In re the Arbitration between Klineman & NJS Inc.

160 Misc. 2d 774, 611 N.Y.S.2d 729, 1993 N.Y. Misc. LEXIS 596
CourtNew York Supreme Court
DecidedMay 7, 1993
StatusPublished
Cited by5 cases

This text of 160 Misc. 2d 774 (In re the Arbitration between Klineman & NJS Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Klineman & NJS Inc., 160 Misc. 2d 774, 611 N.Y.S.2d 729, 1993 N.Y. Misc. LEXIS 596 (N.Y. Super. Ct. 1993).

Opinion

[775]*775OPINION OF THE COURT

Stanley L. Sklar, J.

Can a home improvement contractor, which was unlicensed at the time a contract was solicited and executed, collect for work performed under the contract after the contractor’s license application has been accepted by the Department of Consumer Affairs (the Department)? I hold that the contractor can collect for such work if the homeowners have ratified the contract after the contractor’s license application has been accepted.

Petitioners Kent Klineman, an attorney, and Hedy Kline-man move pursuant to CPLR 7503 (b) to permanently stay the arbitration demanded by respondent NJS Incorporated on the ground that the construction contract containing the arbitration clause is void and unenforceable because of the alleged failure of NJS and its predecessor to comply with the licensing requirements imposed by Administrative Code of the City of New York § 20-385 et seq. NJS cross-moves to compel arbitration.

The construction contract at issue was entered into by petitioner and NJS’ predecessor, nonparty PVS, Incorporated, on January 29, 1990 when petitioners retained PVS to perform extensive construction and remodeling work on their condominium home located in Manhattan. The contract was executed by nonparty Patrick V. Stolmeier, as PVS’ president. Stolmeier is also president of NJS.

PVS began work on petitioners’ home in January 1990. Petitioners began making progress payments under the contract in April 1990. On September 18, 1990 PVS filed for a home improvement contractor’s license and was given a license number by the Department which deems a party licensed once its application has been accepted (see, Department of Consumer Affairs, letter of Jan. 14, 1993). On that same date PVS and the Klinemans executed a document which, by its express terms, amended and expanded the January 29, 1990 contract to include PVS’ license number. A license was issued to PVS on October 2,1990.

In August 1990 Stolmeier created NJS, and on November 9, 1990 NJS filed for a home improvement license. According to Stolmeier, based on Klineman’s legal advice NJS was formed at Klineman’s behest and the contract assigned to NJS to avoid "problems” on the Klinemans’ project arising from a possible execution on a judgment against PVS in an unrelated [776]*776matter which allegedly could have had an adverse impact on the work being performed for the Klinemans. The exact nature of these problems is not revealed and is difficult to envision since a home improvement contractor is required to deposit all payments in accordance with Lien Law § 71-a (4) or to post a bond or contract of indemnity in lieu of the bond. Klineman denies that the incorporation of NJS and the assignment of the contract were based on reliance on his "legal” advice since Stolmeier had his own attorney. Stolmeier represents that subsequent to NJS’ filing and NJS’ receipt of a formal license issued on November 27, 1990, PVS assigned the modified contract to NJS and NJS began work on the project.

At some point a dispute arose concerning almost $650,000 in previously billed labor and expenses which petitioners allegedly improperly refused to pay. NJS demanded arbitration before the AAA under the "January 29, 1990” contract prompting petitioners to file the instant petition to stay.

Petitioners contended in their initial papers that the contract, including the arbitration clause, was void and unenforceable at its inception because PVS had not obtained a home improvement contractor’s license prior to soliciting, obtaining and commencing performance of the contract; nor had PVS even applied for a license until about eight months after signing the contract and commencing work under it. Petitioners also urged that the contract was void even if they were aware of and took advantage of the contractor’s status. Petitioners further asserted that the void contract was not revived or superseded by the September 1990 amendment which they signed with PVS. In addition, petitioners claimed, notwithstanding that the September 1990 amendment was executed by PVS, rather than by NJS, and that PVS had sent invoices to petitioners in October and December 1990 for work through September and November 1990 respectively, that NJS did not assume the contract after it filed for and received its license in November 1990 but, rather, assumed it in August 1990 as evidenced by the fact that the Klinemans had made their first payment to NJS on August 23, 1990. The Kline-mans also noted that no copy of the alleged assignment has been provided. The Klinemans maintained, inter alia, that because NJS was unlicensed when it assumed the contract it could not enforce that contract. Finally, the Klinemans asserted that because the contract, including its arbitration clause, was unenforceable, even if NJS could collect in quantum meruit for work performed after it was licensed (see, [777]*777Matter of Hirsch Constr. Corp. [Cooper], 181 AD2d 52, 57 [1st Dept 1992]; Todisco v Econopouly, 155 AD2d 441, 442, lv dismissed 76 NY2d 772), this application to stay arbitration must be granted, and NJS would be relegated to an action at law.

NJS in opposition claimed that the agreement had not been assigned and that it did not begin to perform work under the agreement until after it received its license in November 1990. NJS claimed that Klineman made checks payable to NJS before that time so as to "conceal the fact that PVS was working on the project” and to "shield [Klineman’s] project from any interruptions in construction which might arise from execution on a judgment which might be obtained against PVS in an unrelated lawsuit.”

NJS, relying on Beacon Term. Corp. v Chemprene, Inc. (75 AD2d 350 [2d Dept 1980], lv denied 51 NY2d 706), also asserted that the amendment of the January 1990 contract in September 1990 which added, inter alia, PVS’ license number, constituted a new agreement, and that because at the time of the new agreement PVS was deemed licensed by the Department, it and its assignee, which was licensed when it assumed the contract, were entitled to collect for any work performed under that new agreement. NJS does not assert that there was a novation in September 1990.

The issue is can NJS seek to enforce the contract in arbitration?1 The determination of whether a contract is unenforceable on public policy grounds may be made by the court on an application for a stay of arbitration. (Matter of Hirsch Constr. Corp. [Cooper], 181 AD2d 52, 57 [1st Dept 1992], supra; Hirsch v Hirsch, 37 NY2d 312, 315 [1975].)

Section 20-387 (a) of the Administrative Code provides in its entirety that "No person shall solicit, canvass, sell, perform or obtain a home improvement contract as a contractor or sales[778]*778person for an owner without a license therefor.” The violation of this provision constitutes a misdemeanor punishable by imprisonment. (Id., § 20-401; cf., Mortise v 55 Liberty Owners Corp., 102 AD2d 719 [1st Dept 1984], affd 63 NY2d 743.) The purpose of the foregoing licensing requirement is to "protect the homeowner against abuses and fraudulent practice.” (Administrative Code § 20-385; see also, B & F Bldg. Corp. v Liebig,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nemard Construction Corp. v. Deafeamkpor
21 Misc. 3d 320 (New York Supreme Court, 2008)
Davidson v. Hensen
135 Wash. 2d 112 (Washington Supreme Court, 1998)
Fong v. Johnson
212 A.D.2d 457 (Appellate Division of the Supreme Court of New York, 1995)
Mindich Developers, Inc. v. Milstein
164 Misc. 2d 71 (New York Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
160 Misc. 2d 774, 611 N.Y.S.2d 729, 1993 N.Y. Misc. LEXIS 596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-klineman-njs-inc-nysupct-1993.