In Re Southern Scrap Material Co., LLC

713 F. Supp. 2d 568, 2010 U.S. Dist. LEXIS 47855, 2010 WL 1961205
CourtDistrict Court, E.D. Louisiana
DecidedMay 14, 2010
DocketCivil Action 06-1860, 08-5026
StatusPublished
Cited by4 cases

This text of 713 F. Supp. 2d 568 (In Re Southern Scrap Material Co., LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Southern Scrap Material Co., LLC, 713 F. Supp. 2d 568, 2010 U.S. Dist. LEXIS 47855, 2010 WL 1961205 (E.D. La. 2010).

Opinion

ORDER AND REASONS

MARTIN L.C. FELDMAN, District Judge.

Before the Court are three motions by the United States: (1) motion for summary judgment on liability; (2) motion to dismiss or alternatively to sever and stay Southern Scrap’s counterclaims; and (3) motion for summary judgment and motion in limine regarding actual wreck removal costs. For the reasons that follow, the motion for summary judgment on liability is GRANTED; the motion to dismiss or alternatively sever and Stay Southern Scrap’s counterclaims is DENIED in part and GRANTED in part; and the motion for summary judgment and motion in limine is GRANTED in part and DENIED in part.

Background

This case arises from the well-known breakaway and sinking of Southern Scrap’s drydock in the Industrial Canal during Hurricane Katrina, and its subsequent removal by the United States Army Corps of Engineers.

The Drydock

Southern Scrap owns a metal recycling facility in New Orleans, which is located at *571 the junction of the Inner Harbor Navigational Channel (IHNC or Industrial Canal) and the Mississippi River-Gulf Outlet (MRGO). 1 In July of 2005, Southern Scrap purchased a modular drydock section, intending to recycle it for scrap metal. Once it was towed from Mississippi to New Orleans, the drydock, which was 220 feet long by 157 feet wide by 24 feet deep and displaced 3,868 tons, was secured at the Vessel Recycling Facility with multiple soft mooring lines forward and aft secured to concrete deadmen embedded in the bank, as well as four heavy anchor chains secured to concrete piers built into the bank. The anchor chains and mooring lines were secured initially to mooring bitts on the drydock, but as the mooring bitts were removed as part of the scrapping process, the lines were secured to and around steal beams within the drydock’s structural framework.

Hurricane Preparations

Sometime after August 16, 2005, during the course of cutting the drydock into pieces for recycling, Southern Scrap, had disconnected the mooring lines and turned the drydock around. On Friday, August 26, 2005, with Hurricane Katrina in the Gulf of Mexico, Southern Scrap personnel began preparations for the storm. Grant Judy (Southern Scrap’s supervisor of demolition) was instructed to reattach the four anchor chains to prepare the drydock for 6 to 10 feet of tides. Judy passed each of the four anchor chains through a hole cut into the drydock’s watertight bulkhead, looped each chain around a structural beam within the drydock’s framing, brought each chain back out through another hole cut into the drydock’s bulkhead, and then shackled each chain to itself using a 100-ton shackle. 2 On Saturday, August 27, the National Hurricane Center classified Hurricane Katrina as a Category 3 hurricane, which would strengthen over the next 24 hours and directly strike New Orleans. That same day, the Orleans Parish Levee District notified Southern Scrap that it was preparing to close the SI floodgate late that day, which would block road access into and out of Southern -Scrap’s facility. Southern Scrap had many tasks to complete in a limited amount of time, with limited personnel (all of whom had to evacuate) in advance of the storm. Southern Scrap employees had evacuated the facility by 6:00 p.m.

Hurricane Katrina

On Monday, August 29, 2005, Hurricane Katrina made landfall in southeast Louisiana as a Category 3 hurricane with sustained winds of 127 miles per hour. Katrina produced a storm surge up to 17 feet on Southern Scrap’s property at the junction of the Industrial Canal and MRGO; 3 at some point during the storm, the partially scrapped drydock broke free from its moorings, 4 crossed the Industrial Canal, *572 and partially sank against the northwest fender of the Florida Avenue Bridge. 5 Along with many other obstructions in the waterways, 6 the government considered the sunken drydock, which was allegedly struck by two different commercial tows, 7 a hazard to navigation and determined that it had to be removed immediately, on an emergency basis. 8

Drydock Removal

On September 3, 2005, the Corps hired Boh Bros, to clear all obstructions from Southwest Pass and the Industrial Canal, including the Southern Scrap drydock, for a fixed price not to exceed $500,000. Several days later, the Corps contacted Southern Scrap’s president, Joel Dupre, and asked him to remove the drydock (which, at the time, still had a barge on top of it). Dupre told the Corps that Southern Scrap could not do so because it did not have access to its drydock given the complete lockdown of New Orleans.

In mid-September 2005 the U.S. Army Corps of Engineers undertook to remove the drydock; Boh Bros. Construction Co. and its subcontractor, Bisso Marine, began salvaging the drydock. Two and a half months later, removal was completed on December 2, 2005. 9 Boh Bros, invoiced, and the Corps paid, more than $12 million for the removal of the obstructions from Southwest Pass and the Industrial Canal; the Corps contends that $9.3 million of *573 that total is attributed to the removal of the Southern Scrap drydock. The Corps sent a demand letter to Southern Scrap, seeking reimbursement for wreck removal costs pursuant to 33 U.S.C. § 409. Southern Scrap refused to pay, and this litigation ensued.

Procedural History

On April 11, 2006, Southern Scrap filed a limitation proceeding, seeking to limit its liability, pursuant to the Limitation of Liability Act, 46 U.S.C. § 30305, to the post-casualty value of the drydock. 10 In accordance with the Limitation of Liability Act, the Court entered an order enjoining the commencement or prosecution of all claims against Southern Scrap based on the dry-dock breakaway, and set a deadline for filing claims in the limitation proceeding. The United States, and four others, filed claims.

In December 2006, the United States requested that the Court lift its injunction so that it could pursue a separate Wreck Act claim against Southern Scrap. In April 2007 the Court granted the United States’ request. In re Southern Scrap Material Co., L.L.C., No. 06-1860, 2007 WL 1234995 (E.D.La. Apr. 26, 2007). Southern Scrap appealed. On August 25, 2008 the Fifth Circuit affirmed the Court’s ruling, expressly holding that the United States’ Wreck Act claim was not subject to the Limitation Act. In re Southern Scrap Material Co., LLC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atchafalaya Basinkeeper v. U.S. Army Corps of Eng'rs
310 F. Supp. 3d 707 (M.D. Louisiana, 2018)
Board of Commissioners v. Tennessee Gas Pipeline Co.
88 F. Supp. 3d 615 (E.D. Louisiana, 2015)
In re the Complaint of ENSCO Offshore Co.
9 F. Supp. 3d 713 (S.D. Texas, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
713 F. Supp. 2d 568, 2010 U.S. Dist. LEXIS 47855, 2010 WL 1961205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-southern-scrap-material-co-llc-laed-2010.