In re: Maui Electric Company, Limited.

Hawaii Supreme Court·Decided March 2, 2022·No. SCOT-21-0000041·Published

Opinion

Electronically Filed

Supreme Court

SCOT-XX-XXXXXXX

02-MAR-2022

02:35 PM

Dkt. 195 OP

IN THE SUPREME COURT OF THE STATE OF HAWAI‘I ---o0o---

In the Matter of the Application of MAUI ELECTRIC COMPANY, LIMITED

For Approval of Power Purchase Agreement for Renewable Dispatchable Generation with Paeahu Solar LLC.

SCOT-XX-XXXXXXX

APPEAL FROM THE PUBLIC UTILITIES COMMISSION (Agency Docket No. 2018-0433)

MARCH 2, 2022

RECKTENWALD, C.J., NAKAYAMA, McKENNA, AND EDDINS, JJ.;

AND WILSON, J., DISSENTING

OPINION OF THE COURT BY EDDINS, J.

After a contested case proceeding, the Public Utilities Commission (PUC) approved a power purchase agreement (PPA) between Maui Electric Company, Limited (MECO) and Paeahu Solar LLC (Paeahu).

The PPA followed competitive bidding that MECO and other electric utility companies collectively conducted in 2018. Paeahu was one of eight projects selected through this competitive procurement process. Under the PPA, MECO would purchase renewable energy from Paeahu’s solar-plus-battery plant located within Ulupalakua Ranch on Maui (the Project).

Appellant Pono Power Coalition (Pono Power), a Maui community group, asks this court to vacate the PUC’s approval of the PPA for two reasons. 1 First, Pono Power points to the winning bidders’ post-

selection use of the same counsel to negotiate non-price PPA terms. It argues the PUC failed to evaluate the common counsel’s involvement under the “rule of reason,” a burden- shifting standard created for Sherman Antitrust Act cases.

Second, Pono Power asserts that the PUC failed to fulfill its public trust duties. It claims the PUC merely catalogued the Project’s anticipated permits and left decision-making about trust resources to the agencies with jurisdiction over those permits. Instead, Pono Power contends, the PUC should have made

1 As a third point of error, Pono Power contests the PUC’s conclusion that Paeahu satisfied its community outreach obligations. This argument lacks merit. The PUC reviewed evidence about Paeahu’s community engagement activities. And it credited Paeahu’s responses to community concerns; Paeahu made design changes and explored an alternative location. The PUC then found that Paeahu fulfilled its community outreach requirements. We do not find clear error in the PUC’s findings.

explicit findings that identified the affected trust resources and how they would be protected.

We reject both arguments.

We decline to inject antitrust standards into PPA approval proceedings. Hawai‘i Revised Statutes (HRS) 2 chapter 269 already requires the PUC to examine potential anticompetitive practices. And those statutes equip the PUC with a framework for that analysis: they prescribe “the public interest” as the controlling principle.

We hold that the PUC appropriately evaluated the allegations of anticompetitive conduct. The PUC considered the circumstances relating to the winning bidders’ shared counsel, balanced other statutory factors, and found the PPA terms reasonable and in the public interest. The PUC was not required to apply antitrust standards in this analysis.

Next, we hold that the statutes governing the PUC’s PPA review – HRS §§ 269-6(b) and 269-145.5(b) - reflect the core public trust principles: the State and its agencies must protect and promote the justified use of Hawaiʻi’s natural beauty and natural resources. Thus, when there is no reasonable threat to a trust resource, satisfying those statutory provisions fulfills the PUC’s obligations as trustee. But when a project poses a

2 All references to HRS provisions reflect their latest published version as of the PUC’s Decision and Order 37340 approving the PPA.

reasonable threat, the public trust principles require more from the PUC: the commission must assess that threat and make specific findings about the affected trust resource.

Here, the record shows that the PUC conducted the statutory balancing. Under HRS § 269-6(b), the PUC considered the need to mitigate the risks associated with fossil fuel-based energy; it also weighed other “technical, economic, environmental, and cultural considerations” under HRS § 269-145.5(b). The PUC then found the PPA “in the public interest.” Because the record lacks a reasonable threat to a trust resource, this public interest-minded balancing satisfied the PUC’s public trust duties.

