In re Precision Tube Co.

2 Pa. D. & C.3d 1
CourtPennsylvania Environmental Hearing Board
DecidedAugust 29, 1975
Docketdocket no. 74-271-W
StatusPublished

This text of 2 Pa. D. & C.3d 1 (In re Precision Tube Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Environmental Hearing Board primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Precision Tube Co., 2 Pa. D. & C.3d 1 (Pa. Super. Ct. 1975).

Opinion

WATERS, Chairman,

This matter comes before the board as an appeal from the grant by the Department of Environmental Resources (hereinafter “DER”) of two permits to the Pennsylvania Department of Transportation (hereinafter “PennDOT”) to construct necessary culverts for stream crossings for the planned North Penn Expressway. The new State highway will cross the Wissahickon Creek near the property of Precision Tube Co., Inc., the intervenor herein, and because of the problems they expect this to create, including a drastic reduction in their water supply as well as for alleged statutory and constitutional violations, they oppose DER’s action.

FINDINGS OF FACT

1. Appellant, Precision Tube Co. (hereinafter [3]*3“Precision”) is a corporation conducting a business along the Wissahickon Creek in Upper Gwynedd Township, Montgomery County, near where the stream crossing of the proposed North Penn Expressway will be constructed.

2. Intervenor is the permittee PennDOT, which received two permits issued under The Water Obstruction Act from the predecessor of DER in 1971.

3. The permits were issued for portions of the construction of Legislative Route 782, commonly known as the North Penn Expressway (hereinafter “expressway”) a proposed four-lane limited access State highway, entirely State-funded, which is planned to go from Spring House to Kulpsville, Montgomery County, at a total cost of not less than $40,000,000 in 1974 dollars; the current status of funding is that no funds are yet budgeted for construction, but funds are available for right-of-way acquisition.

4. PennDOT made application to DER in 1970 for the permits here in controversy, and the exhibits C-6, P.D. 9, and A-2 must be taken collectively, due to microfilming problems of DER, to establish the contents of PennDOT’s application for these permits.

5. P.D. 9 includes the documents forwarded to DER for the 1970 application. This exhibit differs from appellant’s exhibit 2 which it alleges to be the application because of the missing stream profile and channel cross-section sheet.

6. Stream profiles and cross-sections were forwarded from PennDOT to DER as part of the application.

7. These stream profiles and cross-sections were missing from DER’s files for this permit application [4]*4and the Fish Commission reports in DER and PennDOT’s files differ.

8. DET had its records microfilmed and, upon receiving the microfilm, found sheets missing and found instances where the entire permit and documentation is missing. The stream profiles and cross-sections were probably lost during microfilming.

9. The area surrounding and in which the project is located is characterized by existing roads, railroad facilities, power fines, and residential and light industrial development such that it would be extremely difficult to establish a greenbelt system.

10. The work in the project area covered in this litigation begins at the downstream side of the Reading Railroad structure. Going downstream, there will be a relocated rock-lined channel for the Wissahickon Creek for about 260 feet; then there will be a highway culvert 413 feet long; then the relocated rock-lined channel for the Wissahickon Creek will continue for about 394 feet; then a second highway culvert, 82 feet long, will be constructed; then the relocated rock-lined channel will continue for 436 feet.

11. In a meeting on June 4, 1973, PennDOT was requested by DER to perform a secondary project study and in this study was advised to ignore the Reading Railroad culvert in order to analyze the full impact of the PennDOT culvert disregarding the restriction caused by the Reading Railroad culvert because the railroad structure may not exist in the future and PennDOT was also advised not to consider effects downstream of the culverts.

12. The study completed for PennDOT by Sandors and Thomas, Engineers, in 1974 was forwarded by DER to the Wissahickon Valley [5]*5Watershed Association which commented on the report.

13. The project also includes pipes which carry storm water, as opposed to sewer water, runoff from the highway slopes shoulders and paving. If these pipes were not constructed, rainwater could pond on the highway or it could find its way to the stream another way.

14. The requirements of FWWR-23 which contain instructions for the permit application, were not absolute regulations nor were they enforced as such; they were only guidelines of the Department of Forests and Waters, predecessor to DER.

15. The plans for highway ramps were modified by PennDOT so that Precision could, and did, expand their plant.

16. PennDOT also will construct a retaining wall along the main line of the highway to further reduce the amount of right-of-way that would be needed from Precision.

17. In 1973, a report prepared by Valley Forge Laboratories for Precision was presented to PennDOT as a proposal to reroute the expressway in the vicinity of Wissahickon Avenue.

18. This plan, not adopted, involved shifting the main line off of the property of Precision onto adjacent property, keeping Wissahickon Avenue open, and rearranging the ramp configuration.

19. PennDOT exhibit 4 is a narrative description of the Erosion Control Plan which includes a discussion of the erodibility of the soil types in the area, the controls that will be implemented, and the sequence of operations that the contractor will follow during construction.

20. The purpose of the Erosion Control Plan is to stop the earth under the topsoil from eroding when [6]*6it is exposed and to prevent the sediment from washing off the highway construction site, although no separate permit was issued for this plan.

21. A basic premise is that no more than 17 acres of land area within a watershed will be disturbed at any one time. The project is segmented and construction will take place on a defined sequence of operation. The project is divided into 15 distinct areas of work ranging from 2 to 17 acres.

22. The erosion control plan includes velocity dissipators to prevent erosion at culvert outlets, lined channels to prevent erosion in the channels, basins to take out the silt, seeding to keep erosion from occurring, and hay bales to filter out sediment during construction.

23. If grading doesn’t proceed according to plan and an area remains exposed more than 21 days, temporary seeding is to be performed.

24. If construction proceeds in the winter, the plans in the Erosion Control Plan require sedimentation basins, straw bales, and other methods used in conjunction with seeding.

25. Asa permanent feature, trees will be planted and these plantings are included on the construction drawings.

26. A velocity dissipator is to be constructed at any major outfall of a pipe carrying runoff from the highway to the stream. There is a rock sedimentation basin. It is a formed basin and fully fined with rocks. It will serve to lower or dissipate the velocity of the runoff water coming from the culverts and help to settle out any sediment during construction.

27. This rock-fined channel will not only protect the channel but should also aid in ground water recharge.

28. The Standard Drawings and Specifications [7]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Payne v. Kassab
312 A.2d 86 (Commonwealth Court of Pennsylvania, 1973)
Merchants' Warehouse Co. v. Gelder
36 A.2d 444 (Supreme Court of Pennsylvania, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
2 Pa. D. & C.3d 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-precision-tube-co-paenvhrbd-1975.