In Re Husting Land & Development, Inc.

255 B.R. 772
CourtUnited States Bankruptcy Court, D. Utah
DecidedNovember 22, 2000
Docket19-20208
StatusPublished
Cited by6 cases

This text of 255 B.R. 772 (In Re Husting Land & Development, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Husting Land & Development, Inc., 255 B.R. 772 (Utah 2000).

Opinion

MEMORANDUM DECISION AND ORDER

JUDITH A. BOULDEN, Bankruptcy Judge.

This is a contested matter arising from the application for allowance of administrative expense filed by R.A. McKell Excavating, Inc. (RAM) in the Chapter 11 case of Husting Land & Development, Inc. (Hust-ing). The issue presented is whether or not the administrative expense claim of RAM is allowable as a post-petition debt incurred in the ordinary course of business pursuant to 11 U.S.C. § 364(a). 1 During a two-day evidentiary hearing, RAM presented evidence in support of its argument that the debt owed to it for infrastructure improvements made to Husting’s real estate development was incurred in the ordinary course of business. In so doing, RAM offered, and the Court excluded, certain expert testimony on the basis that the failure to prove the reliability of the expert’s methodology precluded the Court from considering his opinion as to whether the debt was incurred in the ordinary course of business. Upon careful consideration of the remaining evidence, the pleadings and arguments, and upon an independent analysis of applicable law, the Court concludes that, applying the creditor *775 expectations/vertical dimension test, the debt incurred by Husting was not in the ordinary course of its business and, accordingly, RAM’s claim cannot be allowed as an administrative expense of the estate under § 503(b)(1).

FACTS

Husting was incorporated in 1994 for the purpose of developing a sixty-one acre, three-phase, sixty-nine lot residential subdivision in Draper, Utah, commonly known as Galena Hills. The purchase price of the real estate, which was in excess of $1,075,-000, was subordinated by the seller to a $1,500,000 development loan. In connection with the development of the Galena Hills project, Husting was required by Draper City and the Salt Lake County Sewer Improvement District to post cash escrow bonds (the Escrow Accounts) in the aggregate amount of approximately $612,000 to ensure payment to all persons supplying labor, services, equipment, or material to the Galena Hills project. Husting could obtain incremental release of funds in the Escrow Accounts to pay for improvements once the municipalities had approved the installation of various phases of the infrastructure.

Adjacent to Galena Hills was another subdivision development project, Parkway Estates, owned by John Holmes Construction, Inc. and Holmes Mesa Construction, Inc. (Holmes Mesa). Because Galena Hills required access through the Parkway Estates property, and Galena Hills and Parkway Estates shared common areas and roadways, it was necessary to install certain improvements and utilities that would benefit both subdivisions. Thus, Husting and Holmes Mesa entered into an Adjoining Subdivisions Agreement in which Husting agreed to complete certain improvements on Parkway Estates, and Holmes Mesa agreed to reimburse Hust-ing on a pro rata basis for its construction expenses. The Adjoining Subdivisions Agreement provided that reimbursement funds would not be paid to Husting until twenty-four months after final inspection and approval of construction by various municipalities, and then only if certain other conditions were met.

In February 1996, Husting entered into a Development Agreement with Construct Tech, in which Construct Tech agreed to provide excavation and construction services for the Galena Hills project, including storm drains, sewer, curb and gutter, sidewalk and street improvements. Construction on Galena Hills and the adjoining Parkway Estates subdivision was to begin in April of 1996. However, Construct Tech did not actually break ground on the project until June of that year. From its inception, the relationship between Hust-ing and Construct Tech was fraught with problems and disagreements. Husting’s sole shareholder and president, Leon Har-ward (Harward), provided uncontroverted testimony that Construct Tech’s work was incomplete, substandard and defective. Ultimately, in November of 1996, Hustings terminated its contract with Construct Tech.

As a result of difficulties encountered with Construct Tech, the Galena Hills project was seriously behind schedule and Husting was unable to meet payment obligations on its construction financing. On January 14, 1997, Husting, as debtor-in-possession, filed its voluntary petition for relief under Chapter 11. At the time of its Chapter 11 filing, Husting’s intention for reorganization was to complete necessary subdivision improvements to Galena Hills and then sell the improved lots to pay secured and unsecured creditors.

In February 1997, Harward and Rick McKell (McKell), President of RAM, visited the Galena Hills site to assess the work necessary to correct defects in the excavation and construction work and complete the project. At the site, McKell observed open trenches, pipelines that were not backfilled, lidless manholes and a number of other deficiencies. After further discussion between the parties, Harward invited RAM to bid on the project. RAM’s bid *776 proposal, for work on sewer, water, storm drain, irrigation and site work, totaled $258,191.40. In April 1997, Husting and RAM entered into a post-petition agreement (Construction Agreement), whereby RAM agreed to correct the defective work performed pre-petition by Construct Tech and to complete the remaining work on Phase II of the Galena Hills and Parkway Estates projects on a time and materials basis. The Construction Agreement provides as follows:

2. Contract Sum: The owner shall pay the Contractor in current funds for the Contractor’s performance of the Contract, subject to additions and deductions as provided for herein, as follows:
A. During the process of correcting the other contractor’s work to meet City and Sewer District requirements, R.A. McKell Excavation will invoice on a time and materials basis. Once deficiencies have been corrected progress can then proceed at agreed to unit price basis.
3. Progress Payments:
B. Based upon application for payment submitted to the Owner by the Contractor, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided herein. The period for payment shall be bi-weekly or as determined by the contractor but at no time will the billing period be less than bi-weekly. Owner agrees to make prompt application for payment from the escrow accounts presently established for the purpose of providing funds to pay the Contract Sum....

RAM Exhibit 11, Construction Agreement at ¶¶ 2 and 3.

Prior to entering into the Construction Agreement, RAM was aware that Husting had filed for relief under Chapter 11 and understood that the only present sources of payment for its work was the approximate $612,000 in the Escrow Accounts established pursuant to the bonds with Draper City and the Salt Lake County Sewer District.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jubber v. SMC Electrical Products, Inc.
798 F.3d 983 (Tenth Circuit, 2015)
In Re Ockerlund Construction Co.
308 B.R. 325 (N.D. Illinois, 2004)
In Re Blessing Industries Inc.
263 B.R. 268 (N.D. Iowa, 2001)
In Re Canvas Specialty, Inc.
261 B.R. 12 (C.D. California, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
255 B.R. 772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-husting-land-development-inc-utb-2000.