In re Hudson River Water Power Co.

148 F. 877, 1906 U.S. Dist. LEXIS 100
CourtDistrict Court, N.D. New York
DecidedNovember 26, 1906
StatusPublished
Cited by1 cases

This text of 148 F. 877 (In re Hudson River Water Power Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Hudson River Water Power Co., 148 F. 877, 1906 U.S. Dist. LEXIS 100 (N.D.N.Y. 1906).

Opinion

RAY, District Judge.

Prior to the filing of the petition in bankruptcy, the National Contracting Company, the main petitioning creditor, éntered into a written contract with the Hudson River Water Power Company whereby it agreed to construct for the latter company a masonry dam across the Hudson river at a designated point in consideration of certain compensation to be paid from time to time, and which was to be ascertained in certain ways with certain named prices for work as a basis'.

The contracting company entered on the performance of the contract, and in all respects complied with its requirements down to a time when the Hudson River Company undertook to make certain changes in the form and material of the dam, viz., by substituting an earth dam with a masonry core for the masonry dam the contracting company had agreed to build. The officers of the Hudson River Company claimed and asserted to the contracting company that it had decided to make, and had made, the change, and demanded and required that the contracting company proceed with and complete the work in accordance with the changed or new plans and specifications. The contracting company denied the right of the Hudson River Company to make these changes or require it to proceed under and in accordance there*with, insisting that the changes were fundamental and made a new contract, one they had not assented to, one the parties had mutually agreed they would not make. The contracting company insisted that, while it had agreed to changes in form and material such as the Hudson River Company might from time to time determine upon, still, these were limited to changes, etc., and material in the construction of a masonry dam, and did not authorize the substitution of an earth dam with a mere core of masonry. The Hudson River Company insisting and demanding the new construction, and, in effect, forbidding the construction in any other way, the contracting company insisted the Hudson River Company had broken the contract, and thereupon aban-[879]*879cloned the work and sued in the Supreme Court of the state of New York for damages for the alleged breach and for the amount due it for work done under the agreement.

The defendant, Hudson River Company, denied a breach on its part, and alleged a breach by the plaintiff, the contracting company, and counterclaimed its alleged damages. A trial o'f the action before Rx-Judge Bookstaver as referee resulted in a judgment in favor of the National Contracting Company against the Hudson River Water Power Company on the 12th day of April, 1905, for $51-7,696.10, of which $97,-126.77 was for work done and not: paid for.

After the referee had made his report and just before the entry of the judgment, the defendant, Hudson River Water Power Company, mortgaged all its property to certain other companies for about $7,000,000, a sum largely in excess of the value of all its property, real and personal,' including all property lights and franchises o f every kind and nature. This was not based on any new or present consideration and the contention was that the mortgages were without any consideration whatever. Kxecution was issued and returned unsatisfied and these proceedings in bankruptcy were then instituted. The mortgagees under the state law immediately procured the appointment of a receiver and purported to take possession’ of all the property. This court, on the filing of the petition in bankruptcy, duly appointed a receiver 'who took possession of all the property he could find, but same, including all rights and franchises, was evidently of insufficient value to satisfy any considerable part of the mortgages. A motion was made to dismiss the proceedings and an answer denying insolvency was interposed, and it was also denied that the petitioners were creditors, etc. This court appointed a special master to take evidence and report the facts. A large amount of evidence was taken and reported to the court, and the matter was about to be submitted on .argument when the petitioning creditors and the alleged bankrupt and all directly interested in the proceeding entered into a stipulation and agreement, in substance that, pending the final adjudication and determination in the state courts of the claim of the National Contracting Company against the said Hudson River Water Power Company, certain moneys and securities should be placed and left with a designated person and trust company, appointed and approved by this court, as security for such claim and any judgment the contracting company might obtain against the Hudson River Company thereon. The money, etc., so deposited is to be applied to the payment of the claim or to the payment of such part of it, if any, as the contracting- company may be adjudged entitled to. An appeal by the Hudson River Company from the judgment first mentioned establishing such claim was then pending, and the stipulation expressly covered the contingency of a reversal and the granting of a new trial and of a protracted litigation over the claim with possible varying results in the different appellate courts. It was expressly contemplated by the parties and by the court, in making its order ratifying and approving the stipulation and agreement, that the judgment might be reversed; that a result adverse to the National Contracting Company might be reached on a new trial in the trial court and that appeals might he necessary, and even a third trial had [880]*880and appeals taken from any judgment then obtained, before a final determination was arrived at. All these contingencies were considered and provided for by the general terms of the stipulation. The heart of the whole agreement was that the deposit should stand as security for the claim until its merits were finally passed upon and determined by the appellate courts in case the questions involved should be taken there. Tire National Contracting Company was not to be paid from the deposit in case a new or second trial, if granted, resulted in a judgment in its favor unless the appellate courts affirmed the judgment, if taken there for review; nor was the deposit to be released in case a second or new trial, if granted, resulted in a decision adverse to the contracting company, unless such determination should be affirmed in case an appeal was taken. The obligations were mutual,' and were intended to be, and the final determination of the litigation was to settle the question of either the release of the deposit or its appropriation to the payment of the claim. This is the only fair and logical construction and interpretation of the stipulation and order. Such was the understanding of this court after a full and fair hearing as to the stipulation and its purpose. On the making and filing of the stipulation and of the order of this court approving same, and, pursuant to its terms, the receiver appointed by this court was discharged and the Hudson River Company was restored to and resumed full control of its property and business, and the bankruptcy .proceeding was and has been held in abeyance pending the final determination of such claim. On the ap--peal from the judgment, it was reversed, and a new trial ordered. On the new trial the referee, Hon. Alton B. Parker, has held that there was no breach of the contract by the Pludson River Company and that there was a breach by the National Contracting Company, and, on its counterclaim for damages, he has given the defendant, Hudson River Water Power Company, an affirmative judgment for damages to the amount of $383,352.60 besides costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gay v. Hudson River Electric Power Co.
184 F. 631 (U.S. Circuit Court for the District of Northern New York, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
148 F. 877, 1906 U.S. Dist. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-hudson-river-water-power-co-nynd-1906.