in Re Reliability Plans of Electric Utilities for 2017-2021

CourtMichigan Supreme Court
DecidedApril 2, 2020
Docket158308
StatusPublished

This text of in Re Reliability Plans of Electric Utilities for 2017-2021 (in Re Reliability Plans of Electric Utilities for 2017-2021) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
in Re Reliability Plans of Electric Utilities for 2017-2021, (Mich. 2020).

Opinion

Michigan Supreme Court Lansing, Michigan Chief Justice: Justices:

Syllabus Bridget M. McCormack Chief Justice Pro Tem: David F. Viviano Stephen J. Markman Brian K. Zahra Richard H. Bernstein Elizabeth T. Clement Megan K. Cavanagh

This syllabus constitutes no part of the opinion of the Court but has been Reporter of Decisions: prepared by the Reporter of Decisions for the convenience of the reader. Kathryn L. Loomis

In re RELIABILITY PLANS OF ELECTRIC UTILITIES FOR 2017–2021

Docket Nos. 158305 through 158308. Argued on application for leave to appeal November 7, 2019. Decided April 2, 2020.

The Association of Businesses Advocating Tariff Equity (ABATE) (Docket Nos. 158305 and 158306) and Energy Michigan, Inc. (Docket Nos. 158307 and 158308) each appealed an order of the Michigan Public Service Commission (MPSC) implementing MCL 460.6w. The MPSC order imposed a local clearing requirement on individual alternative electric suppliers. The name “alternative electric suppliers” reflects that these providers give consumers a choice (i.e., an alternative) about the upstream provider of their power; it has no relationship to renewable energy. The local clearing requirement represented the amount of capacity resources that were required to be in the local resource zone in which the electric supplier’s demand was served. Before MCL 460.6w was enacted, the MPSC did not impose a local clearing requirement on individual alternative electric suppliers; the Midcontinent Independent System Operator (MISO)—the regional transmission organization responsible for managing the transmission of electric power in a large geographic area—applied a local clearing requirement as a whole to the geographic area covered by MISO’s local clearing requirement. ABATE and Energy Michigan challenged the MPSC’s interpretation of MCL 460.6w, and Energy Michigan further asserted that the MPSC order improperly imposed new rules that were not promulgated in compliance with the Administrative Procedures Act (APA), MCL 24.201 et seq. The Court of Appeals, METER, P.J., and GADOLA and TUKEL, JJ., consolidated the appeals and reversed the MPSC’s decision, holding that no provision of MCL 460.6w clearly and unmistakably authorized the MPSC to impose a local clearing requirement on individual alternative electric suppliers and that the MPSC could impose a local clearing requirement only exactly as MISO does—on a zonal basis. 325 Mich App 207 (2018). Accordingly, the Court of Appeals concluded that the MPSC was not permitted to impose a local clearing requirement on any provider individually. Because the Court of Appeals held that MCL 460.6w did not provide the MPSC with the authority to impose a local clearing requirement on individual alternative electric suppliers, the Court of Appeals found it unnecessary to reach the question whether the MPSC’s decision concerning the local clearing requirement resulted in improperly imposed rules that were not promulgated in compliance with the APA. The MPSC and Consumers Energy Company sought leave to appeal in the Supreme Court, and the Supreme Court ordered and heard oral argument on whether to grant the applications or take other action. 504 Mich 894 (2019); 504 Mich 895 (2019). In a unanimous opinion by Chief Justice MCCORMACK, the Supreme Court, in lieu of granting leave to appeal, held:

