In Re Harnischfeger Industries, Inc.

294 B.R. 47, 2003 Bankr. LEXIS 745, 2003 WL 21180084
Procedural entryThis page is a short order in In Re Harnischfeger Industries, Inc.. Read the opinion of the Court — 293 B.R. 650
United States Bankruptcy Court, D. Delaware·Decided May 16, 2003·No. 19-10408·Published

Opinion

MEMORANDUM OPINION

PETER J. WALSH, Bankruptcy Judge.

This opinion addresses debtor Harnisch-feger Industries, Inc.’s (“HU”) objection to Rockwell International Corporation’s (“Rockwell”) claim number 7082 (the “Claim”). HII asserts that the Claim is unenforceable under Wisconsin contract law and should be expunged pursuant to *50 11 U.S.C. § 502(b)(1). 1 See Doc. # 8455 at 7. Rockwell asserts that debtor Beloit Corporation, an HII subsidiary (“Beloit” and collectively with HII, “Debtors”), owed Rockwell for equipment purchases under prebankruptcy contracts and that following Beloit’s breach of those contracts Be-loit offered certain payment terms to Rockwell to satisfy the obligations. Rockwell contends that the parties created a binding contract upon Rockwell’s acceptance of Beloit’s payment terms and that HII guaranteed Beloit’s performance of the contract. See Doc. # 12624 at 10-15. Alternatively, Rockwell requests that the Court apply the doctrine of promissory estoppel to allow the Claim. See id. at 21. HII characterizes the Beloit-Rockwell post breach communications as preliminary negotiations and asserts that neither party assented to a payment agreement outside of the previously existing contract obligation. See Doc. # 12382 at 9-10. HII rejects Rockwell’s contention that a May 13, 1999 letter from Beloit to Rockwell constitutes an HII guarantee. See Doc. # 12682 at 22-26. For the reasons discussed below, I conclude that a binding payment plan never existed between Beloit and Rockwell because the parties never agreed on the essential terms of the payment plan. Absent an enforceable Beloib-Rockwell payment terms agreement, HII cannot be liable on any guarantee basis. Furthermore, I find that even if a payment terms agreement existed between Beloit and Rockwell, HII did not guarantee Be-loit’s performance thereunder. 2

BACKGROUND

Each party relies heavily on the business communications among the principal officers of HII, Beloit and Rockwell in support for their respective positions. These communications provide the fact pattern associated with the negotiations and the outcome of this dispute rests on the interpretation of, and, the weight assigned to, these communications. For convenience of reference each company’s principal participants are as follows:

For HII:
John Hanson (“Hanson”) — President, CEO and Chairman of the Board
Mark Readinger (“Readinger”) — Senior Vice President (and also with Beloit)
For Beloit:
Mark Readinger (“Readinger”) — President and director of Beloit
William Hackett (“Hackett”) — Executive Vice President (Operations)
Robert Seidel (“Seidel”) — Director of Purchasing
Bernard Sturgeon (“Sturgeon”) — Purchasing Manager (Jacksonville, FL)
For Rockwell:
Robert Eisenbrown (“Eisenbrown”)— Vice President (Drives Businesses)
Robert Van Lieshout (“Van Lieshout”)— Manager, Forest Products Division

This contested matter results from Asia Pulp & Paper’s (“APP”) failed attempt to construct a paper plant in Perawang, Indonesia. In 1997, APP contracted with Beloit for paper processing machinery. Beloit, in turn, contracted with Rockwell for several component pieces Beloit needed for its APP project. Of the several purchase orders generated by Beloit and Rockwell, the parties only address PPM 4 and PPM 5 (collectively, the “Purchase Orders”) in their pleadings.

