This text of 154 A.2d 201 (In Re Plainfield-Union Water Co.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Plainfield-Union Water Co., 154 A.2d 201, 57 N.J. Super. 158 (N.J. Ct. App. 1959).

Opinion

57 N.J. Super. 158 (1959)
154 A.2d 201

IN THE MATTER OF THE REVISION IN RATES FILED BY PLAINFIELD-UNION WATER COMPANY INCREASING ITS RATES FOR WATER SERVICE.
PLAINFIELD-UNION WATER COMPANY, APPELLANT AND CROSS-RESPONDENT,
v.
BOARD OF PUBLIC UTILITY COMMISSIONERS, DEPARTMENT OF PUBLIC UTILITIES, STATE OF NEW JERSEY, RESPONDENT, AND STATE OF NEW JERSEY, RESPONDENT AND CROSS-APPELLANT.

Superior Court of New Jersey, Appellate Division.

Argued May 25, 1959.
Decided September 1, 1959.

*163 Before Judges GOLDMANN, CONFORD and HANEMAN.

Mr. John R. Sailer argued the cause for appellant and cross-respondent.

Mr. H. Frank Pettit argued the cause for cross-appellant.

Mr. Howard T. Rosen argued the cause for respondents and cross-appellant (Mr. David D. Furman, Attorney General, attorney).

*164 The opinion of the court was delivered by HANEMAN, J.A.D.

This is an appeal by Plainfield-Union Water Company (the company) from a final decision and order of the New Jersey Board of Public Utility Commissioners (the Board) on the company's application for increased rates. The company complains that the rate increase allowed is less than what it maintains is necessary to permit it to carry out necessary construction. Rate counsel, appointed by the Attorney General, prosecutes a cross-appeal from the Board's inclusion of certain scheduled construction projects in the rate base.

On January 31, 1958 the company filed a schedule of rates with the Board. That schedule reflected an increase in rates equal to approximately 18% of the rates the company was then charging its users. On February 13, 1958 the Board ordered the proposed schedule of rates suspended and fixed April 14, 1958 as the first date of hearing on the justness and reasonableness of the proposed rates. The company was ordered to give notice to its customers of the purpose, time and place of the hearing. Public hearings were held on five days between April 14 and May 29, 1958. Represented at these hearings were the company, the public (through rate counsel appointed by the Attorney General), and the Inter-municipal Water Committee (a group composed of representatives of the municipalities served by the company).

By an order dated August 28, 1958 the Board determined that the existing rates were unjust and unreasonable because the company was denied thereunder an opportunity to earn a fair return; but that the yield under the rates proposed by the company would be excessive. The Board permitted an increase in the company's annual revenues equal to $201,245, rather than, as requested, $428,891. The increase allowed would permit the company to earn operating income of $574,362, a return equal to 6% per annum on a rate base of $9,572,704.

*165 The company appeals from that order. Its appeal challenges the reasonableness of the Board's action on the following grounds: the increase allowed will not permit the company to maintain and support its credit and to raise the capital necessary to a proper discharge of its duties; the refusal by the Board to give weight to the depreciated reproduction cost rate base; its reduction of the company's rate base by the amount of profit realized on the 1931 sale of a portion of the company's distribution system; its refusal to value the company's real estate at fair market value; its refusal to "normalize" 1957 metered water consumption and adjust operating revenues accordingly for purposes of calculation of income for the 1957 "test year"; its refusal to "normalize" federal income taxes and adjust operating expenses accordingly; its rejection of amortized expenses of prior rate cases as an operating expense in the test year for the same purpose; and, finally, the order is violative of the United States and New Jersey Constitutions as a taking of private property without compensation and without due process of law.

On the cross-appeal rate counsel challenges the reasonableness of the company's rate base as determined by the Board upon the ground that the Board included $887,600 therein for projected additions to the company's plant, representing improvements and extensions (mainly non-revenue producing) which were only proposed, i.e., facilities not then existing and used or useful in the public service.

The company provides water service to approximately 52,000 customers located in 21 municipalities in Union, Somerset and Middlesex Counties. (This represents an increase in the number of customers of approximately 2,000 over the number served in 1956). The water supply is obtained from wells and by purchase from adjacent water companies, principally Elizabethtown Water Company, Consolidated. Storage is provided by the use of collecting basins and closed reservoirs, tanks and standpipes. The distribution system is composed of approximately 500 miles of cast iron *166 mains ranging in size from 2 to 24 inches. Attached to the system are about 300 fire hydrants.

