In re Tamarac Utilities, Inc.

45 Fla. Supp. 164
CourtFlorida Public Service Commission
DecidedApril 27, 1977
DocketDocket No. 74173-WS(CR). Order No. 7788
StatusPublished
Cited by1 cases

This text of 45 Fla. Supp. 164 (In re Tamarac Utilities, Inc.) is published on Counsel Stack Legal Research, covering Florida Public Service Commission primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Tamarac Utilities, Inc., 45 Fla. Supp. 164 (Fla. Super. Ct. 1977).

Opinion

BY THE COMMISSION.

Pursuant to notice the commission by its duly designated hearing examiner, Harold E. Smithers, held a public hearing on this matter in Fort Lauderdale on August 31, 1976.

The examiner’s recommendations were filed and served on October 21, 1976. The parties filed timely exceptions. Oral argument thereon, by Tamarac President’s Council and the applicant, was heard on February 14, 1977. Having considered all the evidence, we now enter our order.

On March 18, 1974 Tamarac Utilities, Inc. filed this request for an increase in water and sewer rates for its systems in Broward County. Public hearings were held on December 3 and 4, 1974 and April 3 and 4, 1975.

On January 15, 1975 we issued Order No. 6461, allowing the utility to increase its rates so as to provide gross annual revenues of $861,072 and $694,025 for water and sewer service, respectively, on an interim basis.

On September 9, 1975 we issued Order No. 6891, in which we determined the rate base, revenues, expenses and cost of capital of the utility. However, because we believed the utility had not adequately documented all of its contributions-in-aid-of-construction, we imputed CIAC based on the best information available; continued the interim rates authorized in Order No. 6461, and further required —

. . that the utility shall within ninety days from the date hereof file a schedule, certified by a certified public accountant, setting forth by year and contributor all contributions in aid of construction reecived by the company, including, but not limited to, payments received under developer contracts, lines and/ or plant facilities received by the utility as a donation from any source. The report will also include a statement as to the amount of lines and/or plant facilities transferred to the utility by the respective parent companies other than as a contribution which was written off by the respective parent companies as development costs for federal income tax purposes.”

Pursuant to the above mandate, the utility filed the report (Ex. 1 to the August 31, 1976 hearing). A motion to strike the report, as well as motions to take depositions and to have a rehearing, were filed by the intervenors.

In Order No. 7120, issued February 19, 1976, we restated and clarified our requirement to review the accounting report on CIAC [166]*166submitted by the utility. In that order, we disposed of the motions of the intervenor, Tamarac President’s Council, for reasons fully described in that order, and directed a further hearing limited as noted below.

The public hearing

The purpose of this hearing was to review the audit report containing “by year and contributor, all contributions in aid of construction received by the company . . . including . . . payments . . . lines and/or plant facilities received .. . from any source.” (Order No. 6891.)

The utility prefiled Exhibit 1 to enable our auditing staff to review and verify the information therein.

The utility witness (Mr. Brandt) was a certified public accountant of Price, Waterhouse Co. (“PW”), a private accounting firm retained specifically to prepare the report. We believe it is a fair summary of his testimony to state that the utility prepared schedules by years 1968 to 1972 (tr 1066) inclusive, from Account 271 (tr 1079). PW took the schedules and verified those figures against the utility-prepared schedules (tr 1066). PW reviewed all contracts for the sale of land (tr 1067), tested those in excess of $50,000 (tr 1137), and reviewed four developer agreements. These four agreements were the largest dollar apaounts and were all in excess of $5,000 in CIAC (tr 1067).

The witness stated that from the data PW compiled and reviewed, CIAC was computed in the utility schedules at $35 per lot up until some unknown date in 1971, and that after the unknown 1971 date, the CIAC was computed on the basis of $423.50 per acre (tr 1070). This does not represent an increase in charges but is merely the multiplying of the number of lots, per acre, by $35 per lot.

The sum and substance of the testimony and Exhibit 1 is that the total contribution paid to and recorded by the utiliy for the calendar years 1968 to 1972, inclusive, is $793,870.

Our staff auditor agreed that the CIAC shown in Exhibit 1 was in fact received by the utility (tr 1153). It is important to note that the auditor testified that there could be CIAC not reflected in Exhibit 1 and in excess of the $793,870.

We have reviewed the testimony and record of this hearing and the previous hearings on the rate application. Based on this, we believe that the PW audit is incomplete and that more CIAC exists than is shown in the audit.

[167]*1671. Order No. 6981 required a schedule setting forth all CIAC received by the company from any source. Exhibit 1 does not do that and, in fact, is basically a verification of a utility-prepared schedule (tr 1113, 1104) of Account 271 (tr 1082). Any errors made by the utility when it made its original entries would be carried through to the schedules used by PW. We do not believe this certified anything except those schedules.

2. PW did not use the utility tariff (tr 1083) nor the annual reports (tr 1108) in preparing Exhibit 1. Any audit would, of necessity, have to begin with those documents to determine if the utility schedules included all the connections made up to December 31, 1972 and whether each connection was charged the correct amount according to the tariff. Failure to use the tariff and annual report casts serious doubt on the completeness of the audit.

3. The number of developer agreements sampled by PW (four) was extremely small in comparison with the large number available. We note that in Docket No. 74844-WS (Service Availability Charges of Tamarac Utilities, Inc.) the utility filed 96 developer agreements of which 50 were dated prior to December 31, 1972. Even assuming that the 50 agréments are the total signed before December 31, 1972, a sample of 8% in this case, we believe, is too small.

4. In preparing Exhibit 1, PW reviewed the developer agreements for the total dollar amounts, rather than the basis on which those dollars were calculated (number of connections x connection fee (tr 1116). Further, the assumption inherent in Exhibit 1 is that the connection charges were either $35 per lot or $423.50 per acre, an assumption not supported by the facts as herein discussed.

In making the audit tests, PW used the $35 charge (tr 1070, 1132), based on total lots and compared that amount with the $793,870 booked as CIAC. Quite naturally, the two figures were substantially the same. However, Exhibit 3 shows that, in early 1971, the connection charge was increased at least twice from $35 to approximately $95, and then to $150 (see, for example, Ex. 7 in the previous hearings). We believe that the increases reflect a significant policy change in connection fees by the utility and that PW should have used the new connection charges (in conducting its test) beginning in 1971. Had it done so, it would have seen a significant difference between CIAC booked in Account 271 and the actual contribution policy of the utility. This failure lends further doubt as to the completeness of the audit.

In addition, there is evidence in this docket (Exhibit 7, previous hearings) that as early as April 1971, the utility substantially increased its CIAC. Exhibit 1 fails to show this change.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sarasota County v. Tamaron Utilities, Inc.
429 So. 2d 322 (District Court of Appeal of Florida, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
45 Fla. Supp. 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-tamarac-utilities-inc-flapubserv-1977.