WINTER, District Judge.
This proceeding for exoneration, or limitation of liability, arises from the following:
The Mattawoman Creek, approximately 4,400 feet in width, is a navigable body of water within Charles County, Maryland, approximately thirty miles south of Washington, D. C., which flows in a southwesterly direction into the Potomac River. The place of its confluence with the Potomac River is known as Indian Head, Maryland, consisting of Cornwallis Neck on the northeast shore, and Stump Neck on the southwest shore. On both necks the United States- Navy maintained a military installation, i. e., the United States Naval Propellant Plant. To provide electric power and communications to both necks, cables are submerged in the creek and run between the installations on both sides of the creek.
In 1963, a new electric power cable was installed across the creek to replace an outmoded existing cable. The new cable was installed pursuant to a Corps of Engineers' permit, issued September 3, 1964.
Petitioner, Potomac Sand and Gravel Company (hereafter called “Potomac”), owned various sand and gravel deposits situate in the upper reaches of Mattawoman Creek, above the town of Mar-bury, Maryland. To work these deposits, Potomac posted a dredge (Dredge No. 5) in the upper reaches of the creek and; began dredging operations in early January, 1964. Potomac, because of shallowness in the upper- reaches of the creek near Dredge No. 5, could not utilize its Tug Keystone to tow barges up and down Mattawoman Creek to and from the dredge. It, therefore, anchored Barge No. 125 in the creek somewhere upstream from the cable-crossing area and employed the Tug Keystone to tow empty barges from Potomac’s Washington, D. C. plant and into the mouth of the creek to Barge No. 125, where the Tug Fairfax, of shallower draft than the Tug Keystone, would disengage the empty barges, take them to Dredge No. 5 and then return to the Keystone, or Barge No. 125, with loaded barges for the Keystone to take back to the Washington, D. C. plant.
On February 8, 1964, in the early morning hours, the Keystone towed a flotilla of five unladen barges from Potomac’s plant in Washington, D, C., proceeded down the Potomac River, met the Tug Fairfax, and secured her alongside. The entire flotilla arrived at the juncture of the Potomac River and Mattawoman Creek at approximately 9:45 A.M. The Fairfax disengaged the empty barges and proceeded up the creek to Dredge No. 5 with the barges in tow. The Keystone tied up to Barge No. 125. Between 9:51 and 9:52 A.M. an interruption of power was experienced at the Indian Head facility, shown by stopped electric clocks to have occurred at that time. Investigation showed that the submarine power cable was torn loose from the Stump Neck side of the creek, so that its terminal end and pothead lay loosely out in the creek and away from its securing pole.
On April 29, 1964, Potomac, as owner of Barge No. 125, filed a petition to obtain exoneration or, alternatively, to limit its liability to the value of the barge (stipulated to be $10,000.00) for the claims exceeding $45,000.00 demand[270] ed by the United States for damages to the submarine cable. An order was entered allowing Potomac to file a stipulation of $10,000.00 for the value of the barge and staying and restraining all other suits, actions or claims of any nature arising from the February 8 cable damage. The United States (hereafter called “Claimant”) answered Potomac’s petition, alleging expressly that the Keystone, valued at approximately $225,000.00, dragged Barge No. 125 over the cable area, thereby causing the damage. Claimant moved to amend the restraining order to allow it to proceed against the Tug Keystone in a separate action, or to require Potomac to include the value of the Tug Keystone in the limitation proceedings. After Potomac answered and excepted to Claimant’s motion, the parties stipulated that ruling on the motion be deferred until the conclusion of the trial of the limitation proceedings and allowing the United States to recover damages to the value of the Tug Keystone, as if formally in the limitation proceeding, if the Court should find the Keystone at fault in causing damage to the submarine cable. Later, an order was entered setting the petition for hearing on the issue of liability only, and the matter has been submitted for decision on this question.
