In Re Penn Central Transportation Co.

458 F. Supp. 1357, 1978 U.S. Dist. LEXIS 16072
District Court, E.D. Pennsylvania·Decided August 11, 1978·No. 70-347·Published·Cited by 3 cases

Opinion

OPINION RE SETTLEMENTS WITH AMTRAK, CONRAIL, NEW YORK STATE, AND THE SIX MONTHS CREDITORS

FULLAM, District Judge.

In the Approval Opinion, a pending settlement of Amtrak’s claims and the dispute with respect to the amount and character of ConRail’s claims were discussed. The Trustees and ConRail have resolved their disputes and a settlement has been presented to the Court. Settlements with the State of New York and the Six Months Creditors have also been presented to the Court for approval. All four settlements will be approved.

SETTLEMENT WITH AMTRAK

The proposal is to settle a large number of reciprocal claims between the Trustees and Amtrak by paying to Amtrak, partly in cash over a period of time, and partly in securities of the new company, a total of approximately $40 million. The claims and counterclaims which would thus be released fall into five categories, of which two are relatively insignificant: (1) adjustments in the proper accounting for Amtrak’s share of certain costs; and (2) miscellaneous claims. *1359 The remaining three categories are more significant, at least in terms of the potential theoretical exposure: (3) Amtrak’s claims for track maintenance; (4) the final compensation to be paid to the Trustees for furnishing facilities and services to Amtrak after the initial start-up period; and (5) Amtrak’s claims for maintenance of highway bridges over the Northeast Corridor.

The Trustees assert claims against Amtrak in the first two categories which, if the Trustees were completely successful, would mean that Amtrak owes the Trustees $16.3 million for accounting adjustments and $2.8 million for miscellaneous claims, or a total of $19.1 million. Many of the Trustees’ claims are tenuous, however, and it is fair to state that the Trustees would undoubtedly consider it a victory if they established liability on the part of Amtrak for $8.8 million in accounting adjustments, and $1 million on the miscellaneous claims, for a total of $9.8 million. If Amtrak were totally successful on its claims in these categories, the Trustees would owe Amtrak $6.8 million for accounting adjustments, and $3.7 million for miscellaneous claims, for a total of $10.5 million. Here again, however, the likelihood of such a totally favorable outcome for Amtrak seems remote. I have no doubt that it would generally be considered a victory for Amtrak and a loss for the Trustees if the slate were wiped clean with respect to claims in these two categories. The realistic range of litigation possibilities, therefore, is probably between a $9 or $10 million recovery by the Trustees, on the one hand, and no recovery by either party, on the other.

Pursuant to the Amtrak statute, the parties have attempted to agree upon the appropriate level of compensation to be paid by Amtrak to the Trustees for furnishing facilities and services, covering the period from June 1, 1973 to April 1,1976 (the date of the conveyance to ConRail), and, upon being unable to agree, submitted the dispute to the Interstate Commerce Commission for resolution. The ICC rendered an interim opinion, establishing certain guidelines. 1 The parties then worked out a tentative compromise settlement agreement, in light of the ICC guidelines and an amendment to the statute which Congress enacted in the meantime. I rejected the proposed settlement, as providing inadequate compensation to the Trustees, and Amtrak simultaneously announced its withdrawal from the settlement agreement. 2 Further litigation before the ICC would be required to resolve this dispute. If the Trustees were fully successful, Amtrak would owe the Trustees as much as $147 million. However, such complete success is unlikely. The theories on which the Trustees would be most likely to recover would generate a return of approximately $85 million. If Amtrak were completely successful, it would owe the Trustees nothing. Here again, however, the likelihood of such a result appears remote. It seems doubtful that the Trustees could fail to establish liability on the part of Amtrak for much less than $30 million additional compensation.

Thus, combining all claims in the categories thus' far analyzed, it appears that the range of probable recoveries by the Trustees extends from a high of $94 or $95 million to a low of about $30 million.

Offsetting these reasonably predictable favorable results are the claims asserted by Amtrak in the remaining two categories. Amtrak asserts that it has claims against the Trustees for as much as $30 million, representing a rough estimate of what it might cost to rebuild a large number pf highway bridges crossing the Northeast Corridor. The facts are these: Pursuant to the RRRA, the Trustees conveyed the railroad, including the Northeast Corridor, to ConRail. ConRail then sold the Northeast Corridor to Amtrak, at the (very low) valuations tentatively specified by USRA in the Final System Plan. ConRail conveyed the properties to Amtrak “as is.” Amtrak takes the position that various highway *1360 bridges crossing the Northeast Corridor should have been better maintained by Penn Central during its ownership, and that, as the present owner of the property, Amtrak may find it necessary to rebuild or restore these bridges. Amtrak expresses considerable uncertainty as to just what interest in the bridges passed to Amtrak from ConRail, but I am not aware of any contention that Penn Central retained any ownership rights in the Corridor.

In presenting objections to the Reorganization Plan on the basis of its failure to provide for this claim, Amtrak was unable to articulate any legal theory which would support the imposition of liability upon the Penn Central estate in these circumstances, and, so far as I am aware, no such legal theory has yet been developed by anyone. The benefit to the Debtor’s estate from release of this claim in connection with the settlement agreement is therefore plainly minimal, namely, avoiding the costs of defending the action, if Amtrak were to attempt to pursue it.

Free access — add to your briefcase to read the full text and ask questions with AI

In Re Penn Central Transportation Co., 458 F. Supp. 1357, 1978 U.S. Dist. LEXIS 16072 (E.D. Pa. 1978).

458 F. Supp. 1357 (In Re Penn Central Transportation Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re DiMartino
144 B.R. 225 (D. Rhode Island, 1992)
In re Boston & Maine Corp.
46 B.R. 962 (D. Massachusetts, 1984)
In re Lehigh Valley Railroad
19 B.R. 978 (E.D. Pennsylvania, 1982)