In re the Arbitration between Baker & Board of Education

13 Misc. 2d 922, 175 N.Y.S.2d 360, 1957 N.Y. Misc. LEXIS 2362
CourtNew York Supreme Court
DecidedOctober 16, 1957
StatusPublished

This text of 13 Misc. 2d 922 (In re the Arbitration between Baker & Board of Education) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Arbitration between Baker & Board of Education, 13 Misc. 2d 922, 175 N.Y.S.2d 360, 1957 N.Y. Misc. LEXIS 2362 (N.Y. Super. Ct. 1957).

Opinion

David H. Shearer,

Arbitrator. This is an arbitration proceeding between Ervay J. Baker, White & Helm, and the Board of Education of Central School District No. 2 of the Towns of Bath, et al., Steuben County, New York, in which the undersigned was designated and appointed as arbitrator to act under a contract between the parties with the same force and effect as if he had been named arbitrator therein, by order of the Special Term of the Supreme Court made the 14th day of June, 1956. The contract between the parties is an agreement between Owner and Architect made the 12th day of July, 1951 by and between the Board of Education of Central [925]*925School District No. 2 of Bath, New York, therein called the Owner, and Ervay J. Baker of Hammondsport, New York, and Thomas Lynn White and F. Kirk Helm, doing business as White & Helm of Geneva, New York, therein called the Architect. Section 12 thereof is as follows: “ 12. Arbitration. All questions in dispute under this agreement shall be submitted to arbitration at the choice of either party.”

During the course of the construction, which was the subject matter of said agreement, a dispute arose between Baker, one of the architects, and the Board of Education, as owner. Subsequently, Baker served two demands for arbitration, one in his own name, and one in the joint names of Baker and White & Helm. Litigation with respect to Baker’s right to arbitration ensued with the result that the Court of Appeals in Matter of Baker (Board of Educ.) (309 N. Y. 551) finally determined that Baker was entitled to arbitration. Thereafter the order of the Special Term referred to above was made, appointing the undersigned as arbitrator. In both demands for arbitration Baker alleged claims only against the Board of Education. At the hearings, however, Baker broadened his claims so as to include not only his claim against the Board of Education but also whatever claim he might have against White & Helm. At the outset of the hearings, the Board of Education filed a statement of its claims against the Architect under the agreement referred to above dated July 12, 1951, included both Baker and White & Helm as the Architect and expressly stated its claim against both Baker and White & Helm for any damages it may have sustained. At the commencement of the hearings, White & Helm took the position that any claims between Baker, on the one hand, and White & Helm, on the other, were outside the scope of this arbitration. The arbitrator held that no such limit had been placed on the scope of the arbitration by the order appointing him, that the language of section 12 of the contract was broad enough to include all such claims, and that in the absence of any direction of the court so limiting the scope of the arbitration, the arbitrator would not so limit the proof. Thereafter White & Helm put in proof of the damages they claim to have sustained but stated that they were making no claim against anyone except as an offset against any claim that might be made against White & Helm.

A written stipulation waiving the taking of the oath by the arbitrator was entered into by all the parties. A further written stipulation was made that the fee of the arbitrator be $100 for each day spent in the business of the arbitration, plus [926]*926expenses, and that the award may require the payment by any party of the arbitrator’s fee and expenses. The hearings were begun on July 24, 1956 and continued intermittently on 22 separate days until December 19, 1956. One hundred sixty-eight exhibits were received in evidence and the transcript of testimony totalled 2,644 pages. The matters involved were thoroughly briefed by attorneys for the parties and in August, 1957 the matter was finally submitted to the arbitrator for his award.

On July 12,1951 the Board of Education entered into an agreement dated that day with Baker and White & Helm for architectural services for such building or buildings and alterations as may be necessary to house a portion of the school and its equipment” and agreed to pay the architects a fee of 6% of the cost of the work. On the same day Baker and White & Helm entered into an agreement between themselves by which they agreed to divide the work so that Baker would do the design, White & Helm the working drawings, and Baker the supervision, each to receive a total of 3%, or one half of the total fee of 6%. Thereafter several schemes for the building of the new junior-senior high school and bus garage and for the remodeling of the existing school were proposed and taken up with the State Education Department. An application for examination and approval of preliminary plans was filed wdth the State Education Department April 24, 1952. On June 5, 1952 the proposition was submitted to the voters of the Haverling Central School District. In the proposed $2,750,000 bond issue were included a new 800-pupil junior-senior high school, a bus garage, and a remodeling of the existing building to house 1,200 pupils, kindergarten through sixth grade. A separate proposition of $185,000 for a swimming pool was included, making the total $2,935,000. The swimming pool proposition was defeated. The remainder were approved. Working drawings were then prepared by White & Helm and the plans and specifications were submitted for bids. John Banner & Associates was the low bidder for the general contract and an agreement dated February 18, 1953 was entered into between John Banner & Associates and the Board of Education for the general contract on the junior-senior high school and bus garage totalling $1,346,000, the bus garage to be completed by September 1, 1953, the high school by September 1, 1954 (Exhibit 4).

The construction seems to have proceeded satisfactorily until August, 1953. Banner was then about two months ahead of schedule. At this point trouble developed between Kinner and [927]*927Baker, the supervising architect. Much proof was presented at the hearings by all parties to bring to light the facts as they occurred. It is evident that a so-called clash of personalities developed. Baker, relatively limited in his experience in supervision of a construction project of this size, adopted arbitrary methods in dealing with construction defects which he discovered upon inspection. Kinner, the contractor, admitted the defects to others but was quick to take offense at Baker’s methods. Neither sought to conciliate the other with the result that what might have been a harmless spark turned into a conflagration. It must be concluded that both Baker and Kinner were responsible for the trouble which ensued. On August 18, Kinner appeared before the Board of Education and stated Ms grievances against Baker. Baker advised the board that Kinner’s work was defective and continued his efforts to amass proof of the same. The board at first sided with Baker. Kinner took further offense at this. On August 25, Banner served formal notice to arbitrate. On the same day Banner submitted Requisition No. 6 for progress payment in the amount of $81,889.80 for work done from July 27 to August 28. Baker issued stop-work orders on August 27 and on September 8 on the basis that Kinner had given notice of intention to pour a concrete slab in each ease over fill improperly compacted. In the meantime, Baker was assembling his experts to prove Banner was wrong (Goodwin, Metcalf, Hough) and was sending Kinner a multiplicity of letters regarding defects in the work (six letters).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fudickar v. . Guardian Mutual Life Ins. Co.
62 N.Y. 392 (New York Court of Appeals, 1875)
Elizabeth Sash, Door & Supply Co. v. Saint Vincent's Hospital
241 A.D. 751 (Appellate Division of the Supreme Court of New York, 1934)
Everett v. Brown
120 Misc. 349 (New York Supreme Court, 1923)
In re the Arbitration between Baker & Board of Education
309 N.Y. 551 (New York Court of Appeals, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
13 Misc. 2d 922, 175 N.Y.S.2d 360, 1957 N.Y. Misc. LEXIS 2362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-baker-board-of-education-nysupct-1957.