The proctors for the parties agree that the key question bearing on the issue of liability is how the submarine cable was damaged. This question is factual. By the very nature of the type of damage, and the circumstances under which it occurred, this question must be determined largely by circumstantial evidence. The proctors' conceded, in a joint pretrial memorandum, that from the evidence the Court might conclude that the cable was damaged by the act of Barge No. 125 alone, by the act of the Tug Keystone alone, or by the j'oint act of the Tug Keystone and Barge No. 125. The proctors also conceded that in regard to any one of the three alternatives previously stated, the Court could find any one of three additional alternatives, viz., that there was mutual fault on the part of both parties, fault solely on the part of the petitioner, or fault solely on the part of claimant.
At trial and in final argument, petitioner contended that the cable was damaged by being caught in the pintle which is part of the kort nozzle of the Keystone, but that fault rested solely on claimant by reason of the negligent manner in which the submarine cable was installed, so as to constitute it a hazard to navigation. Explicit in the contention was the assertion that there was no negligence or want of care on the part of petitioner which caused or contributed to the damage. Claimant contended that the cable was damaged by being caught in one or more of the flukes of one or both of the anchors by which Barge No. 125 was moored, at a time when Barge No. 125 was pushed or pulled by the Tug Keystone, and that the damage was the sole fault of petitioner. Explicit in this contention was the assertion that the submarine cable was properly installed by claimant, and there was no negligence or want of care on the part of claimant causing or contributing to the damage. An analysis of the evidence, and the Court’s findings therefrom, follow.
A — How the Submarine Cable was Damaged:
Free access — add to your briefcase to read the full text and ask questions with AI
WINTER, District Judge.
This proceeding for exoneration, or limitation of liability, arises from the following:
The Mattawoman Creek, approximately 4,400 feet in width, is a navigable body of water within Charles County, Maryland, approximately thirty miles south of Washington, D. C., which flows in a southwesterly direction into the Potomac River. The place of its confluence with the Potomac River is known as Indian Head, Maryland, consisting of Cornwallis Neck on the northeast shore, and Stump Neck on the southwest shore. On both necks the United States- Navy maintained a military installation, i. e., the United States Naval Propellant Plant. To provide electric power and communications to both necks, cables are submerged in the creek and run between the installations on both sides of the creek.
In 1963, a new electric power cable was installed across the creek to replace an outmoded existing cable. The new cable was installed pursuant to a Corps of Engineers' permit, issued September 3, 1964.
Petitioner, Potomac Sand and Gravel Company (hereafter called “Potomac”), owned various sand and gravel deposits situate in the upper reaches of Mattawoman Creek, above the town of Mar-bury, Maryland. To work these deposits, Potomac posted a dredge (Dredge No. 5) in the upper reaches of the creek and; began dredging operations in early January, 1964. Potomac, because of shallowness in the upper- reaches of the creek near Dredge No. 5, could not utilize its Tug Keystone to tow barges up and down Mattawoman Creek to and from the dredge. It, therefore, anchored Barge No. 125 in the creek somewhere upstream from the cable-crossing area and employed the Tug Keystone to tow empty barges from Potomac’s Washington, D. C. plant and into the mouth of the creek to Barge No. 125, where the Tug Fairfax, of shallower draft than the Tug Keystone, would disengage the empty barges, take them to Dredge No. 5 and then return to the Keystone, or Barge No. 125, with loaded barges for the Keystone to take back to the Washington, D. C. plant.
On February 8, 1964, in the early morning hours, the Keystone towed a flotilla of five unladen barges from Potomac’s plant in Washington, D, C., proceeded down the Potomac River, met the Tug Fairfax, and secured her alongside. The entire flotilla arrived at the juncture of the Potomac River and Mattawoman Creek at approximately 9:45 A.M. The Fairfax disengaged the empty barges and proceeded up the creek to Dredge No. 5 with the barges in tow. The Keystone tied up to Barge No. 125. Between 9:51 and 9:52 A.M. an interruption of power was experienced at the Indian Head facility, shown by stopped electric clocks to have occurred at that time. Investigation showed that the submarine power cable was torn loose from the Stump Neck side of the creek, so that its terminal end and pothead lay loosely out in the creek and away from its securing pole.