MCL 460.6w imposes resource adequacy requirements on electric service providers in Michigan and delegates authority to the MPSC to plan for energy capacity in the retail market by setting and enforcing capacity obligations for all energy providers in the state. MCL 460.6w authorizes the MPSC to determine both the local clearing requirement and the planning reserve margin requirement with the same text; no statutory language imposes additional requirements or limitations on the MPSC for setting the local clearing requirement versus the planning reserve margin requirement. However, despite the identical language describing the MPSC’s authority for determining both elements of its capacity obligation, the Court of Appeals concluded that there was a difference based on its review of the entire statute. But that conclusion was unfounded; in fact, a contextual review of the statute supported the opposite conclusion. Furthermore, MCL 460.6w requires cooperation with MISO, not adopting MISO’s methodology for one capacity obligation only. Nor does the requirement that a capacity charge must coordinate with, and not conflict with, MISO’s planning process require the MPSC to duplicate MISO’s zonal local clearing requirement. Accordingly, the Court of Appeals misread MCL 460.6w when it read into the statutory text a requirement that the MPSC impose Michigan’s local clearing requirement using the same methodology MISO does. The Court of Appeals further misunderstood the differences between the wholesale and retail capacity markets when it held that the MPSC could not impose a local clearing requirement on alternative electric suppliers individually. The planning reserve margin requirement in MCL 460.6w includes no measure of in-zone resources as MISO’s does with its zonal resource credits; instead, MCL 460.6w accounts for in-zone capacity in the providers’ individual local clearing requirement. And the Court of Appeals did not make clear what the relevant “zone” would be in its interpretation of the local clearing requirement. If it meant that the MPSC could only impose a local clearing requirement that maps exactly onto MISO’s zonal measurement, that interpretation would make little sense given MISO’s zone geography and the MPSC’s authority. A contextual understanding of the MCL 460.6w capacity planning process and MISO’s process supports a plain reading of the statute. In requiring that each provider, including alternative electric suppliers, meet an individual local clearing requirement, the MPSC did what the statute required of it to ensure reliability of retail electric markets in Michigan. Accordingly, the Court of Appeals erred when it held that the MPSC could not impose a local clearing requirement on alternative electric suppliers individually.

Reversed and remanded to the Court of Appeals for further proceedings, including addressing whether the MPSC’s order complied with the APA.

©2020 State of Michigan Michigan Supreme Court Lansing, Michigan Chief Justice: Justices:

OPINION Bridget M. McCormack Chief Justice Pro Tem: David F. Viviano Stephen J. Markman Brian K. Zahra Richard H. Bernstein Elizabeth T. Clement Megan K. Cavanagh

FILED April 2, 2020

STATE OF MICHIGAN

SUPREME COURT

In re RELIABILITY PLANS OF ELECTRIC UTILITIES FOR 2017–2021.

ASSOCIATION OF BUSINESSES ADVOCATING TARIFF EQUITY,

Appellee,

v No. 158305

CONSUMERS ENERGY COMPANY,

Appellant,

and

MICHIGAN PUBLIC SERVICE COMMISSION, ENERGY MICHIGAN, INC., and MICHIGAN ELECTRIC AND GAS ASSOCIATION,

Appellees. ENERGY MICHIGAN, INC.,

v No. 158306

MICHIGAN PUBLIC SERVICE COMMISSION and MICHIGAN ELECTRIC AND GAS ASSOCIATION,

Appellees.

v No. 158307

MICHIGAN PUBLIC SERVICE COMMISSION,

CONSUMERS ENERGY COMPANY, ENERGY MICHIGAN, INC., and MICHIGAN ELECTRIC AND GAS ASSOCIATION,

2 ENERGY MICHIGAN, INC.,

v No. 158308

CONSUMERS ENERGY COMPANY and MICHIGAN ELECTRIC AND GAS ASSOCIATION,

BEFORE THE ENTIRE BENCH

MCCORMACK, C.J. In 2016, the Legislature passed Public Act 341 to ensure reliability of the state’s

electric grid. The act charged the Michigan Public Service Commission (MPSC), which

regulates retail electricity markets, with setting what are known as “capacity requirements”

for a four-year period. Those capacity requirements are imposed upon the state’s electricity

providers. MCL 460.6w. As explained below, “capacity” refers roughly to the electrical

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Complaint of Rovas Against Sbc
754 N.W.2d 259 (Michigan Supreme Court, 2008)
Clonlara, Inc v. State Board of Education
501 N.W.2d 88 (Michigan Supreme Court, 1993)
Consumers Power Co. v. Public Service Commission
596 N.W.2d 126 (Michigan Supreme Court, 1999)
Bank of America Na v. First American Title Insurance Company
878 N.W.2d 816 (Michigan Supreme Court, 2016)
Hughes v. Talen Energy Marketing, LLC
578 U.S. 150 (Supreme Court, 2016)
People of Michigan v. Carl Rene Bruner II
912 N.W.2d 514 (Michigan Supreme Court, 2018)
Rovas v. SBC Michigan
482 Mich. 90 (Michigan Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
in Re Reliability Plans of Electric Utilities for 2017-2021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-reliability-plans-of-electric-utilities-for-2017-2021-mich-2020.