During World War II there had been little increase over the prior demand for water in the territory served by the company. Consulting engineers for the company estimated at that time that the average daily demand for 1956 would range between 12 and 13 million gallons. This figure was exceeded in 1949 and 1951. Service difficulties developed during drought periods from 1949 to 1955, with resulting complaints by consumers to the Board and various municipal officials.

Eighteen of the municipalities serviced by the company formed the Inter-municipal Water Committee for the purpose of investigating the necessity for improvements to assure adequate water service. After the receipt of independent engineering advice, this committee concluded that construction of additional physical facilities was required to accomplish that end, and that an increase in rates was necessary to finance such construction. The company concurred in this finding and in 1956 adopted a capital improvement program to accomplish the improvements recommended.

The company requested an increase in rates during 1953. The rates then proposed were designed to produce additional annual revenue of $582,500, thus enabling the company to obtain $1,000,000 additional capital for construction purposes. By an order dated March 24, 1954 the Board granted a rate increase to produce additional revenue of $272,280. Actual expenditures for capital improvements in 1954 amounted to $900,223.

In 1956 the company adopted a five-year construction program which provided for expenditures of $1,710,000 between the years 1956 and 1960. In that year the company again requested the Board to approve an increase in rates designed to produce $550,000 additional annual revenue in order to obtain additional funds necessary to finance the five-year improvement program. The Board granted a rate increase *167 designed to produce additional annual revenue of $249,600. The company expended in excess of $250,000 for major capital improvements during 1956 but deferred any further construction during 1957, assertedly because of its inability to raise further capital.

Thereafter the company adopted a new three-year program of major construction improvements necessitating a total expenditure of $1,795,000. As projected, $202,600 would have been expended immediately (in 1958), $685,000 by the summer of 1959, $476,000 by the summer of 1960, and $431,400 by the summer of 1961.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Essex County Board of Taxation v. Township of Caldwell
21 N.J. Tax 188 (New Jersey Superior Court App Division, 2003)
Lally v. PUBLIC EMP. RET. SYS.
587 A.2d 303 (New Jersey Superior Court App Division, 1991)
Allen v. Board of Trustees, Police & Firemen's Retirement System
558 A.2d 496 (New Jersey Superior Court App Division, 1989)
Koschker v. Board of Trustees
558 A.2d 503 (New Jersey Superior Court App Division, 1989)
Simon v. Board of Trustees
558 A.2d 490 (New Jersey Superior Court App Division, 1989)
State v. Laurick
555 A.2d 1133 (New Jersey Superior Court App Division, 1989)
Maine Water Co. v. Public Utilities Commission
482 A.2d 443 (Supreme Judicial Court of Maine, 1984)
HP Higgs Co., Inc. v. Madison
446 A.2d 193 (New Jersey Superior Court App Division, 1982)
NJ BLDRS. ASS'N v. Dept. of Environmental Protec.
404 A.2d 320 (New Jersey Superior Court App Division, 1979)
Casco Bay Lines v. Public Utilities Commission
390 A.2d 483 (Supreme Judicial Court of Maine, 1978)
United States v. Hall
3 M.J. 969 (U.S. Navy-Marine Corps Court of Military Review, 1977)
Essex County Welfare Board v. Klein
373 A.2d 691 (New Jersey Superior Court App Division, 1977)
Hoeganaes Corp. v. Dir. of Div. of Tax
367 A.2d 1182 (New Jersey Superior Court App Division, 1976)
Communications Workers v. Union Cty. Welfare Bd.
315 A.2d 709 (New Jersey Superior Court App Division, 1974)
United States v. Scott
22 C.M.A. 25 (United States Court of Military Appeals, 1972)
In Re Ridgway
281 A.2d 390 (New Jersey Superior Court App Division, 1971)
City of Lexington v. Lexington Water Company
458 S.W.2d 778 (Court of Appeals of Kentucky (pre-1976), 1970)
United States v. Baker
18 C.M.A. 504 (United States Court of Military Appeals, 1969)
Ferrante Equipment Co. v. Foley MacHinery Co.
231 A.2d 208 (Supreme Court of New Jersey, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
154 A.2d 201, 57 N.J. Super. 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-plainfield-union-water-co-njsuperctappdiv-1959.