On April 29, 1964, Potomac, as owner of Barge No. 125, filed a petition to obtain exoneration or, alternatively, to limit its liability to the value of the barge (stipulated to be $10,000.00) for the claims exceeding $45,000.00 demand[270] ed by the United States for damages to the submarine cable. An order was entered allowing Potomac to file a stipulation of $10,000.00 for the value of the barge and staying and restraining all other suits, actions or claims of any nature arising from the February 8 cable damage. The United States (hereafter called “Claimant”) answered Potomac’s petition, alleging expressly that the Keystone, valued at approximately $225,000.00, dragged Barge No. 125 over the cable area, thereby causing the damage. Claimant moved to amend the restraining order to allow it to proceed against the Tug Keystone in a separate action, or to require Potomac to include the value of the Tug Keystone in the limitation proceedings. After Potomac answered and excepted to Claimant’s motion, the parties stipulated that ruling on the motion be deferred until the conclusion of the trial of the limitation proceedings and allowing the United States to recover damages to the value of the Tug Keystone, as if formally in the limitation proceeding, if the Court should find the Keystone at fault in causing damage to the submarine cable. Later, an order was entered setting the petition for hearing on the issue of liability only, and the matter has been submitted for decision on this question.
The proctors for the parties agree that the key question bearing on the issue of liability is how the submarine cable was damaged. This question is factual. By the very nature of the type of damage, and the circumstances under which it occurred, this question must be determined largely by circumstantial evidence. The proctors' conceded, in a joint pretrial memorandum, that from the evidence the Court might conclude that the cable was damaged by the act of Barge No. 125 alone, by the act of the Tug Keystone alone, or by the j'oint act of the Tug Keystone and Barge No. 125. The proctors also conceded that in regard to any one of the three alternatives previously stated, the Court could find any one of three additional alternatives, viz., that there was mutual fault on the part of both parties, fault solely on the part of the petitioner, or fault solely on the part of claimant.
At trial and in final argument, petitioner contended that the cable was damaged by being caught in the pintle which is part of the kort nozzle of the Keystone, but that fault rested solely on claimant by reason of the negligent manner in which the submarine cable was installed, so as to constitute it a hazard to navigation. Explicit in the contention was the assertion that there was no negligence or want of care on the part of petitioner which caused or contributed to the damage. Claimant contended that the cable was damaged by being caught in one or more of the flukes of one or both of the anchors by which Barge No. 125 was moored, at a time when Barge No. 125 was pushed or pulled by the Tug Keystone, and that the damage was the sole fault of petitioner. Explicit in this contention was the assertion that the submarine cable was properly installed by claimant, and there was no negligence or want of care on the part of claimant causing or contributing to the damage. An analysis of the evidence, and the Court’s findings therefrom, follow.
A — How the Submarine Cable was Damaged:
The damaged submarine cable was a 3-conductor, polyethelene-insulated, lead-sheathed, armored and j’ute covered, 15 KV cable, 2.83 inches in diameter, and weighing 10 pounds per foot. It was installed in the general area of previous submarine power and telephone cables which existed since at least 1955, some of which had been abandoned and some of which were still in use. The cable was not entrenched in installation except as it approached the shore line on either side of the creek, because Mattawoman Creek has a soft, muddy bottom and it was thought that by its own weight the cable would sink appreciably after being laid across the creek. Because there was a question of how deeply the cable would sink, it was laid in a [271] generously curving double arc (serpentine) to allow sufficient play for the eable to seek a lower level. There were 4,520 feet of cable actually laid; 4,447 feet would, have been required to lay a cable in a straight line between the two points on shore where the cable came out of the water. There was, therefore, 73 feet of play in the cable and, if the cable rested on a flat bottom and did not sink, and if the cable were laid in a single arc, the point of maximum departure from a straight line, between the two points where the cable entered the water, would be at least 350 feet from that line.
On either side of the creek the area in which the cable had' been laid (and existing cables previously laid) was marked by signs reading, “Cable Crossing — Do Not Anchor.” The letters on the signs were 18 inches high, and the distance between the signs from shore to shore was in excess of 3/4ths of a mile. On the Stump Neck side the sign was 6 feet downstream from the point where the cable came ashore. On the Indian Head side the sign was approximately 150 feet upstream from the point where- the cable entered the water. The course of the cable across the stream was not marked, but the evidence indicated that the course of the cable was a maximum of 150 feet upstream from the point that the two ends entered the water, so that the cable was in the general area defined by the crossing signs.
