 (Appellate Division of the Supreme Court of New York, 1995)
Policemen's Benevolent Ass'n v. Rosenthal
207 A.D.2d 492 (Appellate Division of the Supreme Court of New York, 1994)
Office of Irwin G. Cantor, P. C. v. Swanke Hayden Connell & Partners
186 A.D.2d 71 (Appellate Division of the Supreme Court of New York, 1992)
Niagara Frontier Transportation Authority v. Computer Sciences Corp.
179 A.D.2d 1037 (Appellate Division of the Supreme Court of New York, 1992)
Gaspard v. American Transit Insurance
157 A.D.2d 543 (Appellate Division of the Supreme Court of New York, 1990)
Avon Products, Inc. v. Solow
150 A.D.2d 236 (Appellate Division of the Supreme Court of New York, 1989)
Rider v. Oakfield-Alabama Central School District
144 A.D.2d 918 (Appellate Division of the Supreme Court of New York, 1988)
In re the Arbitration between City of Albany & Pomakoy
142 A.D.2d 775 (Appellate Division of the Supreme Court of New York, 1988)
Singletary v. Government Employees Insurance
139 A.D.2d 723 (Appellate Division of the Supreme Court of New York, 1988)
In re the Arbitration between Guetta & Raxon Fabrics Corp.
123 A.D.2d 40 (Appellate Division of the Supreme Court of New York, 1987)
Sullivan v. American Airlines, Inc.
613 F. Supp. 226 (S.D. New York, 1985)
In re the Arbitration between Pierre & General Accident Insurance
100 A.D.2d 705 (Appellate Division of the Supreme Court of New York, 1984)
Seiler v. Kemper Insurance
100 A.D.2d 735 (Appellate Division of the Supreme Court of New York, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
298 N.E.2d 91, 32 N.Y.2d 274, 344 N.Y.S.2d 917, 1973 N.Y. LEXIS 1307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-raisler-corp-new-york-city-housing-ny-1973.