In Re McCrory Corp.

188 B.R. 763, 41 ERC (BNA) 2042, 1995 Bankr. LEXIS 1955, 1995 WL 688702
CourtUnited States Bankruptcy Court, S.D. New York
DecidedNovember 20, 1995
Docket19-10066
StatusPublished
Cited by4 cases

This text of 188 B.R. 763 (In Re McCrory Corp.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re McCrory Corp., 188 B.R. 763, 41 ERC (BNA) 2042, 1995 Bankr. LEXIS 1955, 1995 WL 688702 (N.Y. 1995).

Opinion

DECISION ON ADMINISTRATIVE EXPENSE PRIORITY STATUS OF ENVIRONMENTAL CLEAN UP COSTS

CORNELIUS BLACKSHEAR, Bankruptcy Judge.

This Court is asked to determine whether environmental clean-up costs incurred post-petition under the New Jersey Environmental Cleanup Recovery Act (“ECRA”) 1 , N.J.Stat.Ann. § 13:lK-6 to -35 (West 1991), resulting from debtor’s pre-petition actions are entitled to administrative expense priority pursuant to 11 U.S.C. §§ 503 and 507.

FACTS

McCrory Corporation (“McCrory”) leased certain real property in Jersey City, New Jersey (the “Property”) from Pegasus Industrial Associates (“Pegasus”). The Property, which included a truck terminal, was used by McCrory as a warehouse and distribution facility. Under the terms of the lease, McCrory agreed to comply with all Federal, State, and local environmental laws and to clean-up any environmental contamination resulting from the discharge of hazardous substances at the Property during the term of the lease. McCrory was further obligated to indemnify Pegasus for all claims stemming from any such discharges.

McCrory filed a Chapter 11 bankruptcy petition on February 26, 1992. Subsequently, McCrory moved to reject the lease with Pegasus pursuant to 11 U.S.C. § 365. Neither Pegasus nor any other party objected to the rejection and the court approved the lease rejection on July 13, 1992. At some point after filing its petition, but prior to rejection of its lease, McCrory ceased operations at the Property.

Upon McCrory’s rejection of the lease, Pegasus hired Environmental Waste Management Associates (“Waste Management”), an environmental consulting firm 2 , to assess the environmental contamination present at the site. This site assessment was commissioned in order to comply with ECRA, which requires that upon the closing of any industrial establishment or transfer of real property utilized in connection with hazardous substances, the owner or operator of the site must notify the New Jersey Department of *765 Environmental Protection and Energy of any discharge of hazardous substances at the site and, if necessary, prepare a clean-up plan. N.J.Stat.Ann. § 13:lK-9.

Waste Management issued a report dated August 19, 1992 indicating several areas of environmental concern at the site, including petroleum stains and the existence of above-ground and underground storage tanks. Pegasus requested that Waste Management submit a proposal for services required to bring the site into compliance with ECRA. The preliminary clean-up report, which Waste Management issued on September 18, 1992, estimated the initial costs to be $11,920. The report called for the closing of the tanks, tank excavation and removal, and continuing site assessments. This initial report was based only on a walk-through inspection, and did not include the cost of waste removal. The parties were aware that the additional costs required to comply with ECRA could be significant. Indeed, the costs through May 31, 1995 have totaled approximately $101,524.87. Part of the additional cost stems from remediation required to eliminate soil contamination observed during the excavation process and the continued monitoring of the site.

On May 12, 1993, ten months after McCro-ry rejected the lease, Waste Management submitted the clean-up plan to the New Jersey Department of Environmental Protection and Energy. The clean-up plan provided for removal of storage tanks by June 7, 1993. The tanks were ultimately removed in July, 1993.

In September, 1992, after McCrory left the Property and before implementation of the clean-up plan, another entity commenced operations at the Property, also utilizing the truck terminal facility.

Pegasus filed a motion seeking entry of an order declaring that the environmental cleanup costs are entitled to administrative priority pursuant to 11 U.S.C. §§ 503 and 507 and requesting current payment of these expenses.

McCrory opposes the motion and maintains that because the estate no longer has an interest in the property and the claims are based on debtor’s pre-petition activity, they are general unsecured claims.

There has been no evidence adduced that there was any discharge of hazardous substances at the Property post-petition, prior to the new tenant occupying the Property. Therefore, our analysis is limited to pre-petition actions, during the term of the lease, that resulted in post-petition clean-up costs.

DISCUSSION

Administrative priority is accorded to those - expenses that are “actual, necessary costs and expenses of preserving the estate.” 11 U.S.C. §§ 503(b)(1)(A) & 507(a)(1).

Claims for reimbursement of amounts expended on environmental clean-up costs arising from pre-petition activities are ordinarily considered general unsecured claims. Burlington Northern R.R. Co. v. Dant & Russell, Inc. (In re Dant & Russell, Inc.), 853 F.2d 700, 709 (9th Cir.1988); Southern Ry. Co. v. Johnson Bronze Co. (In re Johnson Bronze Co.), 758 F.2d 137, 141 (3d Cir.1985).

Some courts, however, have accorded these claims administrative status. Lancaster v. Tennessee Dep’t. of Health & Env’t (In re Wall Tube & Metal Products Co.), 831 F.2d 118 (6th Cir.1987); United States v. LTV Corp. (In re Chateaugay Corp.), 944 F.2d 997 (2d Cir.1991); In re National Gypsum Co., 139 B.R. 397 (N.D.Tex.1992).

Most courts that have accorded administrative expense priority to a claim based on pre-petition action that gives rise to post-petition environmental clean-up costs have relied on the combined effect of the Supreme Court decision in Midlantic National Bank v. New Jersey Dep’t. of Envtl. Protection, 474 U.S. 494, 106 S.Ct. 755, 88 L.Ed.2d 859 (1986), and the debtor’s obligation to maintain or preserve estate property in compliance with state environmental laws based on, either or both, the requirement noted by the Supreme Court in Ohio v. Kovacs, 469 U.S. 274

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Howard
533 B.R. 532 (S.D. Mississippi, 2015)
In Re Lyondell Chemical Co.
416 B.R. 108 (S.D. New York, 2009)
In Re Insilco Technologies, Inc.
309 B.R. 111 (D. Delaware, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
188 B.R. 763, 41 ERC (BNA) 2042, 1995 Bankr. LEXIS 1955, 1995 WL 688702, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-mccrory-corp-nysb-1995.