Mattawoman Creek has a chartered mean low water depth of 7y2 feet in the cable-crossing area. The depth of water varies with the tides and weather conditions. A strong northeast wind can cause low tides to be 1% to 2 feet below charted mean low water depth. The creek, has no clearly defined channel. In January, 1965, when the Keystone towed Dredge No. 5 into position in the upper reaches of the creek to begin dredging operations, the Keystone plowed through the soft, muddy bottom of the creek, notwithstanding that there then existed a condition of extremely high tide.
The Tug Keystone is a 108-foot long, twin-screwed, 1,100 horsepower tug boat, with a draft, fore- and aft, of 6.5 feet. It was capable of producing 34,500 pounds of pushing force; its pushing power achieved this maximum by the use of kort nozzles, which are metal shrouds surrounding both screws, which increased- the thrust of the screws and kept objects out of the propellers. There are two pintles, fore of the screws and part of each of the two kort nozzle assemblies. These pintles are the means of supporting the flanking rudders, and the maximum space between the flanking rudders and the pintles is 1 % inches. The pintles are not lower than the tug’s keel.- The distances between various combinations of the fore pintles are three-fold. The distance between the outboard pintles is 17 feet 2 inches, and between the inboard pintles 7 feet 10 inches. There are also two pintles in the portion of the kort nozzle assembly aft of the screws which support the steering rudders, but the parties concede the aft pintles can have no significance in this case.
The Tug Fairfax is a smaller, less powerful tug than the Keystone and has a lesser draft.
Barge No. 125 was anchored in Mattawoman Creek on February 5, 1964. Pri- or to anchorage, Potomac requested- a mooring point in the deeper water of Mattawoman Creek adjacent to Cornwallis Neck. Naval officers stationed at this installation refused the request, apparently because of its proximity to the point where used propellant fuel was burned. Potomac then determined to moor Barge No. 125 approximately 500 yards east of the cable-crossing area near the Stump Neck side of the creek. The captain of the Keystone was given instructions to anchor the barge with two 200-pound anchors at a point east from the cable-crossing area in the deeper portions of the creek near the Stump Neck side of the creek.
How the orders were executed is a matter of dispute. The captain of the Keystone testified that the barge was [272] moored as directed, but the point selected was arrived at totally without any navigational aid, and the testimony of the captain of the Keystone, a crew member of the Keystone, and the captain of the Fairfax, both at trial and- on deposition, placed the barge within a range of 150 feet to 1,500 feet above the cable area. Potomac’s fleet superintendent claimed that, when he saw it on February 6, the barge was placed in accordance with the orders, but he could not remember the place from which he made his observation of the barge- after mooring; he did not know where the cable was, and he could not see the cable signs when he observed the barge in the creek. This witness marked a chart to show when he saw the barge and he placed it 5,000 feet above the cable-crossing area. Potomac’s assistant general manager, the only witness entitled to any credibility as to where the barge was anchored, testified that he last saw the barge on February & at approximately 1,500 feet from the cable-crossing area.
The barge was moored by the use of two old-fashioned or admiralty-type anchors, with fixed stocks secured to a single length of wire rope made fast to a chain which, in turn, was secured to a comer bit. The anchors had small flukes, and the presence of a stock would normally prevent more than one fluke from each anchor digging into the bottom of the creek. A mushroom anchor, which has no flukes, would not damage a cable if dragged over it, and a stock-less anchor allows both flukes to dig in and provide holding power.. Either of these types of anchors would have provided greater holding power for Barge No. 125. Even if admiralty-type anchors with fixed stocks were used, either a 2-point method or a 4-point method of anchorage would have provided better protection against dragging.
Irrespective of where Barge No. 125 may have been initially anchored, a preponderance of the evidence shows that, on the morning of February 8, 1964, it was not at all times 1,500 feet above the cable-crossing area.
Approximately 10 A.M.