In re the Arbitration between Manitt Construction Corp. & J. S. Plumbing & Heating Corp.

50 Misc. 2d 502, 270 N.Y.S.2d 716, 1966 N.Y. Misc. LEXIS 1839
CourtNew York Supreme Court
DecidedMay 25, 1966
StatusPublished
Cited by5 cases

This text of 50 Misc. 2d 502 (In re the Arbitration between Manitt Construction Corp. & J. S. Plumbing & Heating Corp.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Manitt Construction Corp. & J. S. Plumbing & Heating Corp., 50 Misc. 2d 502, 270 N.Y.S.2d 716, 1966 N.Y. Misc. LEXIS 1839 (N.Y. Super. Ct. 1966).

Opinion

J. Irwin Shapiro, J.

This is an application by the petitioner in which it seeks to vacate a demand for arbitration dated March 23, 1966 and “ an order staying the said arbitration between j. s. plumbing & heating corp. and madtel corp. [the respondents herein] ” and petitioner.

On September 14, 1965 petitioner and respondents entered into a contract wherein the respondents agreed to provide petitioner with the labor and materials for certain plumbing subcontract work in connection with a building project which the petitioner was constructing in Bayville, New York.

Insofar as material, paragraph “ 17 ” of the agreement between the parties provides that: “In consideration of the premises and as a condition of this agreement, the Sub-Contractor [respondents] hereby waives and releases the filing of any lien or claims and all right of lien now existing or that may hereafter arise for work or labor performed or materials furnished under this contract, under any present or future law, upon said structure, the land upon which the same is situated, and upon any money or moneys due or to become due from any person or persons to said Contractor [the petitioner] ”. Paragraph “ 24 ” of the agreement in pertinent part states: “ Any dispute or claim arising out of, or relating to this agreement or the breach thereof, shall be settled by arbitration in accord[504]*504anee with the provisions, then obtaining, of the standard form of arbitration procedure of the American Arbitration Association”. (Emphasis supplied.)

On or about March 11, 1966 the respondents served and filed a mechanic’s lien against the building project and the petitioner, alleging that the petitioner had failed and refused to pay the respondents $13,795 for work performed and material furnished under the contract.

The petitioner contends that by filing a mechanic’s lien in violation of the terms of the agreement (par.“17”, supra) the respondents as a matter of law waived their right to proceed against the petitioner in arbitration under the arbitration clause of the agreement (par. “ 24 ”, supra).

In opposition, the respondents argue for a dismissal of the petition on the grounds that,

“1. It sets forth no legally tenable ground for denying arbitration

‘ ‘ 2. The application is made in the wrong Court; and this Court has no jurisdiction of the application.

“3. It is not timely made ”.

On the merits the issue, simply stated, is whether under the facts of this case the respondents, by filing a mechanic’s lien in the face of their agreement not to do so, effectually abandoned their right to proceed against the petitioner by arbitration.

In general, the rule is that when a party to a contract containing an arbitration clause takes steps inconsistent with his right to proceed by arbitration, such as instituting an action at law on the contract or by interposing a counterclaim thereon, he thereby waives his right to arbitration. (Matter of Zimmerman v. Cohen, 236 N. Y. 15.)

Matter of Young v. Crescent Development Co. (240 N. Y. 244) involved a building contract which contained a provision to submit any dispute “under the contract” to arbitration. The respondent filed a mechanic’s lien and the court held that that act operated as a waiver of his right to arbitration. The court said (pp. 248-249): “ and I think that the answer to that question must be that the respondents by filing mechanic’s liens set out on a course so inconsistent with arbitration that they must be regarded as having decisively elected to waive and abandon their right to that course ”. The Young case would therefore be a conclusive authority against the right to maintain arbitration here were it not for the provisions of section 35 of the Lien Law (added by L. 1929, eh. 515) which were apparently adopted in view of the Young decision and the [505]*505suggestion made therein (p. 249) that: “ If we should conceive of a statute which gave general permission to a contractor to file a lien for the purpose of securing a claim no matter when or by what manner of proceeding ultimately established, the act of filing such a lien would not be a decisive election of remedies.”

Section 35 of the Lien Law explicitly provides that: “ The filing of a notice of lien shall not be a waiver of any right of arbitration of a contractor, * * * material man or laborer secured to him by his contract to furnish labor or materials.”

A waiver is an intentional abandonment or relinquishment of a known right. (Alsens Amer. Portland Cement Works v. Degnon Contr. Co., 222 N. Y. 34.) Here, by contract, there was such an intentional and unequivocal relinquishment of a known right, to wit, the statutory right to file a mechanic’s lien. Therefore, when in violation of the provisions of the contract, the respondents filed a mechanic’s lien, they evidenced an intention to prosecute their rights in a court of law, thereby effectually nullifying their right to proceed against the petitioner in an arbitration proceeding. The statute permitting the filing of a mechanic’s lien and preserving the lienor’s right to proceed by arbitration (Lien Law, § 35) is of no help to the respondents, for, by the express provisions contained in paragraph “17” of the contract between the parties, they relinquished their right to avail themselves of the benefit of the Lien Law.

Not being entitled to statutory immunity, the respondents, by filing a mechanic’s lien, put themselves in the same position as the respondents in the Young case (supra) and they are therefore not in a position to proceed against the petitioner by arbitration.

Matter of Askovitz (227 App. Div. 752 and 229 App. Div 258) highlights the question here at issue. Upon the first appeal the Appellate Division said (p. 753): “ Order granting motion to direct arbitration affirmed, with ten dollars costs and disbursements. There is no proof in this record that the contractors filed liens.”

After the respondents in the Askovitz case had been successful at Special Term in obtaining an order directing arbitration and while the first appeal to the Appellate Division was pending “ the respondents filed a notice of mechanic’s lien to save their interests from being jeopardized by the delays in the arbitration proceeding, and thereafter appellant made another motion to vacate the order of the Special Term directing arbitration, on the ground that the respondents had filed notices of lien,” [506]*506(Matter of Askovitz, supra, p. 259.) When that motion was denied, the second appeal was taken to the Appellate Division and the court said (pp. 259, 260-261):

“ The appellant’s claim on the first motion and on the former appeal to this court was that the filing of mechanics’ liens against the appellant’s premises by subcontractors had operated as a waiver of the respondents ’ rights under the arbitration clause and as a release of the appellant’s obligation thereunder. This court affirmed the order denying the former motion on the ground that there was no proof that mechanics’ liens had been filed by the contractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Arbitration between Allstate Insurance & Winter
75 Misc. 2d 795 (New York Supreme Court, 1973)
Modular Technics Corp. v. Graverne Contracting Corp.
40 A.D.2d 996 (Appellate Division of the Supreme Court of New York, 1972)
Sommer v. Anthony J. Quarant Contracting, Inc.
40 A.D.2d 95 (Appellate Division of the Supreme Court of New York, 1972)
Sowalskie v. Cohoes Housing Authority, Inc.
69 Misc. 2d 665 (New York Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
50 Misc. 2d 502, 270 N.Y.S.2d 716, 1966 N.Y. Misc. LEXIS 1839, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-manitt-construction-corp-j-s-plumbing-nysupct-1966.