In Re Appropriation of Easements for Hwy. Purposes Over Property of Forte

231 N.E.2d 498, 12 Ohio App. 2d 173, 41 Ohio Op. 2d 259, 1967 Ohio App. LEXIS 397
CourtOhio Court of Appeals
DecidedNovember 28, 1967
Docket1734
StatusPublished

This text of 231 N.E.2d 498 (In Re Appropriation of Easements for Hwy. Purposes Over Property of Forte) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Appropriation of Easements for Hwy. Purposes Over Property of Forte, 231 N.E.2d 498, 12 Ohio App. 2d 173, 41 Ohio Op. 2d 259, 1967 Ohio App. LEXIS 397 (Ohio Ct. App. 1967).

Opinion

Lynch, J.

Appellants, whose property was appropriated by the State Highway Department, are dissatisfied with the jury verdict and are questioning the procedure followed in the Common Pleas Court. There is no bill of exceptions filed in this case.

The first assignment of error concerns the description of the property contained in the copy of the resolution filed by the Director of Highways, which is as follows:

“The aforementioned property to be appropriated is located in Lot 23, Town 5 North, Range 1 "West, Hartford Township, Trumbull County, Ohio, lying on the left side of the centerline of a survey made by the Department of Highways, and recorded in the records of Trumbull County, Ohio, and being more fully described as follows:
“Parcel No. 181 (Highway)
“Perpetual Easement por Highway Purposes
“Beginning at the owners’ southeast property corner, said corner also being at the intersection of the existing centerline of survey of State Route No. 7 (which is also the line between Lots 17 & 23) and the owners’ southerly property line at Station 622 plus 58.13 in the centerline of survey above referred to; thence westerly along said southerly property line passing through the existing westerly right of way line 30 feet left of Station 622 plus 58.13 to a point 60 feet left of Station 622 plus 58.13 in the proposed westerly right of way line of State Route Nó. 7; thence northwesterly along said right of way line to a point-75 feet left of Station 623 plus 58.13 in the owners’ northerly property line; thence easterly along said northerly property line passing through the aforesaid existing westerly right of way line of State Route No. 7 at a point 30 feet left of Station 623 plus 58.13 to a point at Station 623 plus 58.13 in the aforementioned centerline of survey; thence southerly along said center- *175 line to the point of beginning, containing 0.09 of an acre, more or less, exclusive of the present road which occupies 0.07 of an acre, more or less.”

Appellants contend that this description fails to meet the provisions of Section 5519.01, Eevised Code, requiring “a definite, accurate, and detailed description,” because it is a center line description.

In the instant case, one can not plot the property to be appropriated without reference to the center line survey or the map attached to the resolution and finding. The starting point is definitely located at the southeast corner of the owners’ property, one line goes westerly along the southerly property line for a distance, another line goes for a distance along the owners’ northerly property line, and the amount of property taken is 0.09 of an acre; however, the remaining part of the description is reference to stations that are characteristic of a center line survey and cannot be interpreted without reference to the center line survey or the map attached to the resolution and finding.

Courts have generally indicated their disapproval of the use of a center line description by the State Highway Department in the resolution and finding filed in an appropriation case, but there are some differences in opinion in the cases as to the effect on the jurisdiction of the trial court to hear an appropriation case where the description in the resolution and finding of the State Highway Department is a center line description.

Some courts have held that the description in the resolution and finding must meet the same standards as a metes and bounds description generally used for recording purposes in the transfer of real estate; that a center line description per se does not meet such a standard; and that, therefore, a center line description does not meet the requirements of Section 5519.01, Revised Code. Baughman v. Dir. of Hwys., 5 Ohio App. 2d 171; Appropriation of Easements for Highway Purposes over the Property of Dueber Realty, Inc., 80 Ohio Law Abs. 257.

However, this court has held that the use of a center line description accompanied by a map, that together are adequate enough for the property owner to understand what property is being appropriated, is not per se such a violation of the re *176 quirements of Section 5519.01, Revised Code, as to deny jurisdiction to the trial court, in two unreported Lake County cases, namely, In re Appropriation of Easements over Property of Sopko v. Masheter, Case No. 762, and In re Appropriation of Easement over Property of Basquin, Case No. 696. This is still our position.

Generally, the requirement of the law is fulfilled if the description is such that the landowner is not misled and if its defect may be cured upon demand. 27 American Jurisprudence 2d 275, Eminent Domain, Section 396, and page 278, Section 399.

The legislative grant of the power of eminent domain should be strictly construed, but it should not be technically com strued so as to defeat the purpose of the grant. Covington & Cincinnati Bridge Co. v. Magruder, 63 Ohio St. 455, at page 475.

However, although we disagree with some of the reasoning in the cases of Baughman v. Dir. of Hwys., 5 Ohio App. 2d 171, and Appropriation of Easements for Highway Purposes, 80 Ohio Law Abs. 257, we agree with the results in both these cases for the reason that the property owners in those cases challenged the use of the center line description by a motion prior to the trial of the case.

We agree that a property owner, whose property is being appropriated by the State Highway Department, is entitled pursuant to Section 5519.01, Revised Code, to a metes and bounds description generally used for recording purposes in the transfer of real estate. State, ex rel. Preston, v. Shaver, 172 Ohio St. 111. We further feel that this right is not only based on his being informed as to what land is being appropriated but also as to damage to his title. The property owner acquired title by an instrument of conveyance with a motes and bounds description. When the Director of Highways appropriates a part of this property, we feel that the property owner is entitled to know how his metes and bounds description is changed by the appropriation.

Counsel for the Director of Highways contends that only an easement to the property is appropriated for highway purposes, rather than a fee simple. However, this is a perpetual easement for highway purposes, and the property owner is precluded from the private use of the appropriated property as long as it *177 is used for highway purposes. 27 American Jurisprudence 2d 274, Eminent Domain, Section 39G, states as follows:

“The same certainty and accuracy are essential where an easement, rather than the land itself, is sought. * *

Furthermore, the real estate taxes are reduced in proportion to the part of the real estate appropriated, pursuant to Section 319.201, Revised Code.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Appropriation of Easement for Highway Purposes
132 N.E.2d 247 (Ohio Court of Appeals, 1954)
Baughman v. Director of Highways
214 N.E.2d 843 (Ohio Court of Appeals, 1964)
Thormyer v. Dueber Realty, Inc.
158 N.E.2d 924 (Stark County Court of Common Pleas, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
231 N.E.2d 498, 12 Ohio App. 2d 173, 41 Ohio Op. 2d 259, 1967 Ohio App. LEXIS 397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-appropriation-of-easements-for-hwy-purposes-over-property-of-forte-ohioctapp-1967.