In re JBL Const. Co., Inc.

51 F.3d 266, 1995 U.S. App. LEXIS 13091, 1995 WL 131367
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 27, 1995
Docket93-2473
StatusUnpublished

This text of 51 F.3d 266 (In re JBL Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re JBL Const. Co., Inc., 51 F.3d 266, 1995 U.S. App. LEXIS 13091, 1995 WL 131367 (4th Cir. 1995).

Opinion

51 F.3d 266

NOTICE: Fourth Circuit Local Rule 36(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
In re: JBL CONSTRUCTION COMPANY, INCORPORATED, Debtor.
COLUMBIA GAS OF OHIO, INCORPORATED; Columbia Gas of
Kentucky, Incorporated, Plaintiffs-Appellees,
v.
JBL CONSTRUCTION COMPANY, INCORPORATED, Defendant-Appellant.

No. 93-2473.

United States Court of Appeals, Fourth Circuit.

Argued Nov. 3, 1994.
Decided March 27, 1995.

ARGUED: James William St. Clair, St. Clair & Levine, Huntington, WV, for appellant. James Richard Berendsen, Columbus, OH, for appellees.

Before RUSSELL, WILKINS and HAMILTON, Circuit Judges.

OPINION

PER CURIAM:

This case involves a contract dispute that arises from JBL Construction Co.'s bankruptcy proceedings. The issue is whether JBL Construction Co. ("JBL"), under its contracts with the plaintiff gas companies, had an obligation to provide all of the construction work assigned to it by the gas companies even though the contracts did not expressly require the gas companies to assign construction work exclusively to JBL. Although the bankruptcy court did not enforce the contracts because they lacked an express exclusivity provision, the district court implied the missing term from the history of dealings between the parties. However, we hold that the district court could not have implied an exclusivity provision based on the limited factual record before it. We vacate and remand.

I.

Columbia Gas of Ohio, Inc. and Columbia Gas of Kentucky, Inc. (collectively, "Columbia") are natural gas distribution companies that sell and transport natural gas to consumers. Columbia routinely hires contractors to install and maintain its underground pipeline system. JBL, the defendant below, was one of the contractors that Columbia used over the course of 26 years.

In January 1990, Columbia solicited bids on its pipeline construction and maintenance work for the 1990 construction season. When Columbia solicits bids and awards contracts, neither Columbia nor the bidders know exactly how much work will be required under the contracts. Although Columbia knows that it will need to provide its customers with installation and maintenance service during the year, it does not know the number of new customers it will have to service until later in the construction season. When contractors submit bids, they base their prices on the expectation that they will receive a certain volume of work. The actual volume of work performed in the previous year serves as a baseline. However, Columbia pays contractors only for the work actually performed during the contract year.

JBL was the lowest bidder on five contracts for the 1990 construction year. Each contract required JBL to perform pipeline construction and maintenance work in a specific geographic area of Ohio or Kentucky for a period of one year, beginning in March or April of 1990. Under each contract, JBL agreed to perform the work specified in the attached bid sheets for the various prices stated on those sheets. Neither the contracts nor the bid sheets specified the amount of work to be performed, because Columbia could not know at the time of contracting how much work it would require during the contract year. The contracts did not expressly provide that JBL had an exclusive right to perform all the work required in the contract territory during the contract year.

Columbia explained at a meeting with potential bidders on its contracts that three types of work fall outside the scope of each contract. First, Columbia retains the right to perform some or all of the work with its own crews. Columbia explained, however, that its crews cannot handle more than approximately ten percent of the total work. Second, large construction jobs in excess of $100,000 fall outside the contracts and are bid out separately. Third, in exceptional circumstances and situations, such as a stream crossing or a highway crossing, the contractor does not have to perform the work at the bid prices. This final provision protects the contractor from suffering huge losses in unusual situations where unforeseen circumstances increase the cost of performance.

JBL initially performed all of the work assigned to it under each of the five contracts. On August 22, 1990, however, JBL notified Columbia that it would cease all operations on September 7, 1990.

JBL filed for bankruptcy soon thereafter. JBL completed all work that Columbia had already assigned to it but did not complete the work for the remainder of the contracts' duration. Columbia entered into new contracts with several other contractors to finish the work JBL did not perform.

Upon discontinuance of work, the contracts between Columbia and JBL provided that if Columbia takes over and completes the work (or awards it to another contractor) at a higher cost than what JBL would have charged based on the unit prices under the contracts, then Columbia may collect the excess costs from JBL. Columbia calculated that the amount charged by the replacement contractors exceeded the amount that JBL would have charged under its contracts by $207,619.47.

After abandoning the contracts and filing for bankruptcy, JBL requested that Columbia pay for work that JBL had completed in the amount of $327,563.08. Columbia set off damages in the amount of $207,619.47 and paid JBL only the remaining $119,943.61.

Columbia then filed in the United States Bankruptcy Court for the Southern District of West Virginia a motion to setoff or recoup funds held by Columbia for JBL's failure to complete work under the construction contracts. The bankruptcy court held a hearing on October 16, 1991. At the close of Columbia's presentation of its case, the bankruptcy court denied the relief sought by Columbia. The bankruptcy court found that the contracts were illusory, and therefore unenforceable, because they did not bind Columbia to any obligation. Thus, JBL won in the bankruptcy court without even having to present its case.

Columbia appealed to the United States District Court for the Southern District of West Virginia. The district court implied a promise to employ JBL exclusively to perform the work and, therefore, determined that the contracts constituted valid requirements contracts. The district court reversed the judgment of the bankruptcy court, enforced the contracts, and granted the relief sought by Columbia.

JBL appeals the decision of the district court. We vacate the decision of the district court and remand for further proceedings.

II.

A contract is unenforceable for lack of mutuality of obligation if it fails to bind one of the parties to any sort of obligation. Morgan v. Morgan, 218 S.W.2d 410, 412 (Ky.1949); Preston v. First Bank of Marietta, 473 N.E.2d 1210, 1215 (Ohio Ct.App.1983).1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of Don Orriel Neis, Debtor-Appellant
723 F.2d 584 (Seventh Circuit, 1983)
Beech Creek Coal Co. v. Jones
262 S.W.2d 174 (Court of Appeals of Kentucky (pre-1976), 1953)
Morgan v. Morgan
218 S.W.2d 410 (Court of Appeals of Kentucky (pre-1976), 1949)
Preston v. First Bank of Marietta
473 N.E.2d 1210 (Ohio Court of Appeals, 1983)
Mr. Mark Corp. v. Rush, Inc.
464 N.E.2d 586 (Ohio Court of Appeals, 1983)
Fuchs v. United Motor Stage Co.
21 N.E.2d 669 (Ohio Supreme Court, 1939)
Reynolds Metals Co. v. Barker
256 S.W.2d 17 (Court of Appeals of Kentucky, 1953)
Hale v. Cundari Gas Transmission Co.
454 S.W.2d 680 (Court of Appeals of Kentucky, 1970)
Oglebay Norton Co. v. Armco, Inc.
556 N.E.2d 515 (Ohio Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
51 F.3d 266, 1995 U.S. App. LEXIS 13091, 1995 WL 131367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-jbl-const-co-inc-ca4-1995.