In Re Plum Run Service Corp.

39 Cont. Cas. Fed. 76,584, 159 B.R. 496, 29 Collier Bankr. Cas. 2d 1428, 1993 Bankr. LEXIS 1492, 1993 WL 412965
CourtUnited States Bankruptcy Court, S.D. Ohio
DecidedSeptember 30, 1993
DocketBankruptcy 93-50131
StatusPublished
Cited by9 cases

This text of 39 Cont. Cas. Fed. 76,584 (In Re Plum Run Service Corp.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Plum Run Service Corp., 39 Cont. Cas. Fed. 76,584, 159 B.R. 496, 29 Collier Bankr. Cas. 2d 1428, 1993 Bankr. LEXIS 1492, 1993 WL 412965 (Ohio 1993).

Opinion

ORDER ON MOTION FOR ASSUMPTION OF EXECUTO-RY CONTRACT

DONALD E. CALHOUN, Jr., Bankruptcy Judge.

I. Introduction

The matter to be decided by this Court is the ability of the Debtor-in-possession, Plum Run Service Corp. (“Plum Run”), to. assume a contract or options thereto with the United States Department of Navy (“the Navy”), thereby compelling the Navy to exercise said options against its will. This Court is vested with jurisdiction over this matter pursuant to 28 U.S.C. § 1334 and the General Order of Reference entered in this district. This is a core proceeding under 28 U.S.C. § 157(b)(2)(0).

The contract in question is the Base Operational Support Contract entered between Plum Run and the Navy (“the BOS Contract”). It is undisputed that the “base period” for the BOS Contract was from October 1, 1992 through September 30, 1993. The solicitation for bids for the BOS Contract stated that “Offers shall be submitted for the performance of work for a period of one year plus four option years.”

The BOS Contract was comprised of eleven different functions to be performed by the successful bidder. These functions, in general, provided base maintenance services for the U.S. Naval base in Guantanamo Bay, Cuba. The Debtor asserts that it was induced to bid on the BOS Contract under the assumption that the four option years would be exercised by the Navy; that with *498 the exception of the housing maintenance portion of the BOS contract, Plum Run performed satisfactorily under the BOS contract, especially after filing Chapter 11 in January 1993; and that the Navy refused to exercise the option due solely, or in significant part to the Chapter 11 filing by Plum Run, in violation of 11 U.S.C. § 525. Plum Run thereby asserts a right to assume the contract, together with all options, under 11 U.S.C. § 365.

The Navy argues that Plum Run experienced numerous problems, unrelated to the bankruptcy filing per se, from the inception of its performance under the BOS Contract continuing to the present date. The Navy argues that it had the unilateral right to decide whether the option would be exercised, and chose not to exercise the option due to the fact that Plum Run had not performed well under the BOS Contract, and due to the fact that there was no viable option that could be exercised after the housing maintenance portion of the contract was terminated for cause. 1

The issues before the Court are complex. This complexity was exacerbated by the fact that Plum Run did not obtain its expedited hearing date with respect to this matter until a mere three days prior to the expiration of the base period of the BOS contract. The Court notes that this timing was certainly not caused by special counsel for Plum Run who did an admirable job in preparing this difficult case on such short notice.

II. No Viable Option Remains For Purposes of Assumption

The initial inquiry for this Court is whether the option to extend the BOS Contract is an executory contract, subject to the provisions of 11 U.S.C. § 365, and therefore subject to assumption by Plum Run. Under current case law, contract options are indeed executory in nature, and thereby subject to the province of § 365. However, this case is not quite as clear as that. Here, the Navy obtained relief from the automatic stay to allow for termination of the housing maintenance portion of the BOS Contract, according to the evidence, constituting approximately 20% of the total BOS Contract. The Agreed Order, entered by this Court on April 7, 1993, granted the Navy’s motion to enable the Navy to pursue available administrative remedies, and partially terminate the BOS Contract. 2

The Navy cites pertinent cases indicating that an executory contract must be assumed or rejected by the Debtor in its entirety, and cannot be dealt with in a piecemeal fashion. See, NLRB v. Bildisco (In re Bildisco & Bildisco), 465 U.S. 513, 531-32, 104 S.Ct. 1188, 1199, 79 L.Ed.2d 482 (1984); In re Ritchey, 84 B.R. 474, 476 (Bankr.N.D.Ohio 1988). Any other ruling would allow a Debtor to pick and choose portions of the contract it considered profitable, while rejecting any burdens considered onerous. This is simply not the intent of § 365. However, although not cited by counsel, the Court has also reviewed cases holding that a single writing may contain more than one contract for § 365 assumption purposes. See, e.g., In re Gardinier, Inc., 831 F.2d 974 (11th Cir.1987), cert. denied, 488 U.S. 853, 109 S.Ct. 140, 102 L.Ed.2d 112 (1988); Matter of Holly’s, Inc., 140 B.R. 643, 681 (Bankr.W.D.Mich.1992). To decide whether a contract is divisible for *499 assumption purposes, the Court should look to state law. Ritchey, 84 B.R. at 476. In fact, the courts in Holly’s and Gardinier noted a three-factor test to decide whether agreements set forth in a single document would be considered separate for § 365 assumption-rejection purposes: (1) the differing nature and purpose of the agreement; (2) the separate and distinct consideration for the agreement; and (3) the noninterrelatedness of the obligations of the parties to the document. Holly’s, 140 B.R. at 681; Gardinier, 831 F.2d at 976.

With respect to the law of the State of Ohio, the case of Material Contractors, Inc. v. Donahue, 14 Ohio St.2d 19, 235 N.E.2d 525 (1968) quoted from, and accepted the ruling of the case of Huntington and Finke Co. v. Lake Erie Lumber & Supply Co., 109 Ohio St. 488, 143 N.E. 132 (1924):

Whether a contract ... is entire or divisible depends generally upon the intention of the parties, and this must be ascertained by the ordinary rules of construction, considering not only the language of the contract, but also, in cases of uncertainty, the subject-matter, the situation of the parties and the circumstances surrounding the transaction, and the construction placed upon the contract by the parties themselves.

The Court in Material Contractors, Inc. also relied on the case of Armstrong v. Bankers’ Life Assn., 217 Ind. 601, 29 N.E.2d 415 (1940) which listed several rules on the issue of severability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Minesen Company
D. Hawaii, 2021
GTP Structures I, LLC v. Wisper II, LLC
153 F. Supp. 3d 983 (W.D. Tennessee, 2015)
In Re Buffets Holdings, Inc.
387 B.R. 115 (D. Delaware, 2008)
In Re Nickels Midway Pier, LLC
383 F. App'x 633 (Third Circuit, 2007)
In Re Cafeteria Operators, L.P.
299 B.R. 384 (N.D. Texas, 2003)
In Re Lil' Things, Inc.
220 B.R. 583 (N.D. Texas, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,584, 159 B.R. 496, 29 Collier Bankr. Cas. 2d 1428, 1993 Bankr. LEXIS 1492, 1993 WL 412965, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-plum-run-service-corp-ohsb-1993.