In re Green Brook Flood Control Project

850 A.2d 596, 370 N.J. Super. 122, 2004 N.J. Super. LEXIS 220
CourtNew Jersey Superior Court Appellate Division
DecidedJune 22, 2004
StatusPublished
Cited by2 cases

This text of 850 A.2d 596 (In re Green Brook Flood Control Project) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Green Brook Flood Control Project, 850 A.2d 596, 370 N.J. Super. 122, 2004 N.J. Super. LEXIS 220 (N.J. Ct. App. 2004).

Opinion

The opinion of the court was delivered by

SKILLMAN, P.J.A.D.

The issue presented by this appeal is whether the cost of relocation of public utility facilities necessitated by a flood control project constructed under the State Flood Control Act, N.J.S.A. 58:16A-1 to -17, must be paid by the State or the public utility. We conclude that the directive of N.J.S.A. 58:16A-8, that the total cost of any relocation of utility facilities required under the Act “shall be considered as a part of the cost of the work,” reflects a legislative intent that the State pay the cost of such relocations.

By enactment of § 401 of the Water Resources Act of 1986 (Pub.L. No. 99-662), Congress authorized the construction of the Green Brook Flood Control Project within a sixty-five square mile watershed that encompasses parts of Union, Somerset and Middlesex counties. The project envisions the creation of 66,540 feet of levees, 11,220 feet of floodwalls, 10 bridge replacements, a bridge removal, interior drainage facilities and non-structural measures, and 8 closure structures, to provide a 150-year level of flood protection. The Water Resources Act authorizes the expenditure of $287,053,000 as the federal share of this joint federal-state project.

The State Flood Control Act (the Act), which was first enacted in 1948, L. 1948, c. 351, provides the requisite authorization for the State to participate in such a federal-state flood control project. Under this legislation, the Commissioner of the Department of Environmental Protection (DEP) is authorized “to carry out the State’s participation in a Federal program of flood control.” N.J.S.A. 58:16A-5. The Commissioner’s powers include determining whether a flood control project requires the removal, relocation and reconstruction of public utility facilities. N.J.S.A. 58:16A-8. However, an order by the Commissioner for the relocation of public utility facilities must be approved by the Board of Public Utilities (BPU) before it becomes effective. Ibid.

In 1999, the DEP entered into a project cooperation agreement with the United States Army Corps of Engineers for construction of the Green Brook Flood Control Project. The agreement re[125]*125quires the State to contribute at least 25% of the total project structural costs.

To carry out this agreement, the Commissioner issued a determination order on May 24, 2001, which required various public utilities, including appellants, to remove, relocate and/or reconstruct specified facilities located within the project area. Around the same time, appellants entered into agreements with the DEP under which they reserved their rights to seek recovery of the costs associated with the relocation of their facilities from the State. The DEP took the position in both agreements that appellants were responsible for those costs.

As required by the Act, the Commissioner’s order requiring the removal, relocation and reconstruction of public utility facilities in the area of the Green Brook Flood Control Project was submitted to the BPU for approval. While the matter was under review by the BPU, the Attorney General rendered a legal opinion that the costs of the relocation of such facilities must be borne by the public utilities and not by the State. In accordance with this opinion, by order dated January 17, 2002, the BPU approved the Commissioner’s relocation order, and required the public utilities to bear the costs, subject to recoupment in future ratemaking proceedings.

Appellants filed separate appeals from the part of the order that requires them to bear the cost of the removal, relocation and reconstruction of their facilities necessitated by the flood control project, which we consolidated.

In their joint brief, appellants argued not only that the BPU, based on the Attorney General’s advice, had incorrectly construed the Act to impose responsibility upon them for the costs of relocation of their facilities, but also that the BPU had acted beyond its jurisdiction in deciding this legal issue and had violated the Administrative Procedure Act, N.J.S.A. 52:14B-1 to -25, and requirements of due process by deciding the issue without notice to affected parties. However, appellants agreed at oral argument that this court has jurisdiction to decide whether the Act requires [126]*126public utilities or the State to pay the cost of the relocation of public utility facilities necessitated by a flood control project, and that we should decide this legal issue now rather than remanding the case to the BPU or DEP.

The common law rule is that a public utility must bear the cost of any relocation of its facilities necessitated by the construction of a public improvement project. Pine Belt Chevrolet, Inc. v. Jersey Cent. Power & Light Co., 132 N.J. 564, 572-73, 626 A.2d 434 (1993); Port of New York Auth. v. Hackensack Water Co., 41 N.J. 90, 97-98, 195 A.2d 1 (1963). However, the legislation authorizing a public project may alter this common law rule and. place the financial responsibility for any required relocations of public utility facilities upon the government agency that is constructing the project. Id. at 101, 108, 195 A.2d 1. Therefore, the question is whether the Act reflects a legislative intent to place the financial responsibility for any relocation of public utility facilities necessitated by a flood control project upon the State rather than the utilities.

The governing section of the Act states in relevant part:

Whenever the commissioner shall determine that the construction of a flood control- project requires the removal, relocation and reconstruction of any plants, works, holders, pumping stations, pipes, mains, tunnels, bridges, tracks, generating or switching stations, substations, transformers, conduits, cables, wires, towers, poles, or other structures, equipment, apparatus, or appurtenances (herein called “facilities”) of any public utility, ... the public utility owning or operating such facilities shall remove, relocate and reconstruct the same, upon the order of the commissioner, and the total cost and expense of the removal, relocation and reconstruction of such facilities, including the cost of installing such facilities in a new location or new locations, and the cost of any lands or any rights or interests in lands, or any other rights, required to accomplish such removal, relocation and reconstruction, shaU be considered as a part of the cost of the work.
[N.J.S.A. 58:16A-8 (emphasis added).]

This section has not been interpreted in any reported opinion. Moreover, neither appellants nor the DEP have offered any evidence concerning how the financial responsibility for the relocation of utility facilities was assigned in connection with other flood control projects constructed under the Act. Consequently, this appeal involves solely the interpretation of the language of [127]*127N.J.S.A. 58:16A-8, considered in light of certain other sections of the original Act.

The only reference to the term “work” in the Act other than in N.J.S.A. 58:16A-8 is contained in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Fire & Casualty Co. v. New Jersey Division of Taxation
868 A.2d 346 (New Jersey Superior Court App Division, 2005)
AMERICAN FIRE v. NJ Div. of Tax.
868 A.2d 346 (New Jersey Superior Court App Division, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
850 A.2d 596, 370 N.J. Super. 122, 2004 N.J. Super. LEXIS 220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-green-brook-flood-control-project-njsuperctappdiv-2004.