In re the Arbitration between Perkins & Will Partnership & Syska & Hennessy

50 A.D.2d 226, 376 N.Y.S.2d 533, 1975 N.Y. App. Div. LEXIS 11483
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 16, 1975
StatusPublished
Cited by9 cases

This text of 50 A.D.2d 226 (In re the Arbitration between Perkins & Will Partnership & Syska & Hennessy) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Perkins & Will Partnership & Syska & Hennessy, 50 A.D.2d 226, 376 N.Y.S.2d 533, 1975 N.Y. App. Div. LEXIS 11483 (N.Y. Ct. App. 1975).

Opinion

Lupiano, J.

The controversies at bar arise out of the construction of certain additions to and alterations of the facilities of The Mount Sinai Hospital of Hartford, Connecticut. The Mount Sinai Hospital (hereinafter "the Hospital”) entered into an agreement with The Perkins & Will Partnership (hereinafter "the Architect”) on or about July 28, 1965 for certain architectural and other services in connection with this construction. Similarly, on or about October 29, 1968, the Hospital entered into an agreement with Walter Kidde Constructors, Inc. (hereinafter "the General Contractor”) whereby the latter agreed to construct the additions and alterations to the Hospital’s facilities. The Architect utilized as consulting engineers on this project the firms of Syska and Hennessy (hereinafter "the Mechanical Engineers”) and Garfinkel, Marenberg & Associates (hereinafter "the Structural Engineers”). In March, 1972, the General Contractor commenced an arbitration proceeding against the Hospital under the arbitration provision of their agreement. In that proceeding the General Contractor asserts a claim for delay, extras and changes in the sum of $9,645,787. By demand dated April 20, 1973, the Hospital initiated an arbitration proceeding against the Architect, seeking to recover "[s]o much of damages claimed by [the General Contractor], which were the fault of the Architects and their Engineers”. Subsequently, the Hospital’s arbitration proceeding against the Architect, asserting a claim over, was consolidated into the prior arbitration proceeding between the General Contractor and the Hospital. While the determination consolidating these arbitration proceedings was subject to appellate review at the behest of the Architect, the Hospital and the General Contractor engaged in litigating discovery matters. Following appellate imprimatur of the court-directed consolidation, the litigation engaged in by the Hospital and the General Contractor resulted in a court order (March 7, 1975), directing the parties to proceed forthwith to arbitration.

Following this directive and before the selection of any arbitrators, the Architect served a demand for arbitration dated April 24, 1975 on both the Mechanical Engineers and the Structural Engineers. The demand stated as the nature of [229]*229the dispute the arbitration instituted by the Hospital against the Architect and as the claim or relief sought "[s]o much of the claims being made against [the Architect] by [the Hospital] * * * for which this [Architect] may be held liable to said [Hospital], for which the above-named [engineers] to whom this Demand is addressed may be liable for to the [Architect] herein”. Paragraph "15” in the agreement between the Architect and the Mechanical Engineers and in the agreement between the Architect and the Structural Engineers provides as follows: "Any decision or determination by the [Hospital] relating to the Architects performance or compensation under his contract with the [Hospital], which is binding upon the Architect, shall also be binding on the Consultant [the engineers] insofar as it relates to or involves his performance of compensation under this agreement. Any decision or determination resulting from arbitration between the Architect and the [Hospital] which relates to the Consultant’s services shall be binding upon the Consultant, provided that the Consultant has been afforded the opportunity to participate in the arbitration. Except as is heretofore provided for in this paragraph, any dispute arising between the parties to this agreement, or involving the interpretation of the terms of this agreement or a Work Authorization Form subject to this agreement, or any breach of either, shall be submitted and determined by arbitration before the American Arbitration Association. * * * All notices with respect to the demand for arbitration, the conduct of the arbitration and the enforcement of the arbitration award shall be deemed sufficient if served by telegram or certified or registered mail addressed by one party to the other at the addresses set forth herein” (emphasis supplied). The rider to the demand for arbitration served on the engineers contains specific reference to the contractual vouching-in procedure delineated in paragraph "15”. Further, it appears that the Architect served on the Structural Engineers by registered mail, return receipt requested, care of Sol Marenberg Associates, a letter dated April 30, 1975, referring to the arbitration provision of their agreement and advising of the pending arbitration against the Architect by the Hospital, as follows: "We are advising you of the aforesaid arbitration to which we have been made a party by the [Hospital] in accordance with the provisions of the * * * agreement between us dated June 24, 1966, and as revised, inform you thereof in accordance with that agreement and afford you the opportunity to participate in that arbitration.”

