In Re Lamica Corp.

65 B.R. 849
CourtUnited States Bankruptcy Court, S.D. New York
DecidedSeptember 29, 1986
Docket19-22518
StatusPublished
Cited by1 cases

This text of 65 B.R. 849 (In Re Lamica Corp.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Lamica Corp., 65 B.R. 849 (N.Y. 1986).

Opinion

DECISION ON MOTION FOR AN ORDER EXPUNGING CLAIM OF BHM METAL PRODUCTS

HOWARD SCHWARTZBERG, Bankruptcy Judge.

The debtor in possession in this Chapter 11 case, moved to reduce the $68,215.26 proof of claim filed by Bernard Gordon and Marvin Gordon, individually and doing business as BHM Metal Products Company (“BHM”). The debtor contends that BHM failed to deliver on time certain metal frames and tubes pursuant to a written contract between the parties, with the result that the debtor was penalized under a contract it had with its customer, who in turn had contracted to sell children’s table desks to a school board.

FINDINGS OF FACT

1. The debtor, Lamica Corporation, filed with this court its petition for reorganiza-tional relief under Chapter 11 of the Bankruptcy Code on November 20,1985 and was continued in possession and authorized to operate its business pursuant to 11 U.S.C. §§ 1107 and 1108. The debtor is located in Hillburn, New York and is engaged in the business of manufacturing formica office furniture.

2. The creditor, BHM Metal Products Company, is a partnership whose premises are located in Sullivan County, New York and is engaged in the business of manufacturing and selling metal products.

3. On August 4, 1984, Messrs. Bob and Jim Gordon, representatives of BHM visited the office of Paul Richard, president of the debtor. BHM had previously done business with the debtor. Mr. Richard informed BHM’s representatives that the debtor had entered into a contract in May of 1984 with another supplier for the purchase of metal frames and tubes which were required by the debtor in order to satisfy a contract it had which called for delivery by August 27, 1984. Mr. Richard informed the BHM representatives that its supplier could not meet the delivery date and that other suppliers were unable to step in and meet the August 27th deadline. The BHM representatives assured Mr. Richard that BHM could satisfy the debt- or’s requirements. Mr. Richard testified that he told the BHM representatives that time was of the essence because the debtor had agreed to furnish formica table tops to a customer who, in turn, had agreed to sell children’s tables for use as desks to a school board. The debtor’s customer was threatening to pass on to the debtor any liquidated damages that the customer might be assessed by the school board.

4. The debtor’s president informed BHM’s representatives as to the details of the contract which the debtor’s supplier had failed to meet, including unit prices *851 and quantities. Mr. Richard prepared a handwritten purchase order (Exhibit 1) which divided the units ordered into three priorities; Priority # 1 was stated as “Need by 8/8/84;” Priority #2 contained items that were captioned as “Need By 8/10/84 or ASAP.” The term “ASAP” meant as soon as possible. Priority # 3, which comprised most of ordered products, stated: “Need By ASAP At Job Site, Farragut, TN.” The handwritten order contained four columns entitled “Quant”, “P/N”, “Descrip.” and “Price.” All of the columns were followed by a listing of items, except that the “Price” column was originally blank. The prices that the debt- or was to pay for the various units listed in the contract with the debtor’s previous supplier were to be forwarded to BHM at a later date.

5. The debtor’s president, Paul Richard, testified with respect to the August 4,1984 meeting with the BHM representatives that: “We informed them of what the unit prices were we were currently paying for those parts at which time they agreed to produce them for those prices.” 1 Mr. Richard testified that the total price for the merchandise, as specified in the contract with the previous supplier was $22,631, which BHM’s representatives agreed to meet.

6. A formal purchase order was not prepared on August 4, 1984. BHM failed to make the first priority delivery on August 8, 1984, as specified on the handwritten order, although this was the date picked by the debtor’s customer for assembling the products at the job site. The debtor’s president personally visited the BHM premises on August 11, 1984 and was informed that the materials had not yet arrived and that BHM was trying to get them from their suppliers.

7. Following his visit to the BHM premises, the debtor’s president addressed a handwritten note to his office manager to prepare a typed formal purchase order reflecting the information contained in the handwritten purchase order dated August 4, 1984, which should indicate that the delivery requirement for the total order was August 27, 1984. This note reads as follows:

Mark
Please issue purchase orders to B.H.M. for the metal parts as per the attached. Date of P.O. 8/4/84
Indicate Confirmation of orders placed w/ Bob & Jim Gordon in person on this day by P.E.R.
Indicate delivery requirement of 8/27/84. (total).
Delivery date approved by both of the above to me on 8/4/84 and again to me during visit to plant on 8/11/84.
Indicate paint finish (Polane).
(Polane)

(Exhibit 1).

8. On August 14, 1984, BHM’s representative visited the debtor’s premises and picked up a $4000 check as a deposit towards the contract between the parties.

9. On August 20, 1984, the debtor typed and mailed to BHM a formal purchase order which specified the three priority delivery requirements and stating that metal products had to be shipped “By 8/27/84 (Total)”. (Exhibit 1). The number of units of each item was listed on the order, but no prices were typed in the “Unit Price” column. The typed notes at the bottom of the order stated:

NOTES:
1/ Above is confirmation of orders placed with Bob & Jim Gordon in person on 6/-2Q/-84 by Paul Richard. (Cont’d) . . . 8/4/84
NOTES (Cont’d):
2/ Deliver requirement: 8/27/84 (TOTAL) (Delivery date approved by both gentlemen (Bob & Jim Gordon) to me on 8/4/ 84 and again to me during visit to plant on 8/11/84.)
3/ Paint Finish: POLANE
4/ Deposit payment of $4000.00 made on 8/14/84 (Check #0627).

*852 10. A copy of the handwritten order dated August 4, 1984, which was attached to a copy of the purchase order typed on August 20, 1984, was introduced in evidence by the debtor as Exhibit # 1. The column marked “Price” on the handwritten order contained a list of prices for each unit ordered. As in the case of the handwritten order dated August 4, 1984, the column entitled “Unit Price” on the debt- or’s purchase order that was typed on August 20, 1984 did not list any prices for the various units. The debtor’s president testified that these price figures were accumulated later by the debtor for BHM at the latter’s request.

11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Ousley
92 B.R. 278 (S.D. Ohio, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
65 B.R. 849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-lamica-corp-nysb-1986.