in Re Application of Indiana Michigan Power Co to Reconcile Costs

CourtMichigan Court of Appeals
DecidedNovember 29, 2016
Docket327716
StatusUnpublished

This text of in Re Application of Indiana Michigan Power Co to Reconcile Costs (in Re Application of Indiana Michigan Power Co to Reconcile Costs) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
in Re Application of Indiana Michigan Power Co to Reconcile Costs, (Mich. Ct. App. 2016).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS ___________________________________________

In re Application of INDIANA MICHIGAN POWER COMPANY to Reconcile Costs.

INDIANA MICHIGAN POWER COMPANY, UNPUBLISHED November 29, 2016 Appellant,

v No. 326405 MPSC MICHIGAN PUBLIC SERVICE COMMISSION, LC No. 00-017283

Appellee.

In re Application of INDIANA MICHIGAN POWER COMPANY to Reconcile Costs. _________________________________________

INDIANA MICHIGAN POWER COMPANY,

Petitioner-Appellant,

v No. 327716 MPSC MICHIGAN PUBLIC SERVICE COMMISSION, LC No. 00-017603

Before: RONAYNE KRAUSE, P.J., and O’CONNELL and GLEICHER, JJ.

PER CURIAM.

In these consolidated appeals, appellant Indiana Michigan Power Company (I&M) appeals from orders entered on September 26, 2014, and May 14, 2015, by the Michigan Public Service Commission (PSC) denying I&M’s request to reconcile net lost revenues for the 12- month period ending December 31, 2012, and approving I&M’s request to reconcile its energy optimization revenues and expenses for 2013, respectively. For the reasons discussed below, we

-1- remand these cases for reconsideration in light of Enbridge Energy Ltd P’ship v Upper Peninsula Power Co, 313 Mich App 669; 884 NW2d 581 (2015).

I. BACKGROUND

On January 27, 2010, I&M filed a general rate case application. The application, which was docketed as Case No. U-16180, relied on a 2010 test year, sought a revenue increase of $62.5 million, and included proposals for several rate adjustment mechanisms to track and align costs and rates, including a Net Lost Revenue Recovery Tracker (NLRT). On October 14, 2010, the PSC entered an order approving the parties’ settlement agreement and a rate increase of $35 million. Paragraph 15k of the settlement agreement provided:

The Company requested a pilot Energy Optimization (EO) decoupler that limits recovery to lost sales resulting from I&M’s EO plan approved in U-15808. I&M’s Net Lost Revenues will be recovered through a surcharge mechanism as discussed in the direct testimony of Staff witness Morgan and as modified in the rebuttal testimony of Company witness Roush. When calculating I&M’s Net Lost Revenues for 2011, I&M will use one-half the certified EO savings reflected in I&M’s 2010 sales forecast and one-half of its certified EO savings for 2011. The Company will be authorized to create a regulatory asset for the Net Lost Revenues effective January 1, 2011 to be recovered through the Net Lost Revenue Recovery Surcharge. The Company shall file an annual reconciliation of any over or under recovery of the Net Lost Revenue Recovery Surcharge coincident with Energy Optimization Annual Report/Reconciliation—no later than April 30th of each year. Since EO savings are cumulative, future EO reconciliations should reflect one-half of the certified EO savings for 2010 and 2011.

I&M filed an application in its EO plan reconciliation on April 29, 2011. The application was docketed as Case No. U-16311. I&M requested authority to reconcile its EO plan costs, and also requested that in accordance with the approved Settlement Agreement in Case No. U-16180, it be authorized to recover Net Lost Revenues as reflected in the updated EO billing factors.

While the application in Case No. U-16311 was pending I&M filed a general rate case on July 1, 2011. The rate case was docketed as Case No. U-16801. I&M relied on a 2012 test year and requested a rate increase of $24.5 million, noting that its existing rates were established in the approved Settlement Agreement in Case No. U-16180. I&M sought approval of “proposed changes to its terms and conditions for services as well as its proposed rate adjustment mechanisms.” The application made no specific reference to the NLRT approved in Case No. U- 16180.

The PSC issued an order on January 12, 2012, approving a Settlement Agreement in Case No. U-16311. The Settlement Agreement provided in pertinent part:

The parties agree to defer to I&M’s filing in 2012 all issues concerning I&M’s proposed mechanism to recover lost power supply and distribution revenues, as authorized in paragraph 15.k. of the Settlement Agreement in Case No. U-16180.

-2- On February 15, 2012, the PSC approved a Settlement Agreement in Case No. 16801. The order approved a rate increase for I&M in the amount of $14.6 million. Neither the PSC order nor the parties’ Settlement Agreement made reference to the NLRT approved in Case No. U-16180.

