In Re Olde Prairie Block Owner, LLC

448 B.R. 482, 2011 Bankr. LEXIS 1171, 2011 WL 1299374
United States Bankruptcy Court, N.D. Illinois·Decided March 31, 2011·No. 15-33970·Published·Cited by 2 cases

Opinion

AMENDED FINDINGS OF FACT AND CONCLUSIONS OF LAW ON DEBTOR’S MOTION TO ENTER INTO SENIOR SECURED SU-PERPRIORITY DEBTOR-IN-POSSESSION CREDIT FACILITY PURSUANT TO 11 U.S.C. § 364(d) [Docket No. 371]

JACK B. SCHMETTERER, Bankruptcy Judge.

Debtor in this Chapter 11 bankruptcy case has moved under 11 U.S.C. § 364(d) to borrow up to $4 million in exchange for a priming lien on its property. Center-Point Properties Trust (“CenterPoint”), Debtor’s current secured lender, objects. For reasons discussed below, Debtor’s Motion will be granted in part and denied in part. After the original raling on this issue [Docket No. 744], Debtor moved to alter or amend the ruling [Docket No. 760], and the parties have fully briefed and argued that motion. The Amended Find *485 ings and related Amended Order resolve the latter Motion and CenterPoint’s Objection thereto.

BACKGROUND

Debtor’s bankruptcy case has been found to involve single asset real estate, see 11 U.S.C. §§ 101(51B); 362(d)(3), and so it is proceeding on a fast pace toward a confirmation hearing in mid 2011. Debtor must demonstrate actual or imminent refinancing and development funds in order to show a feasible plan for hotel development.

Debtor first filed its pending Motion to enter into credit facility [Docket No. 371] on November 27, 2010. CenterPoint filed an Objection [Docket No. 391], to which Debtor filed a Reply [Docket No. 408], As discussed below, this Motion is critical to Debtor’s effort to obtain credit needed for its development.

When Debtor first presented this Motion on December 10, 2010, it argued that an immediate hearing on the Motion was necessary because, among other things, it sought to borrow money to pay real estate taxes that were due the next Monday, December 13, 2010. Because fourteen days had not elapsed since service of the Motion, a final hearing could not be held that day. See Fed. R. Bankr.P. 4001(c)(2); Local Bankr.R. 4001-2(B). Instead, a preliminary hearing was held at which Debtor first had to show the usual standards required to obtain senior secured financing— inability to obtain credit otherwise and adequate protection of the existing lender’s interest. See 11 U.S.C. § 364 and discussion below. Debtor also had to show for emergency relief that the relief it sought was necessary to avoid immediate and irreparable harm to the estate. See Fed. R. Bankr.P. 4001(c)(2); Local Bankr.R. 4001-2(B).

At the preliminary hearing, Debtor presented evidence in the form of testimony from three witnesses: Pamela Gleichman, its developer; Marc Nuccitelli, its financial advisor; and Gilbert Li, a representative of the potential lender. CenterPoint elected to reserve its cross-examination of these witnesses until the final hearing on Debtor’s Motion. CenterPoint’s counsel argued that CenterPoint would be ready and willing to pay Debtor’s property taxes if Debtor could not, but they did not call any witness or present any evidence by testimony or documents to back that argument with an actual commitment. Of course, the argument of counsel is not evidence. In fact, CenterPoint did not present any evidence at all at that time.

After Debtor rested at that preliminary hearing, it was opined from the bench that Debtor could not otherwise obtain funds to pay its property taxes and that payment of those taxes was necessary to prevent immediate and irreparable harm to the estate. The matter was set on December 13, 2010, for entry of the order for emergency relief. 1 On that date, an order [Docket No. 423] was entered authorizing Debtor to obtain post-petition financing secured by a first priority lien on substantially all of Debtor’s assets pursuant to 11 U.S.C. § 364(d) only to the extent and in the amount necessary to pay real estate property taxes due that day. CenterPoint has appealed from that order [Docket No. 428].

*486 On January 11, 2011, Debtor was ordered [Docket No. 529] to provide at trial a summary chart detailing its proposed payees, including the amount of each expenses that accrued before or would accrue after the final hearing on its motion commenced on January 12, 2011.

Final hearing on evidence presented in support of Debtor’s Motion was held beginning on January 12, 2011. After resting, Debtor and CenterPoint submitted written argument in the form of post-trial proposed findings of fact and conclusions of law.

After the hearing had concluded, Coman & Anderson, P.C., filed an additional objection, arguing that its previously allowed administrative expense claim should be paid along with all other administrative expenses out of the proposed post-petition loan.

Based on evidence presented, the following Findings of Fact and Conclusions of Law are made and will be entered.

FINDINGS OF FACT

Debtor owns two parcels of choice real estate located adjacent to McCormick Place in the City of Chicago as well as a long-term lease of 450 parking spots in the McCormick Place parking garage. Although the properties are mostly vacant and generate very little income, Debtor plans to develop a hotel complex there that will serve the needs of people using and visiting McCormick Place. After an evi-dentiary hearing earlier in this case on CenterPoint’s motion for relief from the automatic stay, it was determined that the value of Debtor’s property was $81,150,000 based on a finding that the highest and best use of the property will be for a fine hotel. In re Olde Prairie Block Owner, LLC, No. 10 B 22668, 2010 WL 4512820, at *4 (Bankr.N.D.Ill. Oct.29, 2010). Center-Point has opposed Debtor’s attempt to reorganize at many stages of this bitterly contested case. 2

Karl Norberg is Debtor’s Manager. His wife Pamela Gleichman is Debtor’s Developer and has signing authority to contract on Debtor’s behalf.

CenterPoint is Debtor’s only secured lender, having advanced a loan to Debtor in 2008 that was secured by a mortgage on Debtor’s property. The loan matured on February 21, 2009, but Debtor defaulted and CenterPoint filed a foreclosure action in state court on February 24, 2009. That proceeding was never resolved because it was interrupted by Debtor’s bankruptcy filing on May 18, 2010. In its Proof of Claim filed in the bankruptcy case, Center-Point asserts a secured claim of about $48,000,000. Given the property value found, Debtor has been found to have an equity cushion over the CenterPoint debt of more than $30 million.

Free access — add to your briefcase to read the full text and ask questions with AI

In Re Olde Prairie Block Owner, LLC, 448 B.R. 482, 2011 Bankr. LEXIS 1171, 2011 WL 1299374 (Ill. 2011).

448 B.R. 482 (In Re Olde Prairie Block Owner, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re: Julie Thuy Vu
Ninth Circuit, 2012