In re Crockett

912 P.2d 176, 259 Kan. 540, 1996 Kan. LEXIS 29
CourtSupreme Court of Kansas
DecidedMarch 8, 1996
DocketNo. 75,207
StatusPublished

This text of 912 P.2d 176 (In re Crockett) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Crockett, 912 P.2d 176, 259 Kan. 540, 1996 Kan. LEXIS 29 (kan 1996).

Opinions

Per Curiam:

This is ah attorney discipline proceeding involving respondent Kenneth F. Crockett, an attorney licensed to practice law in Kansas, whose last registration address-is in Topeka.

The complainants,'Mr.- and Mrs:. Gerald Ashton, had entered into a contract for construction of-a residence with Dean Miller Construction Company: There -were cost , and time overruns'and allegations of poor and unfinished work. The Ashtons met with respondent on October 30,1989, to discuss the construction problems. After additional meetings and telephone calls, the Ashtons retained respondent and paid a $500 retainer on'December 6, 1989.

Respondent wrote a demand letter on December 18, 1989: On January 3,1990, he toured the home with his clients and on January 9, 1990, he toured the home again with his clients and Miller and Miller’s attorney, Greg Lee: In an exchange of letters, the parties attempted to negotiate final repairs and final payments, but this attempt failed.

On February 13,1990, the construction company sued the Ash-tons to foreclose its contractor’s lien and recover $25,500 -still unpaid on the contract. The mortgagor and additional subcontractors were named as additional defendants to require them to assert any claims in the matter. Respondent- filed a timely answer and comy terclaim asserting damages to the Ashtons of $35,000.. Respondent promptly answered plaintiff’s request for discovery and statement of monetary damages. In a letter dated April 4, 1990, Mr. Lee [541]*541suggested arbitration, which was later declined by the Ashtons. On April 16, 1990, a pretrial conference was held before the district judge. At that time a trial date of May 8, 1990, was set if no arbitration was conducted.

The parties appeared for trial on May 8, 1990. At that time, however, the judge took counsel into chambers and announced he had decided to attempt an alternative to trial. With the consent of counsel, a contractor was appointed to be the court’s expert witness. The contractor was to inspect the home and note needed repairs, and Miller would have an opportunity to correct them. Unfortunately, none of this proceeding was recorded by the court or journalized by counsel. The procedure was attempted. Miller performed some of the repairs suggested by the contractor but not others. The Ashtons eventually refused to permit Miller access to their home to make repairs and elected to return to court.

In a December 10, 1990, letter decision, the district judge determined that all issues had been decided and no counterclaim was preserved when the contractor alternative was agreed to by the parties in May 1990. Respondent, without any documentation, disputed this ruling. The court’s decision was journalized by plaintiff’s counsel and filed on January 11, 1991.

Timely notice of appeal was filed by respondent on January 23, 1991, and the appeal was docketed on that date. On February 23, 1991, the Court of Appeals issued a show cause order pointing out that two additional defendants originally sued were not addressed in the decision letter or journal entry. Plaintiff’s counsel prepared a new journal entry of dismissal with prejudice as to those parties. That journal entry was filed with the district court and the Court of Appeals on March 15, 1991.

On March 21, 1991, the Court of Appeals issued a second show cause order, stating the original appeal was prematurely filed and no timely notice of appeal from the March 15, 1991, journal entry had yet been filed. Respondent did not act on this notice. Rather, on April 3, 1991 (mailed March 19, 1991), he responded out of time to the first show cause order (which had been mooted by the March 15,1991, journal entry). On April 16,1991, respondent filed a response to the second show cause order. The certificate of mail[542]*542ing was dated April T2, 1991, but was not received by the Clerk of the Appellate Courts until April 16, 1991. ’

On April 25, 199Í, the Court of Appeals issued a third show cause order, pointing out that the April 16, 1991, response was filed outside the 30-dáy appeal time from the March 15, 1991, journal entry. No response was filed by respondent. On May 20, 1991, the appeal was dismissed for failure to respond to the third show cause order and for untimely filing- of the appeal. The $25,000 construction fund held by the district court was ordered paid to plaintiff Miller Construction.

Respondent never notified his clients of the May 20, 1991, dismissal or that the $25,000 construction fund had been paid to the plaintiff. Rather, he ignored their repeated contacts for the next' 3 years and put them off with vague references to. canceled court dates and “the due process of law.”

.The Ashtons became more persistent in wanting an answer. In March 1994 respondent prepared his own trust account check for $11,844.19 rather than'explaining the dismissal and the. reasons behind it. The Ashtons stated that the.respondent told them the check represented an out-of-court settlement. The check was mailed to .the Ashtons in April 1994, accompanied by a document titled “Disbursement” purporting to be a settlement of the Ash-tons’ counterclaims. Respondent canceled meetings that had been set with the Ashtons, and he failed to return phone calls.

In the fall of 1994 the Ashtons checked with the Clerk of the Appellate Courts to determine .what had occurred and learned their appeal had been dismissed in .1991. They then filed this disciplinary complaint against respondent. The following is a letter dated October 4, 1994, from Gerald Ashton to Bruce E. Miller, Disciplinary Administrator:

“On December 6, 1989 we paid a retainer to Mr. Kénneth Crockett of $500.00 to represent us in a suit against Dean Miller. We were having a new home built and were having trouble with the builder. ,
“On May 8,1990 we went to court on this case. We lost the case and Mr. Crockett filled [sic] an appeal on our behalf.- In January, of. 1991 Mr. Crockett .filed the appeal. The appeal number is 91-66112-A.
[543]*543“On February 7, 1991 we paid into the court the sum of $28,122.67 under case #90-CV-308. We called Mr. Crockett numerous times from January 1991 until after receiving a check from Mr. Crockett in April of 1994. Each time Mr. Crockett told us ‘It was the due process of law’ that was taking so long on the appeal.
“We were told by Mr. Crockett that a court date of September 29, 1993 at 1:30 had been set for our appeal. Mr. Crockett later called and said the court had cancelled the date and he would let us know when it would be rescheduled.
“On October 6, 1993 we contacted Mr. Crockett. On October 9 Mr. Crockett brought Mr. R. L. Olden to check our house for nail pops and to repaint the interior. Mr. Olden estimated this part of the corrections at $2,875.00. We then started calling Mr. Crockett more often to find out what was taking so long. When we were able to reach him he would again say it was the ‘due process of the law.’
‘We called Mr. Crockett on November 9, 1993. On November 30, 1993 Mr. Crockett meet [sic] with us at our home. He told us he was working on getting us a new court date. After not hearing from Mr. Crockett over the holiday we called him on January 20,1994. Mr. Crockett never returned this call so we called him again on January 26, 1994. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Christian
709 P.2d 987 (Supreme Court of Kansas, 1985)
State v. Davitt
671 P.2d 1123 (Supreme Court of Kansas, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
912 P.2d 176, 259 Kan. 540, 1996 Kan. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-crockett-kan-1996.