On April 10, 2012, this Court released its decision in In re Application of Detroit Edison Co, 296 Mich App 101; 817 NW2d 630 (2012). In that case, Detroit Edison requested authority to realign electric rates for certain institutional customers and, among other things, to use a revenue decoupling mechanism (RDM).1 The PSC issued an order allowing Detroit Edison to adopt an RDM. This Court reversed this portion of the PSC’s order, holding that pursuant to MCL 460.1089(6), the PSC had authority to approve the use of an RDM for gas utilities, but not electric utilities. Id. at 108-110.

On April 27, 2012, I&M filed an application, docketed as Case No. U-16739, seeking authority to reconcile EO revenues and expenses for 2011, and to recover net lost revenues of $1,137,616. I&M sought to recover the NLT through the implementation of an NLRT, which I&M asserted was both consistent with other NLRTs approved by the PSC and distinguishable from the RDM that the PSC disallowed in In re Application of Detroit Edison Co.

II. FACTS AND PROCEEDINGS IN UNDERLYING CASES

A. Docket No. 326405

On April 30, 2013, I&M filed an application, docketed as Case No. U-17283, requesting that the PSC “commence an Energy Optimization (EO) Plan Cost Reconciliation proceeding for the period ended December 31, 2012 and approve [I&M’s] reconciliation of Certified Net Lost Revenues (CNLR) resulting from the EO plan.” On December 19, 2013, the PSC issued an order approving a partial Settlement Agreement. The Settlement Agreement provided in pertinent part:

4. Subsequent to the prehearing conference, the parties have engaged in audit procedures and settlement discussions and, as a result, have reached agreement on the following issues in this case. The parties to this Partial Settlement Agreement agree as follows:

a. The 2012 payments for electric and gas totaled $4,420,319 to the Independent Energy Optimization Program Administrator satisfy the payment requirements set forth in MCL 460.1091(1).

1 A revenue decoupling mechanism is a “mechanism that adjusts for sales volumes that are above or below the projected levels that were used to determine the revenue requirement authorized in the natural gas provider’s most recent rate case. In determining the symmetrical revenue decoupling true-up mechanism utilized for each provider, the commission shall give deference to the proposed mechanism submitted by the provider.” MCL 460.1089(6).

-3- b. The proposed reconciliation of 2012 Energy Optimization revenues and payments should be approved and results in a net under-recovery of $710,067 (including interest) through December 31, 2012. The total net under-recovery of $903,516 includes $193,449 of the 2011 under-recovery and should be reflected as the beginning balance of I&M’s 2013 Energy Optimization costs and reconciliation.

c. The proposed revised Energy Optimization surcharges incorporated into the tariff sheets attached hereto as Attachment 1 should be approved for bills beginning with the first billing cycle of January 2014 or the first billing cycle in the month following a Commission order.

5. The parties reserve the right to address in briefs all other issues raised by I&M’s testimony and exhibits but not resolved by this Partial Settlement Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Complaint of Rovas Against Sbc
754 N.W.2d 259 (Michigan Supreme Court, 2008)
Associated Truck Lines, Inc. v. Public Service Commission
140 N.W.2d 515 (Michigan Supreme Court, 1966)
Ameritech Michigan v. PSC MICHIGAN PUBLIC SERVICE COMM'N
658 N.W.2d 849 (Michigan Court of Appeals, 2003)
Michigan Consolidated Gas Co. v. Public Service Commission
209 N.W.2d 210 (Michigan Supreme Court, 1973)
Attorney General v. Public Service Commission No 2
602 N.W.2d 225 (Michigan Court of Appeals, 1999)
In Re MCI Telecommunications Complaint
596 N.W.2d 164 (Michigan Supreme Court, 1999)
Michigan Electric Cooperative Ass'n v. Public Service Commission
705 N.W.2d 709 (Michigan Court of Appeals, 2005)
Enbridge Energy Limited Partnership v. Upper Peninsula Power Co
884 N.W.2d 581 (Michigan Court of Appeals, 2015)
Rovas v. SBC Michigan
482 Mich. 90 (Michigan Supreme Court, 2008)
Attorney General v. Public Service Commission
418 N.W.2d 660 (Michigan Court of Appeals, 1987)
In re Detroit Edison Co.
296 Mich. App. 101 (Michigan Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
in Re Application of Indiana Michigan Power Co to Reconcile Costs, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-indiana-michigan-power-co-to-reconcile-costs-michctapp-2016.