[230]*230The Architect commenced a special proceeding to stay the consolidated arbitration commenced by the General Contractor against the Hospital to which the Architect was made a party pending consolidation of the separate arbitration proceeding commenced by the Architect against the engineers with the afore-mentioned previously consolidated arbitration proceeding involving the General Contractor, the Hospital and the Architect. In answer, the Structural Engineers asserted counterclaims for a declaratory judgment that arbitration against them be permanently stayed on the ground, inter alia, that the demand for arbitration was improperly served and that the contractual vouching-in notice was untimely. The Mechanical Engineers in their answer requested permanent stay of the arbitration commenced against them and of utilization by the Architect of the vouching-in procedure set forth in their contract. In addition to opposing the Architect’s attempt to consolidate the arbitration proceedings, each of the engineers had commenced a separate proceeding to stay the arbitration demanded against them by the Architect. These proceedings were submitted to Special Term which disposed of them as follows: the Architect’s request for consolidation was denied on the ground that the Architect’s delay in proceeding against the engineers should not serve to further delay the prior consolidated arbitration proceeding involving the General Contractor, the Hospital and the Architect. The applications by the engineers to stay arbitration were denied on the ground that the agreements between the Architect and the engineers contained broad arbitration clauses. The Architect appeals and the engineers separately cross-appeal from that determination in the proceeding wherein the Architect seeks consolidation. Further, the Structural Engineers appeal from that determination in the proceeding separately initiated by them to stay the arbitration demanded by the Architect.

Scrutiny of the arbitration provision in the agreements between the Architect and the engineers mandates the conclusion that the Architect’s demand for arbitration against the engineers should have been vacated as no dispute is delineated therein which falls within that portion of the arbitration provision which contains the broad arbitration clause. Patently, the dispute between the Architect and the engineers involves indemnification and is so specified in the demand. This dispute is the subject of the exception to arbitration set forth in paragraph "15” of the agreements between the Archi[231]*231tect and the engineers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of Rozof v. Rozof
2025 NY Slip Op 07309 (Appellate Division of the Supreme Court of New York, 2025)
Larroca v. Royal Associates, L. L. C.
289 A.D.2d 537 (Appellate Division of the Supreme Court of New York, 2001)
In re the Arbitration between NRD, Inc. & Herbert Products, Inc.
153 Misc. 2d 968 (New York Supreme Court, 1992)
Filippazzo v. Garden State Brickface Co.
120 A.D.2d 663 (Appellate Division of the Supreme Court of New York, 1986)
In re Perkins & Will Partnership
131 Misc. 2d 826 (New York Supreme Court, 1985)
SCAC Transport (USA) Inc. v. S.S. "Danaos"
578 F. Supp. 327 (S.D. New York, 1984)
Chazen v. Dutchess Properties
107 Misc. 2d 254 (New York County Courts, 1980)
Joy v. Heidrick & Struggles, Inc.
93 Misc. 2d 818 (Civil Court of the City of New York, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
50 A.D.2d 226, 376 N.Y.S.2d 533, 1975 N.Y. App. Div. LEXIS 11483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-perkins-will-partnership-syska-hennessy-nyappdiv-1975.