In re: Brawner Builders

CourtCourt of Special Appeals of Maryland
DecidedMay 29, 2026
Docket1451/24
StatusPublished

This text of In re: Brawner Builders (In re: Brawner Builders) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re: Brawner Builders, (Md. Ct. App. 2026).

Opinion

In the Matter of Brawner Builders, Inc., No. 1451, September Term, 2024, filed May 29, 2026. Opinion by Friedman, J. HEADNOTES: PUBLIC CONTRACTS — COMPENSATION In an underrun scenario, a Variations in Estimated Quantities (VEQ) clause allows the contractor to demand that the government equitably adjust the contract price if the government procures so much less than the parties had expected that it increases the contractor’s actual costs per unit. PUBLIC CONTRACTS — EXTRA COSTS OR EXPENSES IN GENERAL A contractor must satisfy a four-prong test to prove its entitlement to an equitable adjustment under a VEQ clause in an underrun situation: (1) the government purchased less than 75% of the estimated quantity of a contract item; (2) the actual cost per unit of the item that the government purchased exceeds the contract cost per unit; (3) the actual cost per unit of the item that the government purchased is greater than the per unit cost would have been for units purchased absent the underrun; and (4) the underrun is the sole reason that the actual cost per unit increased. Satisfaction of the first prong establishes the underrun. The remaining three prongs together establish that the contractor’s actual costs per unit increased as a result of the underrun. PUBLIC CONTRACTS — EXTRA COSTS OR EXPENSES IN GENERAL Where contractor’s calculation failed to mention contract costs per unit or the cost of units purchased absent an underrun, contractor could not satisfy prongs (2) and (3) of the four-prong test to establish entitlement to an equitable adjustment under the VEQ clause: that its actual costs per unit exceeded these amounts. PUBLIC CONTRACTS — EXTRA COSTS OR EXPENSES IN GENERAL Contractor failed to satisfy prong (4) of the four-prong test to establish an equitable adjustment under the VEQ clause, that the increased actual costs per unit were caused by the underrun, because its increased actual costs were caused by its decision to buy things that were excluded from payment under the contract. Circuit Court for Baltimore County Case No. C-03-CV-23-000136 REPORTED

IN THE APPELLATE COURT

OF MARYLAND

No. 1451

September Term, 2024

______________________________________

IN THE MATTER OF BRAWNER BUILDERS, INC.

______________________________________ Friedman, Shaw, Kehoe, Christopher B. (Senior Judge, Specially Assigned),

JJ. ______________________________________ Opinion by Friedman, J. ______________________________________

Filed: May 29, 2026

Pursuant to the Maryland Uniform Electronic Legal Materials Act (§§ 10-1601 et seq. of the State Government Article) this document is authentic.

2026.05.29 '00'04- 15:01:33 Gregory Hilton, Clerk When the State government enters into a procurement contract, it may provide

estimates of the items that it will purchase from the contractor. If it does, it is required by

law to insert a Variations in Estimated Quantities (VEQ) clause into the contract. The VEQ

clause provides a narrow remedy to a narrow problem: if the government purchases so

much less of an item that the cost per unit increases, the VEQ clause allows the contractor

to demand an equitable adjustment to the contract price for its increased actual costs. This

clause is intended to provide some security for the contractor, not a mechanism to get more

money for a bid that, in hindsight, turns out to have been unwise.

FACTS

Appellee, Brawner Builders, Inc. (Brawner), entered into a procurement contract

with appellant, the State Highway Administration (SHA), to provide labor and equipment,

such as traffic signs and vehicles, for highway maintenance. The contract provided

estimated total quantities and payment for the labor and equipment that SHA expected to

purchase from Brawner throughout the contract’s two-year term. SHA agreed to pay

Brawner only for those quantities that it ultimately purchased from Brawner. SHA would

not pay Brawner for things that Brawner bought and let sit idle.

The contract also included a VEQ clause:

Where the quantity of a pay item in this Contract is an estimated quantity and where the actual quantity of such pay item varies more than 25 percent above or below the estimated quantity stated in this Contract, an equitable adjustment in the Contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 125 percent or below 75 percent of the estimated quantity.1

This VEQ clause allows the contractor to demand an equitable adjustment to the contract

price if the government purchases less than 75% of the estimated contract quantity (an

underrun), thereby increasing the contractor’s actual costs per unit. The same analysis

applies to the government’s demand for an equitable adjustment when it purchases more

than 125% of the estimated contract quantity (an overrun), thereby decreasing the

contractor’s actual costs per unit.

At the end of the two-year term, Brawner invoked the VEQ clause to demand an

equitable adjustment from SHA. Brawner claimed that SHA had purchased less than 75%

of the estimated quantities of various contract items, and that these underruns had increased

Brawner’s actual costs per unit. SHA denied Brawner’s demand. It asserted that Brawner

had not established its claim that its actual costs per unit had increased.

Brawner appealed from SHA’s denial of its demand to the Maryland State Board of

Contract Appeals (MSBCA). Brawner revised the specific amount that it claimed multiple

times, but settled on a claim for $1,806,493.63.2 The MSBCA denied Brawner’s appeal. It

1 Md. Code, State Fin. & Procurement § 13-218(a)(3) requires that procurement contracts include a clause “covering … variations that occur between estimated and actual quantities of work in a procurement contract.” The implementing COMAR regulation provides the required language for the VEQ clause in all “construction contracts that contain estimated quantity items.” COMAR 21.07.02.03. The required language was inserted into the parties’ contract. 2 Brawner also asserted a second and third claim, which are discussed below. The second claim was for $1,784,300.93, which was based on a formula set forth in TPH Indus., Inc., MSBCA No. 2311 (2003). The MSBCA rejected Brawner’s second claim because TPH does not apply to contracts with a VEQ clause. The circuit court affirmed

2 determined that, although Brawner had established that there was an underrun, Brawner

had failed to establish that its actual costs per unit increased as the VEQ clause requires.

Brawner filed a petition for review of the MSBCA’s decision in the Circuit Court

for Baltimore County. The circuit court determined that Brawner established that the

underrun caused its actual costs per unit to increase. The circuit court reversed the decision

of the MSBCA and remanded the case to the MSBCA with instructions to award Brawner

an equitable adjustment. SHA noted this timely appeal.

that part of the MSBCA’s decision. Brawner did not appeal from that ruling, so it is not before us. Brawner asserted yet a third claim after the MSBCA held a hearing on Brawner’s claims. Brawner claimed that because SHA had “self-performed” the contract, the VEQ clause is “set aside” and Brawner is entitled to the unpaid balance of the contract: $2,696,571.65. The MSBCA found that Brawner had failed to establish that SHA “self-performed” Brawner’s obligations. The circuit court reversed that part of the MSBCA’s decision. We reverse the circuit court and reinstate the MSBCA’s determination that Brawner cannot recover under this claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maryland Aviation Administration v. Noland
873 A.2d 1145 (Court of Appeals of Maryland, 2005)
Genstar Stone Paving Products Co. v. State Highway Administration
618 A.2d 256 (Court of Special Appeals of Maryland, 1993)
People's Counsel v. Surina
929 A.2d 899 (Court of Appeals of Maryland, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
In re: Brawner Builders, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-brawner-builders-mdctspecapp-2026.