In re the Arbitration between Granite Worsted Mills, Inc. & Aaronson Cowen, Ltd.

29 A.D.2d 303, 287 N.Y.S.2d 765, 5 U.C.C. Rep. Serv. (West) 98, 1968 N.Y. App. Div. LEXIS 4521
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 29, 1968
StatusPublished
Cited by6 cases

This text of 29 A.D.2d 303 (In re the Arbitration between Granite Worsted Mills, Inc. & Aaronson Cowen, Ltd.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Granite Worsted Mills, Inc. & Aaronson Cowen, Ltd., 29 A.D.2d 303, 287 N.Y.S.2d 765, 5 U.C.C. Rep. Serv. (West) 98, 1968 N.Y. App. Div. LEXIS 4521 (N.Y. Ct. App. 1968).

Opinions

Rabin, J.

The question posed by this appeal is whether the arbitrator of the dispute between the parties exceeded his powers in awarding the sum of $3,780.51 to the appellant on its claim of defective goods. Special Term thought he did; vacated the award and remitted the matter to the arbitrator for further proceedings.

These proceedings are the result of two sales by Granite Worsted Mills, Inc., (herein referred to as the respondent) to Aaronson Cowen, Ltd., (now known as I. Aaronson, Ltd., and hereinafter referred to as the appellant) of certain cloth goods to be used by the appellant in the manufacture of sport coats. The goods were so used. Subsequently, after its complaint that the goods shipped proved to be defective had been rejected, the appellant demanded arbitration.

The matter proceeded to arbitration before an arbitrator experienced in the textile field. Although in its demand for [305]*305arbitration the appellant claimed the sum of $7,313.20 as its damage, the arbitrator awarded the sum of $3,780.51, plus administration fees. It is the respondent’s position that in making an award in an amount greater than $938.64 — the purchase price of the goods shipped — the arbitrator exceeded his powers because, as it asserts, the contract limited the damage at its maximum to such amount.

Apparently, the arbitrator considered the clause relied on by the respondent, not as a limitation of liability but rather as an attempt to so limit it.

In determining the question involved we need but examine two clauses of the two sales contracts, pursuant to which the sales were made. The first is the arbitration clause, the pertinent part of which is as follows: “12. arbitration, Any controversy or claim arising out of or relating to this contract shall be settled by arbitration.”

The clause is a broad one and contains no restrictive provision. As such, the arbitrator was given the power to consider all of the clauses of the contract in determining the controversy between the parties. Of necessity the arbitrator had to decide what effect should be given to the entirely separate paragraph of the contract entitled “ defective goods ” which is the second clause that calls for our consideration. We set it forth in full. “ 6. defective goods. No goods shall be returned by Buyer unless such return is authorized by Seller. No goods shall be returned nor allowance made, unless defective. Buyer shall be deemed to have accepted goods and his right to reject or claim damages for breach of warranty or otherwise shall expire 15 days after invoice date. Notwithstanding the foregoing, sponging, cutting or otherwise processing goods constitutes final acceptance and waiver of any defect in the goods. If within 15 days after invoice date and before the goods have been sponged, cut or otherwise processed, Buyer notifies Seller in writing of a claimed defect, Buyer shall, together with his notice of claim, offer Seller, in writing, prompt opportunity to examine the goods. Failure to do so constitutes acceptance and waiver of all claims for defects. If Seller determines claim to be valid, it or Mills may replace defective goods within a reasonable time. In such event Seller or Mills shall not be liable for any damages arising from the defective delivery or the delay caused thereby. Buyer shall not be entitled to claim or recover consequential damages for defective goods (whether the defect be latent or otherwise), nor for manufacturing, processing or selling expenses or for the loss of contemplated use or profits; and in all events Buyer’s damages shall not exceed the difference [306]*306in value on date of delivery between goods specified and goods actually delivered.”

In the light of these clauses can we say that the arbitrator, in making the contested award, exceeded his powers (see CPLR 7511, subd. [b], par. 1, cl. [iii]), or that he gave a “ completely irrational construction to the provisions in dispute an, in effect, made a new contract for the parties ” ? (Matter of National Cash Register Co. [Wilson], 8 N Y 2d 377, 383.)

Any such conclusion can only be based on the amount of damages awarded. In relation to that question, appellant maintained that the clause was unconscionable and should not be enforced. It likewise asserted that the custom and usage in the textile industry was such that clauses of this nature are never given effect.

Of course, we do not know the bases for the arbitrator’s decision. But, considering the arguments presented here, and at Special Term, it is quite clear that the arbitrator, in essence, did no more than a court of law could do in the circumstances. Courts are often presented with questions of whether a given clause is unconscionable and should not be enforced. Indeed, questions concerning the enforcibility of stipulations limiting liability often arise, and courts have disregarded such provisions under various circumstances. (E.g., Rappaport v. Phil Gottlieb-Sattler, Inc., 280 App. Div. 424, affd. 305 N. Y. 594; Klar v. H. & M. Parcel Room, 270 App. Div. 538, affd. 296, N. Y. 1044.)

The respondent, however, argues that different rules of law apply to unconscionability in commercial cases as opposed to situations involving consumers, where clauses limiting liability are presumptively unconscionable. (Uniform Commercial Code, § 2-719, subd. [3].) That is quite so and, indeed, it is quite possible — although not without doubt in view of the highly restrictive and seemingly unfair provision with respect to latent defects — that a court of law would not have found the clause in issue here unconscionable. Nevertheless, the mere statement of the issue — whether a clause is or is not unconscionable — presents a matter for factual determination. And this was recognized by Special Term, which held that ‘ ‘ the limitation of damage is not unconscionable in the circumstances here ”. However, “ the circumstances here” were for the arbitrator, and the arbitrator only, to evaluate, and he alone had the power to determine unconscionability.

While it might be argued that the court would never have come to the same conclusion, either with respect to the applicable rules of law, or as to what the facts were, this is irrelevant. The arbitrator’s award is not reviewable by the court of errors of [307]*307law or fact. (Matter of Colletti, 23 A D 2d 245, 248, affd. 17 N Y 2d 460; Matter of Shevell [Besen], 29 A D 2d 751.)

The same principles are equally applicable to the other arguments in the attempt to show usurpation of power. For example, if there were — as seems to have been urged — a custom and usage prevailing in the industry concerning the effect of such a highly restrictive clause, clearly, the arbitrator had the power to consider and give effect to such custom. Indeed, a myriad of arguments could be made with reference to the enforcibility or interpretation of the clause in question, i.e., should the limitation be applied to latent defects? Would that be unconscionable? Would it be contrary to custom and usage? On the other hand it is quite possible — although there is nothing in the record to indicate it — that the arbitrator found a course of conduct on the part of the respondent that would constitute a waiver of the clause relied on.

All the questions concerning the clause were presented to the arbitrator. These questions of necessity had to be considered in consequence of the demand for the sum of over $7,000 contained in the submission — a sum far in excess of the purchase price of the goods shipped.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ebasco Services, Inc. v. Pennsylvania Power & Light Co.
460 F. Supp. 163 (E.D. Pennsylvania, 1978)
Johnson v. Mobil Oil Corp.
415 F. Supp. 264 (E.D. Michigan, 1976)
Kohlenberger, Inc. v. Tyson's Foods, Inc.
510 S.W.2d 555 (Supreme Court of Arkansas, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
29 A.D.2d 303, 287 N.Y.S.2d 765, 5 U.C.C. Rep. Serv. (West) 98, 1968 N.Y. App. Div. LEXIS 4521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-granite-worsted-mills-inc-aaronson-cowen-nyappdiv-1968.