In re Narragansett Bay Commission General Rate Filing

808 A.2d 631, 2002 R.I. LEXIS 187, 2002 WL 31469355
CourtSupreme Court of Rhode Island
DecidedNovember 1, 2002
DocketNo. 2001-518-M.P.
StatusPublished
Cited by3 cases

This text of 808 A.2d 631 (In re Narragansett Bay Commission General Rate Filing) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Narragansett Bay Commission General Rate Filing, 808 A.2d 631, 2002 R.I. LEXIS 187, 2002 WL 31469355 (R.I. 2002).

Opinion

OPINION

WILLIAMS, Chief Justice.

In this petition for certiorari, the Narragansett Bay Commission (NBC) asks us to determine whether the Public Utilities [633]*633Commission (commission) properly ordered the NBC to retain and compensate an independent auditor to oversee the administration of its multimillion-dollar combined sewer overflow abatement project (CSO project). The commission, acting on the recommendation of the Attorney General, found that an independent auditor would serve the public interest by monitoring the CSO project to ensure that it remain within budget. The NBC is concerned that if appointed, an independent auditor would improperly infringe on its managerial discretion. Because we conclude that the commission’s order was made within the scope of its statutory authority and that it is clear that the independent auditor must not invade the prerogative of the NBC to manage the CSO project, we affirm.

I

Facts and Travel

Because of the limited capacity of some municipalities’ sewer systems, approximately two billion gallons of wastewater and storm water discharges into Rhode Island’s urban rivers and upper Narragansett Bay each year. The untreated sewage has a widespread negative impact on the environment. Congress’s Clean Water Act of 1972 required the NBC to eliminate or mitigate seventy combined sewer overflows in its service areas. See 33 U.S.C. § 1251; see also G.L.1956 § 46-15.6-2 (setting forth the importance of clean water to Rhode Island citizens). To comply with the federal mandate, the NBC instituted a capital improvement program which included the CSO project. The construction of the three-phase CSO project is expected to take twenty-two years to complete. The cost of the project is staggering — the original cost estimate in 1995 for phase I was $165 million dollars. It is expected that today’s cost estimate of $227 million will similarly be exceeded. It is believed that the CSO project will be the largest and most costly construction project ever undertaken by the state.

In June 2000, the NBC filed an application with the commission requesting permission to increase the utility rates charged to its customers primarily to maintain financing for the CSO project. The NBC proposed a 34 percent rate increase to be apportioned to each customer based on the customer’s water consumption. The NBC filed testimony and exhibits to support its application. In response, the Rhode Island Division of Public Utilities and Carriers (division), which “serve[s] the commission in bringing to it all relevant evidence, facts, and arguments that will lead the commission in its quasi-judicial capacity to reach a just result,” submitted its own testimony. Providence Water Supply Board v. Public Utilities Commission, 708 A.2d 537, 539 (R.I.1998) (quoting Providence Gas Co. v. Burke, 419 A.2d 263, 270 (R.I.1980)).

To provide an opportunity for public comment, hearings were held to discuss the application. The division and the NBC then began negotiating a settlement agreement (agreement) to present to the commission for its approval. During negotiations, Assistant Attorney General Paul Roberti (Roberti) from the Department of the Attorney General (department), initiated a discussion with NBC and division representatives about incorporating a provision for hiring an independent auditor to oversee the CSO project. Because both the division and the NBC were unwilling to adopt the proposal, the department filed a motion to intervene on behalf of the public. See G.L.1956 § 39-1-20; In re Island Hi-Speed Ferry, LLC, 746 A.2d 1240, 1245 (R.I.2000). The commission granted the motion.

[634]*634In November 2000, the agreement was presented to the commission for its approval. The commission held public evi-dentiary hearings on the agreement. During these hearings Roberti elaborated on the department’s position advocating for “some independent audit” of the CSO project. Roberti asked the commission to consider a position “to ensure that the costs that will arise from [the CSO] project are as low as possible.” Roberti explained that the auditor’s function would not be to “second guess” the engineering or design issues of the CSO project, but instead would be to monitor its costs and report to the commission.

The division opposed the appointment of an auditor. Stephen Scialabba (Scialab-ba), the division’s chief accountant, pointed out that the NBC already had a management services contract with The Louis Berger Group, Inc. (Berger) to oversee the project. In addition, Berger had hired Gilbane Company and Jacobs Associates (Gilbane), to manage the project’s construction. Furthermore, Scialabba believed that various members of the division staff fulfilled the duties of an overseer. The NBC agreed and presented Joseph Pratt (Pratt), vice president of Berger and the CSO project program manager, to explain the overseer functions already in place. Moreover, Pratt discussed the nuances of the competitive bidding process to which the NBC already was bound under state law to counter Roberta’s proposal that the auditor could review bids. Lastly, Pratt discussed the proactive nature of the Disputes Review Board (DRB) members who visit the construction site to ensure harmony and correct foreseeable problems to avoid time-consuming arbitration.

The parties then filed post-hearing memoranda elaborating on the independent auditor proposal. The department outlined several specific tasks that an independent overseer could address including (1) ensure fairness and reasonableness of CSO project budget targets, (2) perform appropriate investigative field work and document review, (3) attend critical project meetings, (4) when problems arise ensure that proposed solutions are cost-effective, (5) provide commission with updates and (6) evaluate costs of the second and third phases of the CSO project. In January 2001, the commission held a final hearing to further explore the independent oversight proposal.

The department presented two additional witnesses to support its recommendation. Attorney Michael McElroy (McElroy) testified that the independent overseer would be valuable to the commission because Berger representatives lacked independence as employees of a for-profit corporation. McElroy opined that the independence of the auditor would instill public confidence in the CSO project. Stephen Garfinkel (Garfinkel) testified in more detail about how an auditor could examine the structure of the accounting system for the CSO project. The NBC again presented Pratt who reiterated his opinion that an independent auditor would do tasks already being done by Berger, Gilbane, the NBC and the DRB. The division maintained that it could do some of the work proposed by the department at no additional cost to the ratepayers.

On October 25, 2001, the commission issued a report and order adopting the department’s recommendation to hire an independent auditor. The commission, relying upon G.L.1956 §§ 39-1-19 and 39 — 1— 26(b), required the NBC to hire and finance an independent auditor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Review of Proposed Town of New Shoreham Project
25 A.3d 482 (Supreme Court of Rhode Island, 2011)
Prov. Water v. Div. of Public Utilities
Superior Court of Rhode Island, 2010

Cite This Page — Counsel Stack

Bluebook (online)
808 A.2d 631, 2002 R.I. LEXIS 187, 2002 WL 31469355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-narragansett-bay-commission-general-rate-filing-ri-2002.