In re Danna Homes, Inc.

58 Pa. D. & C.2d 535
CourtPennsylvania Environmental Hearing Board
DecidedMay 31, 1972
Docketdocket no. 72-137
StatusPublished

This text of 58 Pa. D. & C.2d 535 (In re Danna Homes, Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Environmental Hearing Board primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Danna Homes, Inc., 58 Pa. D. & C.2d 535 (Pa. Super. Ct. 1972).

Opinion

ADJUDICATION

MALIN, Chairman,

-This is an appeal from an order of the Department of Environmental Resources dated December 20, 1971, denying permission to appellant to connect a proposed apartment project to the sanitary sewer system in Morton Borough. A hearing in the matter was held before M. Melvin Shralow, Esq., Hearing Examiner, on February 22, 1972. During the hearing, the parties were given leave to supplement the record by submitting materials after the hearing, but no such materials were submitted. The parties waived filing of briefs.

FINDINGS OF FACT

1. Appellant is the owner of a tract containing approximately 1.43 acres in Morton Borough, Delaware County, having acquired the same on December 8, 1970.

2. The sanitary sewer system in Morton Borough feeds into the Central Delaware County Authority (authority) sewage treatment plant.

3. That plant operates under Sewerage Permit No. 7317 issued by the Sanitary Water Board in February, 1950 and discharges its effluent to the Delaware River.

4. The design capacity of the plant is seven million gallons per day (mgd) average daily flow, peak flow 12.5 mgd. The treatment required is removal of 35 percent of the biological oxygen demand (BOD) and of practically all settleable solids. The plant is designed to serve a population of approximately 65,000 people.

5. From data supplied by the authority and tests made by the Pennsylvania Department of Environmental Resources (department), it has been found that the plant is serving approximately 84,000 people, has an average daily flow of 9.1 mgd, and a peak load [537]*537of 14 to 17 mgd. BOD removal is below 35 percent and removal of settleable solids is down to approximately 47 percent.

6. The department issued orders on or about June 25, 1971, to the authority and to each of the municipalities connected to the system prohibiting additional connections to the system which would add to the load on the treatment plant.

7. On January 11, 1971, appellant applied to the Zoning Hearing Board of Morton Borough for a variance to permit the construction of 55 apartments on the site.

8. The Morton Borough Zoning Board hearing was held on February 24, 1971.

9. In March, 1971, the Pennsylvania Department of Labor and Industry approved appellant’s plans.

10. In April, 1971, appellant applied for a building permit from Morton Borough. In making said application, appellant relied upon the fact that more than 45 days had passed from the date of its hearing before the zoning hearing board without action of the board. Appellant argued this constituted approval of its zoning application under section 908 of the Pennsylvania Municipalities Planning Code of July 31, 1968, 53 PS §10908(9). The borough refused to issue a building permit on this basis, and appellant initiated an action in mandamus in the Court of Common Pleas of Delaware County to compel the issuance of the building permit. That action is still pending.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
58 Pa. D. & C.2d 535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-danna-homes-inc-paenvhrbd-1972.