APP’s project ran into financial and construction difficulties and APP suspended its purchasing obligations under the *51 APP-Beloit purchase orders. 3 At the time of suspension, Beloit had contracted with Rockwell, and Rockwell had already completed a substantial portion of its obligations to Beloit under the Purchase Orders. Neither APP nor Beloit initially informed Rockwell of APP’s intention to suspend the APP-Beloit contracts. Beloit disclosed the suspension to Rockwell during a January 25, 1999 status meeting that addressed the progress of the Purchase Orders. At the meeting, Beloit requested cancellation figures for the Purchase Orders. Rockwell complied and advised that total cancellation charges were $23,825,403.00 for PPM 4 and $4,824,833.00 for PPM 5. 4 See Doc. # 12682, Ex. 2. Beloit did not definitively cancel the Purchase Orders until February 11, 1999. In a letter to Eisenbrown, Hackett stated that Beloit intended to “exercise[ ][its] contractual right to suspend work under the Purchase Order until further notice.” See Doc. # 12624, Ex. 1; Doc. # 12682, Ex. 3. 5 The Purchase Orders only provided for cancellation and did not provide for a general suspension right. See Doc. # 12624, Ex. 18, at 9-11. Hack-ett asked Rockwell to investigate alternative uses for any completed machinery and also requested a meeting to negotiate payment terms. See Doc. # 12624, Ex. 1. The meeting would occur on May 4, 1999, after Beloit received and analyzed Rock■well’s mitigation of damages alternatives.

On May 3, 1999, Sturgeon circulated possible payment plan terms to other Be-loit employees in preparation for the Be-loit-Rockwell meeting. See Doc. # 12624, Ex. 2. Sturgeon’s proposal made the following assumptions: (1) that Beloit owed $2,824,833.00 on PPM 5; (2) that Beloit owed $20,864,244.00 on PPM 4; (3) cost of . money or interest charges were not included; (4) the payments would begin November 1, 1999; and (5) storage costs were to be negotiated. See id. Sturgeon calculated that Beloit would satisfy PPM 5 in eight monthly payments of $353,104.00. PPM 4 would be paid in eighteen months, seventeen payments of $1,159,999.00 and a final $1,161,244.00 installment. See id.

Beloit presented Sturgeon’s proposal toward the close of the meeting. See (Doc # 12624), Ex. 5, at 3. During the ensuing discussion, Rockwell stated that HII would be required to back Beloit’s proposal with a parent guarantee. See id. The Beloit representatives promised to discuss the guarantee with HII personnel and provide Rockwell with an immediate answer.

Hackett coordinated Beloit’s efforts to arrange for the guarantee and queried Readinger about the possibility of HII guaranteeing any Beloit-Rockwell payment agreement. See Doc. # 12624 at 7. Readinger told Hackett that Beloit should submit a guarantee request to HII after Beloit reached an agreement on the payment terms and to not “let [a guarantee] stand in the way of getting an agreement.” See id. at 8.

Free access — add to your briefcase to read the full text and ask questions with AI

In Re Harnischfeger Industries, Inc., 294 B.R. 47, 2003 Bankr. LEXIS 745, 2003 WL 21180084 (Del. 2003).

294 B.R. 47 (In Re Harnischfeger Industries, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pamperin v. Trinity Memorial Hospital
423 N.W.2d 848 (Wisconsin Supreme Court, 1988)
Skrupky v. Elbert
526 N.W.2d 264 (Court of Appeals of Wisconsin, 1994)
NBZ, INC. v. Pilarski
520 N.W.2d 93 (Court of Appeals of Wisconsin, 1994)
Hoffman v. Red Owl Stores, Inc.
133 N.W.2d 267 (Wisconsin Supreme Court, 1965)
Management Computer Services, Inc. v. Hawkins, Ash, Baptie & Co.
557 N.W.2d 67 (Wisconsin Supreme Court, 1996)
Todorovich v. Kinnickinnic Mutual Loan & Building Ass'n
298 N.W. 226 (Wisconsin Supreme Court, 1941)
Francis H. Leggett & Co. v. West Salem Canning Co.
144 N.W. 969 (Wisconsin Supreme Court, 1914)