In Re Contractor Technology, Ltd.

376 B.R. 156, 2007 U.S. Dist. LEXIS 70987, 2007 WL 2818272
CourtDistrict Court, S.D. Texas
DecidedSeptember 25, 2007
Docket7:23-mj-00007
StatusPublished
Cited by1 cases

This text of 376 B.R. 156 (In Re Contractor Technology, Ltd.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Contractor Technology, Ltd., 376 B.R. 156, 2007 U.S. Dist. LEXIS 70987, 2007 WL 2818272 (S.D. Tex. 2007).

Opinion

MEMORANDUM AND ORDER

NANCY F. ATLAS, District Judge.

Appellant Hirschfeld Steel Co., Inc. (“Hirschfeld”) appeals from the United States Bankruptcy Court’s April 16, 2007 Memorandum Opinion (“April Opinion”) and the corresponding June 14, 2007 Final Judgment. Having considered the parties’ submissions, all matters of record, and ap *158 plicable legal authorities, the Court affirms the Bankruptcy Court’s decision.

I. FACTUAL AND PROCEDURAL BACKGROUND

Debtor Contractor Technology, Ltd. (“Contractor Technology”) was the prime contractor on public works projects in Texas, including a road and bridge project referred to as NASA-1. St. Paul Fire and Marine Insurance Company (“St. Paul”) was the surety with whom Contractor Technology executed payment bonds as required by Chapter 2253 of the Texas Government Code (“Payment Bond”). Contractor Technology filed a petition in bankruptcy on May 13, 2005, and the case was converted from Chapter 11 to Chapter 7 in June 2005.

Hirschfeld was a subcontractor on the NASA-1 project, responsible for fabricating structural steel girders. Contractor Technology paid Hirschfeld $268,073.00 on May 12, 2005, but the check did not clear until after the bankruptcy petition was filed. The Bankruptcy Trustee sent a letter to Hirschfeld in September 2005 requesting return of the $268,073.00 as an avoidable post-petition transfer pursuant to 11 U.S.C. § 549.

In February 2006, Hirschfeld and St. Paul entered into a Ratification Agreement whereby St. Paul undertook completion of the NASA-1 project with Hirschfeld continuing to serve as one of the subcontractors. St. Paul agreed to pay Hirschfeld “in accordance to the terms and conditions of the Purchase Order” and the parties agreed as a term of the Ratification Agreement that the amount due was $292,733.40. Upon payment of that specified amount, Hirschfeld released St. Paul from any claims arising against the Payment Bond. 1 At the time the Ratification Agreement was executed, the parties correctly noted that Hirschfeld had been “Paid to Date” $646,721.00, an amount that included the $268,073.00 paid in May 2005.

The Trustee instituted an avoidance action in May 2006. In July 2006, the Bankruptcy Court ordered return of the funds, and in December 2006, Hirschfeld returned the $268,073.00 to the Debtor’s bankruptcy estate.

St. Paul sued Hirschfeld in Texas state court for allegedly refusing to deliver certain specially fabricated steel for the NASA-1 project. The case was removed to the United States Bankruptcy Court on August 14, 2006, Hirschfeld filed an answer and a counterclaim. In its counterclaim, Hirschfeld sought inter alia to recover from St. Paul the amount avoided by the Trustee. The parties filed cross-motions for summary judgment, and the Bankruptcy Court held in St. Paul’s favor. This appeal followed.

II. STANDARD OF REVIEW

The entry of summary judgment by the Bankruptcy Court is reviewed de novo. See In re Ark-La-Tex Timber Co., Inc., 482 F.3d 319, 328 (5th Cir.2007). The reviewing court applies the same standard as the Bankruptcy Court. See id. (citing Gowesky v. Singing River Hosp. Sys., 321 F.3d 503, 507 (5th Cir.2003)). Summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Id.; Fed. R. Civ. P. 56(c). If the non-moving party fails to present evidence on an essential element of that party’s case on which that party has the burden of proof, there can be *159 no genuine issue of material fact. See Mabey v. Dixie Elec. Membership Corp., 2007 WL 2253503, *2 (5th Cir. Aug. 7, 2007) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986)).

III. ANALYSIS

A. The Ratiñcation Agreement 2

It is undisputed that, in Paragraph A of the Ratification Agreement, the parties agreed to a “statement of the Purchase Order account as of January 31, 2006,” including a “Paid to Date” amount of $646,721.00. It is also undisputed that, when the parties entered into the Ratification Agreement, the “Paid to Date” amount was correct even though it included the $268,073.00 that was later subject to the Trustee’s avoidance proceeding. Paragraph A also includes an agreed “Amount Currently Due” of $292,733.40.

The Ratification Agreement provides in Paragraph C that when St. Paul paid “the Amount Currently Due” as set forth above, Hirschfeld “fully and forever releases and discharges St. Paul from any and all claims, suits and actions arising against the Payment Bond for all labor and/or materials furnished to date by” Hirschfeld.

In Paragraph H of the Ratification Agreement, St. Paul agreed to pay Hirsch-feld “in accordance to the terms and conditions of the Purchase Order.” The parties specifically agreed in Paragraph A that the Amount Currently Due under the Purchase Order was $292,733.40.

B. Mutual Mistake

Hirschfeld argues that the Release should not be enforced or should be reformed because it was the result of a mutual mistake. For purposes of contract reformation, the “mutual mistake” must be made after the original agreement in reducing the original agreement to writing. See Wallerstein v. Spirt, 8 S.W.3d 774, 781 (TexApp. — Austin 1999, no pet.). There is no allegation or evidence of a drafting mistake when the parties’ agreement was reduced to writing.

Courts will not enforce an agreement “when parties to an agreement have contracted under a misconception or ignorance of a material fact .... ” Phoenix Network Tech. (Europe) Ltd. v. Neon, 177 S.W.3d 605, 618 (TexApp. — Houston [1st Dist.] 2005) (citing Williams v. dash, 789 S.W.2d 261, 264 (Tex.1990)). “The question of mutual mistake is determined not by self-serving subjective statements of the parties’ intent, ... but rather solely by objective circumstances surrounding” the contract’s execution. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Angles v. Flexible Flyer Liquidating Trust
471 B.R. 182 (N.D. Mississippi, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
376 B.R. 156, 2007 U.S. Dist. LEXIS 70987, 2007 WL 2818272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-contractor-technology-ltd-txsd-2007.