We affirm the PUC’s approval of the PPA.

I.

The Hawai‘i legislature has committed to protect the climate and mitigate climate change by reducing reliance on fossil fuels and converting to renewable energy sources.

In 2015, the legislature took a decisive step: it set a goal to reach 100% renewable energy by 2045. 2015 Haw. Sess. Laws Act 97, § 2 at 245-46; HRS § 269-92(a)(6).

To meet this target, the Hawaiian Electric Companies -

MECO, Hawaiian Electric Company, Inc., and Hawaii Electric Light Company, Inc. – developed a plan to competitively procure grid-

scale renewable power supplies. The PUC accepted this plan in 2017.

The first phase of competitive bidding began in early 2018.

The Hawaiian Electric Companies issued requests for proposals (RFPs) for O‘ahu, Maui, and Hawai‘i Island. The RFPs reflected comments from interested stakeholders. They also incorporated guidance from the PUC and PUC-appointed Independent Observers.

The Hawaiian Electric Companies conducted multi-step bid evaluations. The bidders’ pricing terms were set during this process. The utility companies ultimately selected eight projects: four on Oʻahu, two on Maui, and two on Hawai‘i Island. 3 Paeahu was one of the Maui projects.

The Hawaiian Electric Companies negotiated PPAs for the winning projects. Only non-price terms were discussed since the projects’ prices had already been fixed. During this PPA negotiation phase, one law firm represented the developers for the selected projects (the Finalists).

MECO and Paeahu agreed on the PPA terms. The Independent Observer overseeing MECO’s RFP process (the IO) concluded that MECO conducted bid evaluations and PPA negotiations on a “fair and consistent basis.”

3 Four developers submitted these eight projects.

MECO submitted the PPA for the PUC’s approval. 4 Besides MECO, the Division of Consumer Advocacy (Consumer Advocate or CA) became a party to the PPA approval proceeding. 5 Pono Power then moved to intervene or participate in the PPA approval proceeding. Recognizing Pono Power members’ right to a clean and healthful environment, the PUC granted Pono Power participant status. After considering Paeahu’s motion, the PUC also made it a participant.

The PUC held a two-day evidentiary hearing in December 2019. Witnesses testified and were cross-examined; they discussed the RFP process, PPA negotiations, pricing, greenhouse gas (GHG) analysis, community outreach, and Paeahu’s studies relating to the Project’s impact on cultural and natural resources. Both before and after the hearing, the parties and participants submitted and responded to information requests related to these issues.

In October 2020, the PUC approved the PPA. It issued Decision and Order No. 37340 (the Approval Order). After

4 MECO asked the PUC to review its requests in two stages: (1) addressing its PPA-related requests (including the recovery of costs associated with the PPA) first and (2) considering its request to construct an above-ground line extension later. The PUC granted the request. This appeal concerns the first stage. 5 The CA participated as an ex officio party per HRS § 269-51 and Hawaiʻi Administrative Rules (HAR) § 16-601-62(a). HRS § 269-51(a) requires the CA to “represent, protect, and advance the interests of all consumers . . . of utility services.”

investigating concerns about the Finalists’ common counsel and weighing environmental and other statutory considerations, the PUC found the PPA “in the public interest.”

Pono Power moved for reconsideration of the approval. The PUC denied that motion in Order No. 37553 (the Recon Order).

Pono Power appeals both the Approval and Recon Orders.

Free access — add to your briefcase to read the full text and ask questions with AI

In re: Maui Electric Company, Limited., (haw 2022).

In re: Maui Electric Company, Limited. (In re: Maui Electric Company, Limited.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Water Use Permit Applications
9 P.3d 409 (Hawaii Supreme Court, 2000)
Morgan v. Planning Department, County of Kauai
86 P.3d 982 (Hawaii Supreme Court, 2004)
Ohio v. American Express Co.
585 U.S. 529 (Supreme Court, 2018)
Ching v. Case
449 P.3d 1146 (Hawaii Supreme Court, 2019)
Lana'ians for Sensible Growth v. Land Use Commission.
463 P.3d 1153 (Hawaii Supreme Court, 2020)
National Collegiate Athletic Assn. v. Alston
594 U.S. 69 (Supreme Court, 2021)