This text of 11 N.E.3d 1197 (In re Comm. Rev. of Capacity Charges of Ohio Power Co.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Comm. Rev. of Capacity Charges of Ohio Power Co., 11 N.E.3d 1197, 139 Ohio St. 3d 1476 (Ohio 2014).

Opinion

Public Utilities Commission, No. 10-2929-EL-UNC. This cause is pending before the court as an appeal from the Public Utilities Commission of Ohio.

Upon consideration of the application of appellanf/eross-appellee, FirstEnergy Solutions Corp., for dismissal of its cross-appeal, it is ordered by the court that the application for dismissal is granted. The cross-appeal of FirstEnergy Solutions Corp. is dismissed, and the case remains pending on all other appeals.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
11 N.E.3d 1197, 139 Ohio St. 3d 1476, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-comm-rev-of-capacity-charges-of-ohio-power-co-ohio-2014.