In re the Arbitration between Colasante & Bridgehampton Road Races Corp.

16 Misc. 2d 923, 185 N.Y.S.2d 203, 1959 N.Y. Misc. LEXIS 4275
CourtNew York Supreme Court
DecidedFebruary 19, 1959
StatusPublished
Cited by1 cases

This text of 16 Misc. 2d 923 (In re the Arbitration between Colasante & Bridgehampton Road Races Corp.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Colasante & Bridgehampton Road Races Corp., 16 Misc. 2d 923, 185 N.Y.S.2d 203, 1959 N.Y. Misc. LEXIS 4275 (N.Y. Super. Ct. 1959).

Opinion

J. Irwin Shapiro, J.

Motion by the petitioner for an order confirming an arbitration award in his favor. Cross motion by respondent to vacate said award or, alternatively, to modify and correct the same.

After buying a large plot of land respondent entered into negotiations with petitioner which culminated in a contract between the parties dated September 27, 1956. The contract required the petitioner to construct, from unused woodland, a complete road-racing plant, consisting of a three-mile circuit, administration building, spectator parking area, access roads, toll booths and other necessary racing and spectator facilities, for the sum of $254,200. The original contract was modified and in part superseded by later contracts between the parties, dated March 27,1957, and June 6, 1957.

Petitioner performed a substantial part of the work required by these contracts, but in and about September, 1957 a number of disputes developed between the parties in which petitioner claimed that he had not been paid for some of the work he did under the contracts, or for any of a large quantity of extra work he claimed to have done, and in which respondent claimed that petitioner had not performed his contracts and in which it denied that he had been asked to do or had done any extra work.

The contracts between the parties provided for the arbitration of disputes arising under the contracts by the American Arbitration Association. Accordingly, on February 10, 1958, respondent, by a notice in writing, alleged that it had been damaged in the sum of $178,107.49, by the petitioner’s actions and demanded arbitration of its claim.

Petitioner submitted an ‘‘ answer and counterclaim ’ ’ alleging that he had been damaged in the sum of $149,898.57, by reason of respondent’s actions.

As required by the contracts and under the rules of the American Arbitration Association, three arbitrators were selected and agreed upon by the parties, and hearings were held before them on 15 separate days commencing on April 15, 1958, and terminating on November 15, 1958. A unanimous award resulted in favor of petitioner. Its exact terms are not germane to this decision, except as to item 5 thereof, the effect and meaning of which will be hereafter discussed.

The respondent, by its cross motion, now seeks to vacate or, in the alternative, to modify and correct the award upon various grounds. We shall discuss its contentions seriatim.

The first point upon which respondent asks this court to vacate the award of the arbitrators is that they were guilty [925]*925of misconduct and misbehavior in refusing to make an inspection of the premises where the construction work was done, which led to all the disputes involved in the arbitration proceeding. Respondent’s moving affidavit contends that such refusal on the part of the arbitrators was objected to by it. Its counsel says: “ Prior to the commencement of the arbitration hearings I discussed with the attorneys for petitioner the desirability of arranging that the arbitrators travel to respondent’s property near Bridgehampton, Long Island where the contract work had been done. We agreed that it would be impossible, or next to impossible, for the arbitrators to understand the testimony and adjudicate the disputes fairly unless they made an inspection of the property early in the proceedings. Accordingly at each of the first hearings both Mr. Boyers and I requested that an inspection be held and commenced discussions as to how it could best be done; in fact we offered to supply Carey limousines to take the entire party out and back, which we thought would occupy the better part of a day. When each such request was made, the arbitrators agreed that it would be desirable to do this as requested by both parties. However, they were unwilling to fix any specific time. During one of the hearings when the subject was again renewed, the arbitrators indicated that they had made up their minds that inspection of the property by them was not necessary and that they would not agree to travel to Bridgehampton to make such an inspection. At that time counsel on both sides of the table objected and earnestly requested the arbitrators to reconsider but the arbitrators announced that their decision not to make an inspection was final.”

The petitioner’s attorney, however, says that the respondent’s version of the demand upon the arbitrators to inspect the work and their refusal is incorrect. He says ‘ that the arbitrators stated at the beginning of the proceeding that if they saw fit and if they felt it necessary, that they would visit the property in question. It was their opinion, however, after submission into evidence of all photographs, aerial photographs, overlays, cross-sections, earthwork tabulation sheets, transparencies, etc. of the property in question, they could arrive at their determination without making a personal trip to the site. This was the unanimous opinion of all three of the arbitrators and they so advised the attorneys representing both the petitioner and the respondent. No one voiced any objection when the arbitrators announced their decision not to visit the property in question because they had sufficient photographs and documents [926]*926to apprise them, of the information needed to decide all the issues involved.”

While it is true that the matters before the arbitrators for decision turned upon the nature and quality of the work done by petitioner in performance of his contracts with respondent, and that the work required by the contracts was extensive and was perhaps somewhat unusual in that it involved the conversion of woodland into an entire plant designed to serve the needs of both automobile racing competitors and large crowds of spectators, the court has been unable to find any case which sustains respondent’s views that the failure to view premises or to make an inspection of work involved is cause for setting an award aside. Certainly a judge, sitting as a trier of the facts in a regularly constituted court, could not be required to make an inspection under the circumstances here prevailing. The rule can be no different in the case of an arbitrator or arbitrators.

In American and English Annotated Cases (Yol. 8 [1908], p. 511), an old English ease is summarized as follows: “ Where the dispute referred to arbitrators concerned the condition of a building, and the master was requested by one of the parties to go and inspect the premises, upon a motion made to set aside the award because of the failure of the master to view the building, Erie, O. J., said: 1 know no law which makes it imperative on the master or any other arbitrator to go and look at the premises. It is entirely a matter for his discretion. There will consequently be no rule. ’ The rest of the court concurring, the rule was refused. Munday v. Bluck, 9 C. B. N. S. 557, 99 E. C. L. 557.”

In Matter of Avila Fabrics (135 N. Y. S. 2d 182 [1954]), Mr. Justice Cavagax, sitting in New York County Special Term, denied a motion to vacate an arbitrators’ award which was predicated upon the arbitrators’ refusal to visit a warehouse to inspect the allegedly damaged merchandise involved in the dispute with this language (p. 183): “Where, as here, the arbitrators received what they unquestionably considered some evidence of the controversial issue [a purported sample of light goods] but refused to adopt the petitioner’s unusual recommendation to view at. a place away from the hearing other evidence on that issue, then the arbitrators ’ admission or denial of evidence is not subject to review by this court.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Arbitration between Big-W Construction Corp. & Horowitz
24 Misc. 2d 145 (New York Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
16 Misc. 2d 923, 185 N.Y.S.2d 203, 1959 N.Y. Misc. LEXIS 4275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-colasante-bridgehampton-road-races-corp-nysupct-1959.