In Re Sun Belt Electrical Constructors, Inc.

56 B.R. 686, 1986 Bankr. LEXIS 6886
CourtUnited States Bankruptcy Court, N.D. Georgia
DecidedJanuary 16, 1986
Docket19-51542
StatusPublished
Cited by7 cases

This text of 56 B.R. 686 (In Re Sun Belt Electrical Constructors, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Sun Belt Electrical Constructors, Inc., 56 B.R. 686, 1986 Bankr. LEXIS 6886 (Ga. 1986).

Opinion

ORDER

W. HOMER DRAKE, Bankruptcy Judge.

This case is presently before the Court on two motions. The first is a motion filed on October 8, 1985 by the debtor in possession, Sun Belt Electrical Constructors, Inc. (“Sun Belt”), to reject three executory contracts (“Guy Contracts”) involving Sun Belt, M & M Electric Supply, Inc. (“M & M”), and the Joe N. Guy Company, Inc. (“Guy”). The second motion is a motion filed on November 22, 1985 by M & M to enforce a contract (“Flagler Contract”) involving Sun Belt, M & M, and the Flagler Company (“Flagler”). M & M filed a response to Sun Belt’s motion to reject the Guy Contracts on October 18, 1985. This Court held a hearing on both motions on November 27, 1985, at which time the motions were taken under advisement. Letter briefs were submitted by Sun Belt on December 3, 1985 and December 5, 1985, by Flagler on December 4,1985 and December 6, 1985, and by M & M on December 4, 1985.

The Court must decide the following issues: (1) whether the Flagler Contract and the Guy Contracts are executory; (2) whether the Flagler Contract should be enforced; and (3) whether Sun Belt’s rejection of the Guy Contracts should be approved.

FINDINGS OF FACT

1. Sun Belt performed work as a construction contractor for Guy and for Fla-gler. In the course of this work, Sun Belt purchased electrical materials from M & M.

2. Pursuant to the Guy Contracts, Guy agreed to make payments for construction work by checks jointly payable to both Sun Belt and M & M. In return for this agree *688 ment, M & M agreed not to pursue its lien rights.

3. The Flagler Contract constitutes a similar agreement between Sun Belt, Flagler and M & M.

4. Guy is currently indebted to Sun Belt for construction work performed prior to the filing of Sun Belt’s bankruptcy petition on September 5, 1985. Under the terms of the Guy Contracts, Guy is to pay for this work with checks jointly payable to Sun Belt and M & M. In connection with the construction work giving rise to these obligations, Sun Belt became indebted to M & M for purchases of electrical materials.

5. Similarly, Flagler is indebted to Sun Belt for pre-petition construction work, and Sun Belt is indebted to M & M for purchases in connection with this work. Under the terms of the Flagler Contract, Flagler is to pay for this work with checks jointly payable to Sun Belt and M & M.

6. On October 3, 1985, counsel for Sun Belt informed counsel for M & M that Sun Belt rejects the Guy Contracts pursuant to 11 U.S.C. § 365.

7. Flagler’s subcontract agreement (“Fla-gler’s Subcontract Agreement”) with Sun Belt with respect to a project known as Northridge Phase IV provides that Flagler has the right to retain from progress payments owed to Sun Belt the amount of any claim or lien asserted against Flagler by other parties arising out of Sun Belt’s performance under the contract.

CONCLUSIONS OF LAW

Before addressing the enumerated issues, the Court notes a procedural deficiency in M & M’s motion to enforce the Flagler Contract. M & M’s motion apparently requests injunctive or equitable relief or, at least, a declaratory judgment. Under Bankruptcy Rule 7001, such relief may only be obtained in an adversary proceeding. For that reason, the Court will deny M & M’s motion without prejudice.

The Court observes, however, that the Flagler Contract and the Guy Contracts are virtually identical. The Court further observes that in ruling on Sun Belt’s motion to reject the Guy Contracts, the Court will examine the parties’ rights under the Guy Contracts. As a practical matter, the legal conclusions reached with respect to the Guy Contracts will be equally applicable to the Flagler Contract.

In order to avoid confusion with respect to this application, the Court will discuss the parties’ rights under the Flagler Contract, when the Court discusses the parties’ rights under the Guy Contracts.

Since the Guy Contracts and the Flagler Contract are essentially identical, the Court will consider the executory nature of both contracts in the following single discussion. The appropriate test for determining whether a contract is exec-utory appears to be the one proposed by Professor Countryman. Under that test, an executory contract is one in which the “obligations of both the bankrupt and the other party to the contract are so far unperformed that the failure of either to complete the performance would constitute a material breach excusing the performance of the other.” Lubrizol Enterprises, Inc. v. Richmond Metal Finishers, Inc. (In re Richmond Metal Finishers, Inc.), 756 F.2d 1043, 1045 (4th Cir.1985).

A failure on the part of Flagler or Guy to perform the obligation of issuing checks jointly payable to Sun Belt and M & M would clearly constitute a material breach. M & M’s duty to refrain from pursuing lien rights appears to be a continuing duty. Because some or all of those rights have expired, the Court will examine Sun Belt’s obligations.

Sun Belt's obligations under the contracts include a duty to endorse the jointly payable checks over to M & M to the extent that payment is due for electrical materials purchased in connéction with the construction work giving rise to the checks. The existence of this duty is apparent from the purposes of the contracts. The contracts were entered into by Sun Belt, M & M, Guy, and Flagler. The parties obviously intended that M & M would receive *689 payment out of the checks in return for not filing materialman’s liens. Interpreting the contracts in light of these purposes, it is apparent that the contracts impose on Sun Belt this duty of endorsing the checks over to M & M. Given this unperformed obligation on the part of Sun Belt, the Court concludes that the contracts are ex-ecutory.

Having found that the Flagler Contract is executory, the Court will determine whether it should be enforced. It appears that an executory contract is unenforceable against a debtor in possession who has not yet assumed the contract. Bordewieck, The Postpetition, Pre-Rejection, Pre-Assumption Status of an Executory Contract, 59 Am.Bankr.L.J. 197, 199 (1985). While this principle prevents the enforcement of the Flagler Contract against Sun Belt, it should not affect the enforcement of the contract against Flagler. In order to determine the effect of the Flagler Contract in light of this apparent conflict, the Court will examine the parties’ rights under it.

The Flagler Contract is affected by Fla-gler’s Subcontract Agreement. Under that agreement, Flagler may deduct any portion of the money otherwise due to Sun Belt to satisfy claims asserted against Flagler (or the premises upon which the work was performed) when those claims arise out of Sun Belt’s performance of the agreement. It follows that the amount owed by Flagler to Sun Belt should be reduced by the amount claimed by M & M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Spoverlook, LLC
560 B.R. 358 (D. New Mexico, 2016)
Code Electric, Inc. v. Crampton
197 B.R. 807 (E.D. North Carolina, 1996)
Wilson v. TXO Production Corp. (In Re Wilson)
69 B.R. 960 (N.D. Texas, 1987)
Matter of Dunes Casino Hotel
63 B.R. 939 (D. New Jersey, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
56 B.R. 686, 1986 Bankr. LEXIS 6886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-sun-belt-electrical-constructors-inc-ganb-1986.