IN THE SUPREME COURT OF TEXAS ══════════ No. 15-0882 ══════════

IN RE DEAN DAVENPORT, ET AL., RELATOR

══════════════════════════════════════════ ON PETITION FOR WRIT OF MANDAMUS ══════════════════════════════════════════

JUSTICE BOYD, joined by JUSTICE LEHRMANN, concurring.

The Client,1 represented by the Attorneys,2 settled a lawsuit and received both monetary

payments and ownership interests in a business referred to as WECO. Pursuant to their

contingency-fee agreement, the Client paid the Attorneys forty percent of the monetary payments.

The issue is whether the agreement also requires the Client to give the Attorneys forty percent of

the WECO interests. A jury found that the agreement does not. The trial court then concluded that

it unambiguously does and granted a new trial. The Court concludes that it unambiguously does

not and orders the trial court to set aside the new-trial order and enter judgment for the Client.

Who’s being unreasonable here? When a contract’s language can reasonably support only

one definite or certain meaning, it is unambiguous, and courts must construe it as a matter of law.

Nat’l Union Fire Ins. Co. v. CBI Indus., Inc., 907 S.W.2d 517, 520 (Tex. 1995) (per curiam) (citing

1 Dean Davenport, Dillon Water Resources, Ltd., 5D Drilling and Pump Service, Inc. f/k/a Davenport Drilling & Pump Service, Inc., 5D Water Resources, LLC f/k/a Davenport Oper., LLC, Water Exploration Co., Ltd., WAD, Inc., Water Investment Leasing Company, LLC, Blue Gold Resources Management, LLC, Blue Gold Properties, LLC, and Blue Gold Development, LLC (collectively, the Client). 2 Tom Hall, Thomas C. Hall, P.C., and Blake Dietzman (collectively, the Attorneys). Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983)). But if the language is fairly susceptible to

more than one reasonable interpretation, it is ambiguous and its meaning becomes a fact issue for

the jury to decide. See id.3 Is the Client’s, jury’s, and Court’s construction of the agreement

unreasonable, as the trial court concluded? Or is the Attorneys’ and trial court’s construction

unreasonable, as this Court concludes?

I conclude that the agreement is ambiguous because it reasonably supports both

constructions. The trial court thus erred by deciding that the agreement unambiguously requires

the Client to give the Attorneys forty percent of the WECO interests, but this Court errs by deciding

that it unambiguously does not. Instead, the agreement’s meaning presents a jury issue. The trial

court was initially correct to submit it to the jury, and the jury found that the agreement does not

require the Client to give the Attorneys the WECO interests. I join the Court’s judgment ordering

the trial court to vacate its new-trial order and enter judgment for the Client, but I would order the

trial court to enter the judgment based on the jury’s verdict, not because the agreement

unambiguously favors the Client as a matter of law.

The agreement at issue is a contingency-fee agreement between the Attorneys and “Dean

Davenport on his behalf and on behalf of related entities, 5D Drilling and Pump Services, Inc.,

Dillon Water Services, LP, and Wanda Davenport.” The agreement’s express “purpose” is to

“successfully pursue Client’s claim arising out of business dealings with WECO.” (Emphasis

added). To that end, the Client expressly authorizes the Attorneys “to act in his . . . behalf to obtain

3 See also Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986) (per curiam) (“The jury’s task is to decide a fact issue based on the preponderance of the evidence.”); Coker, 650 S.W.2d at 394 (“When a contract contains an ambiguity, . . . the interpretation of the instrument becomes a fact issue.”) (citing Harris v. Rowe, 593 S.W.2d 303, 306 (Tex. 1980)). 2 satisfaction of that claim.” (Emphasis added). In the provision pertinent here, the agreement then

states:

In consideration for the present agreement of [the Attorneys] to represent [the] Client and the promise to render legal services in the future in pursuit of this claim, [the] Client agrees to sell, transfer, assign and convey to [the Attorneys] an undivided interest in the above claim to be calculated as follows:

Forty percent (40%) of the gross amount recovered Except that Attorneys will not take a fee out of the ownership of 5D Water Resources and Dillon Water Services .... By “GROSS AMOUNT” is meant the total sums recovered.

(Italics added). The agreement later provides that the Client “acknowledges that any proceeds from

this claim are to be paid jointly to Client and Attorneys, and Client hereby agrees to properly

endorse any and all drafts for the purpose of depositing in the trust account of attorneys for

disposition.” (Emphasis added).

The Client argues that by defining “gross amount” as the “total sums recovered,” the

agreement unambiguously provides for a contingency fee based only on a percentage of the

Client’s monetary recovery. Because dictionaries define the word “sum” to mean a quantity of

“money,” and because “[n]o textual support indicates ‘sums’ includes an ‘ownership interest,’”

the Court agrees. Ante at ___ (quoting Sum, BLACK’S LAW DICTIONARY (9th ed. 2009); WEBSTER’S

THIRD NEW INTERNATIONAL DICTIONARY 2289 (1986)). I agree that this is a reasonable

construction. The agreement defines the Attorneys’ contingency interest as a portion of the “total

sums recovered,” and “sums” ordinarily refers to money.

The Attorneys note, however, that the agreement expressly identifies the Client’s “claim

arising out of business dealings with WECO” and grants the Attorneys “an undivided interest” in

that “claim.” The Attorneys argue, and the trial court agreed, that because the agreement grants 3 the Attorneys an interest in the claim and then provides that the Attorneys will not take a “fee”

from the Client’s “ownership of” other companies, the agreement unambiguously entitles the

Attorneys to forty percent of the WECO interests the Client recovered on the claim. I agree that

this is a reasonable construction. The agreement grants the Attorneys an interest in the claim itself,

and if that interest by definition only included an interest in money recovered, the provision that

the Attorneys will not take their “fee” out of ownership interests in 5D and Dillon would have no

meaning or effect at all.

The Court concludes that this construction is unreasonable not only because “sums” refers

to money, but also because attorneys have a duty to draft “clear” fee agreements. Ante at ___

(citing Anglo-Dutch Petroleum Int’l, Inc. v. Greenberg Peden, P.C., 352 S.W.3d 445, 450 (Tex.

2011)). But as the Court acknowledges, that does not mean that an attorney-fee agreement cannot

ever be ambiguous or that “every dispute over the contract’s meaning must be resolved against the

lawyer.” Ante at ___ (quoting Anglo-Dutch, 352 S.W.3d at 451). The Attorneys’ duty to draft a

“clear” agreement merely requires us to construe the agreement by considering how “a reasonable

person in the circumstances of the client would have construed” the agreement. Id. (quoting

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Towers of Texas, Inc. v. J & J SYSTEMS, INC.
834 S.W.2d 1 (Texas Supreme Court, 1992)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Neece v. A. A. A. Realty Co.
322 S.W.2d 597 (Texas Supreme Court, 1959)
Harris v. Rowe
593 S.W.2d 303 (Texas Supreme Court, 1979)
Exxon Corp. v. West Texas Gathering Co.
868 S.W.2d 299 (Texas Supreme Court, 1993)
White v. Moore
760 S.W.2d 242 (Texas Supreme Court, 1988)
Sage Street Associates v. Northdale Construction Co.
863 S.W.2d 438 (Texas Supreme Court, 1993)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Milner v. Milner
361 S.W.3d 615 (Texas Supreme Court, 2012)
Rsui Indemnity Company v. the Lynd Company
466 S.W.3d 113 (Texas Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
in Re Dean Davenport, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-dean-davenport-tex-2017.