In Re Lion Overall Co.

55 F. Supp. 789, 1943 U.S. Dist. LEXIS 1704
CourtDistrict Court, S.D. New York
DecidedSeptember 23, 1943
Docket78528
StatusPublished
Cited by6 cases

This text of 55 F. Supp. 789 (In Re Lion Overall Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Lion Overall Co., 55 F. Supp. 789, 1943 U.S. Dist. LEXIS 1704 (S.D.N.Y. 1943).

Opinion

BRIGHT, District Judge.

The United States petitions for a review of an order of the referee expunging its claim upon the ground that it is for a penalty, and, therefore, not provable under Section 93, sub. j, of the Bankruptcy Act (11 U.S.C.A.), which provides that “Debts owing to the United States * * * as a penalty or forfeiture shall not be allowed, except for the amount of the pecuniary loss sustained * * I think the order must be reversed and the petition sustained.

On July 30, 1940, the bankrupt entered into a contract with the United States under which he agreed to furnish 25,000 one-piece suits at a unit price of $2.12, less a discount of % of 1% for payment within twenty calendar days. They were to be furnished 10% within twenty-one days, 12% within the 'next seven days, and 16% each six days thereafter, until the quantity contracted for had been delivered. The contractor did not comply with his contract, -and on January 15, 1941, the government terminated the contract, at which time 5,991 suits had not been delivered. Thereafter, the United States procured 5,943 of the suits from another contractor at an excess cost of $3.56. The contract also contained the following clause:

“If the contractor refuses or fails to make delivery of the materials or supplies within the time specified in Article 1, or any extension thereof, the actual damage to the Government for the delay will be impossible to determine, and in lieu thereof the contractor shall pay to the Government, as fixed, agreed, and liquidated damages for each calendar day of delay in making delivery, the amount as set forth in the specifications or accompanying papers, and the contractor and his sureties shall be liable for the amount thereof: Provided, however, That the Government reserves the right to terminate the right of the contractor to proceed with deliveries of such part or parts thereof as to which there has been delay, and to purchase similar material or supplies in the open market or secure the manufacture and delivery thereof by contract or otherwise, charging against the contractor and his sureties any excess cost occasioned the Government thereby, together with liquidated damages accruing until such time as the Government may reasonably procure similar material or supplies elsewhere: ¡¡c * * ”

Under this clause, the government claimed there was due for liquidated damages $20,886.95, the computation and amount not being disputed. The contractor was entitled to a credit of $5,509.75 for suits furnished, and $8,648.06 for liquidated damages previously deducted from payments made to him, a total of $14,157.81. Crediting this amount, the government filed a. claim for the balance $6,729.14, plus the $3.56 excess cost, $8 for a set of master patterns and $10 for a sample suit (the latter two having been loaned to the government and not returned), a total of $6,750.70.

The referee disallowed all of the claim, holding that $6,729.14 thereof was for penalties and the balance was offset against the $14,157.81 due the bankrupt.

The clause quoted clearly embraces the agreement of the parties, both of whom recognized in unambiguous language that if the contractor shall fail to deliver on time, the actual damage to the government for the delay will be impossible to determine. The fact that more than excess cost was stipulated for justifies a conclusion that damages in excess of that established might be sustained which would not be *791 capable of ascertainment. The contract was made for an article of military equipment for our troops at a time when the war clouds from Europe were gathering ominously about this country and when it could reasonably be anticipated, certainly by the Army and Navy Departments, that sooner or later we might be embroiled in the conflict. While there were others in the country who were manufacturing similar garments, what damage might result from a delayed delivery could not be ascertained with accuracy. In any event, the agreement was made without any overreaching or fraud, and as an obvious spur to prompt performance.

Such an agreement is not against the public policy of the country. Robinson v. United States, 261 U.S. 486-488, 43 S.Ct. 420, 67 L.Ed. 760. Its construction and application will be governed by federal law. Duncan’s Heirs v. United States, 32 U.S. 435-449, 7 Pet. 435-449, 8 L.Ed. 739; Byron Jackson Company v. United States, D.C., 35 F.Supp. 665-667; Avev v. Leather Products Co., Ohio App. 1st District, December 14, 1942, 55 N.E.2d 813. There is no presumption of invalidity as to it; it is to be construed without bias. In re Outfitters’ Operating Realty Co., 2 Cir., 69 F.2d 90-92, affirmed Irving Trust Co. v. A. W. Perry, Inc., 293 U.S. 307, 55 S.Ct. 150, 79 L.Ed. 379.

The law lends no support to the contention that parties may not bona fide in a case where the damages are of an uncertain nature, estimate and agree upon a measure of damages which may be sustained from a breach of an agreement, and where they have been so liquidated the contract will be enforced. Sun Printing & Publishing Association v. Moore, 183 U.S. 642-662, 22 S.Ct. 240, 46 L.Ed. 366. The claimant must abide by his own words. Maryland Dredging & Contracting Co. v. United States, 241 U.S. 184-189, 36 S. Ct. 545, 60 L.Ed. 945. The courts after some pulling and hauling have become more tolerant of such provisions, have now become strongly inclined to allow parties to make their own contracts, and to carry out their intentions, even when it would result in a recovery of an amount stated as liquidated damages, upon violation of a contract, and without proof of the damages actually sustained. United States v. Bethlehem Steel Co., 205 U.S. 105-119, 27 S.Ct. 450, 51 L.Ed. 731. In that case, war with Spain was imminent, and the fact that not very long after the contract had been signed the war was near to its end, the. importance of the time element had largely disappeared, and practically no damage to the government had accrued, was not permitted to affect the meaning of a similar clause, nor render its language substantially worthless for any security for the proper performance of the contract as to the time of delivery. Such a clause will be given effect where the damages are uncertain in nature or amount, or are difficult of ascertaining, or where the amount stipulated for is not extravagant or disproportionate to the amount of the property lost as to show that compensation was not the object aimed at, or as to imply fraud, mistake, circumvention or oppression.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Rye v. Public Service Mutual Insurance
42 A.D.2d 749 (Appellate Division of the Supreme Court of New York, 1973)
Harbor Island Spa, Inc. v. Norwegian America Line A/S
314 F. Supp. 471 (S.D. New York, 1970)
Plymouth Village Fire District v. New Amsterdam Casualty Co.
130 F. Supp. 798 (D. New Hampshire, 1955)
Gordon v. Woods. In Re Young Corp
202 F.2d 476 (First Circuit, 1953)
United States v. Le Roy Dyal Co., Inc
186 F.2d 460 (Third Circuit, 1950)
Rumsey Mfg. Corp. v. U. S. Hoffman Machinery Corp.
88 F. Supp. 394 (W.D. New York, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
55 F. Supp. 789, 1943 U.S. Dist. LEXIS 1704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-lion-overall-co-nysd-1943.