In re Lien Against the District at City Center

CourtCourt of Appeals of Kansas
DecidedFebruary 28, 2020
Docket121184
StatusPublished

This text of In re Lien Against the District at City Center (In re Lien Against the District at City Center) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Lien Against the District at City Center, (kanctapp 2020).

Opinion

No. 121,184

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

IN RE: A PURPORTED LIEN AGAINST PROPERTY OF THE DISTRICT AT CITY CENTER, LLC.

SYLLABUS BY THE COURT

1. Mechanic's liens are remedial mechanisms, created by statute and designed to protect unpaid suppliers of labor and materials for real estate construction projects. The theory underlying the granting of a mechanic's lien against the property is that the property improved by the labor, equipment, material, or supplies should be charged with the payment of the labor, equipment, material, or supplies.

2. Once a mechanic's lien attaches to property, courts liberally construe Kansas' lien statutes to effect their remedial goal. But a party asserting a lien must strictly comply with Kansas' mechanic's lien statutes before that lien becomes enforceable.

3. Any person filing a lien—whether a contractor, subcontractor, or other supplier— must include a verified statement showing the owner's name, the claimant's name and address for service of process, a description of the real property, and a reasonably itemized statement and the amount of the claim.

4. Questions of statutory interpretation are legal issues over which appellate courts exercise unlimited review. When interpreting statutes, the fundamental rule to which all other rules are subordinate is that the intent of the legislature governs if that intent can be

1 ascertained. For this reason, courts look first to the statute's text; it is only when the meaning of the statutory language is ambiguous that courts turn to rules of statutory construction.

5. The Kansas Legislature enacted K.S.A. 58-4301 in response to the activities of militias and common-law type groups, to provide a quick and efficient method to remove facially bogus liens meant solely to intimidate and harass property owners.

6. K.S.A. 2019 Supp. 58-4301(e)(1) defines a purported lien as "fraudulent" if it is "not a document or instrument provided for by the constitution or laws of this state or of the United States." A court considering an allegation that a lien is "fraudulent" under this provision must not adjudicate whether the lien or interest is legitimate but only whether the documents are recognized under Kansas or federal law.

7. If a document is provided for by constitution or statute, it is not presumed fraudulent. A mechanic's lien is a document provided for by Kansas law and thus is not fraudulent under K.S.A. 2019 Supp. 58-4301(e)(1).

Appeal from Johnson District Court; JAMES F. VANO, judge. Opinion filed February 28, 2020. Reversed and remanded.

Jonathan Sternberg, of Jonathan Sternberg, Attorney, P.C., of Kansas City, Missouri, Jaclyn S. Maloney, of REAL Law, LLC, of Lee's Summit, Missouri, and Mandi R. Hunter, of Hunter Law Group, PA, of Prairie Village, for appellant Kansas City Steel Werx, Inc.

Taylor Jensen and Colin M. Quinn, of Long & Robinson, LLC, of Kansas City, Missouri, for appellee Haren & Laughlin Construction Company, Inc.

2 Before BUSER, P.J., SCHROEDER and WARNER, JJ.

WARNER, J.: Under Kansas law, a subcontractor may file a mechanic's lien with the district court against the property where he or she performs work to secure payment for unpaid labor and materials. Kansas statutes require a person filing a mechanic's lien to include a "reasonably itemized statement" explaining the lien amount. K.S.A. 60- 1102(a)(4). The property owner may seek to cancel the lien if this requirement is not met. Or if the subcontractor seeks to enforce the lien, any interested party—the property owner, the general contractor, or any other subcontractor—may challenge the amount of the lien or its itemization.

In this case, a subcontractor filed a mechanic's lien against a development project in Lenexa to recover payment for unpaid work and materials, but the documents accompanying the lien may not have supported the entire amount sought. Instead of challenging the lien through normal channels, the contractor claimed the lien was "fraudulent" under K.S.A. 2019 Supp. 58-4301—a statute adopted to address bogus and abusive filings by militias and sovereign-citizen groups. The district court granted the contractor's petition and summarily removed the lien, ruling that without a complete itemization the lien was "not a document or instrument provided for by" Kansas law. We reverse, as K.S.A. 2019 Supp. 58-4301 is not a proper avenue for considering the validity of a mechanic's lien.

FACTUAL AND PROCEDURAL BACKGROUND

The District at City Center, LLC, engaged Haren & Laughlin Construction Co., Inc., as the contractor to build a mixed-use development in Lenexa. The contractor then hired a subcontractor, Kansas City Steel Werx, Inc., to supply steel and labor for the project. The contractor and subcontractor entered into a contract for $2,859,387. As work

3 progressed, the subcontractor requested compensation for additional work through change orders submitted to the contractor; the contractor approved two of these change orders, totaling $25,410.45, increasing the projected total contract cost to $2,884,797.45.

To ensure payment for its unpaid services, the subcontractor filed a mechanic's lien in October 2018 against the development. The lien stated unpaid labor and materials costs in the amount of $418,627.94—the difference between $2,904,384.10 (the value of the work the subcontractor asserted it performed at the time the lien was filed) and $2,485,756.16 (the payments the subcontractor had received). The itemizations filed with the lien included documentation of the projected contract cost of $2,884,797.45 (including the original contract and two approved change orders) as well as several change-order requests for additional labor. The lien stated the value of this additional labor was $91,203. But the attached change-order requests only totaled roughly $66,000, leaving the remaining $25,000 in claimed labor unitemized and unexplained. The lien stated the subcontractor's work on the development project was still ongoing, meaning additional costs were being incurred.

Once the mechanic's lien was filed, the property owner could have filed an action challenging the lien. See K.S.A. 60-1108. Or the subcontractor could have attempted to amend or foreclose on the lien, allowing all interested parties to weigh in on the contractor's payment obligations. See K.S.A. 60-1105(a); K.S.A. 60-1106. None of these actions took place, however. Instead, the contractor filed a motion under K.S.A. 2019 Supp. 58-4301, claiming the lien was "fraudulent" and asking the court to set it aside.

Two weeks later, before the subcontractor filed a response, the district court granted the contractor's motion and removed the lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manhattan Mall Co. v. Shult
864 P.2d 1136 (Supreme Court of Kansas, 1993)
Boyce v. Knudson
548 P.2d 712 (Supreme Court of Kansas, 1976)
Haz-Mat Response, Inc. v. Certified Waste Services Ltd.
910 P.2d 839 (Supreme Court of Kansas, 1996)
In Re Purported Liens or Claims Against Samshi Homes, L.L.C.
321 S.W.3d 665 (Court of Appeals of Texas, 2010)
Texcalco, Inc. v. McMillan
524 S.W.2d 405 (Court of Appeals of Texas, 1975)
Buchanan v. Overley
178 P.3d 53 (Court of Appeals of Kansas, 2008)
In Re a Mechanic's Lien Against the City of Kansas City
154 P.3d 515 (Court of Appeals of Kansas, 2007)
Jose Luis Cardenas D/B/A J&S Body Shop v. Betty Wilson & Jeffery Wilson
428 S.W.3d 130 (Court of Appeals of Texas, 2014)
Huber Co. v. DeSouza
86 P.3d 1022 (Court of Appeals of Kansas, 1986)
Tarlton v. Miller's of Claflin, Inc.
227 P.3d 23 (Court of Appeals of Kansas, 2010)
Sierra Club v. Moser
310 P.3d 360 (Supreme Court of Kansas, 2013)
Neighbor v. Westar Energy, Inc.
349 P.3d 469 (Supreme Court of Kansas, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
In re Lien Against the District at City Center, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-lien-against-the-district-at-city-center-kanctapp-2020.